66 Neb. 839 | Neb. | 1902
A temporary bridge, costing $95, and afterward a permanent one, costing $2,945, were constructed oyer a stream on a highway on the line between the counties which are parties to this action in 1893, to replace one that had been destroyed by a freshet. The entire cost of these structures was paid by Saline county, the plaintiff, on the 25th day of April, 1894, although the bridge which they replaced had been built and kept in repair at the joint expense of both counties; whether by contract or not does not appear. After paying the cost of erecting the bridges in question, the plaintiff presented a bill to the defendant for one-half thereof, which was allowed by the county board of the defendant, and a warrant drawn for its payment. In due time a taxpayer of the defendant appealed to the district court from the order allowing the claim. In the district court the plaintiff pleaded two causes of action, namely, one for. one-half the cost of the temporary bridge, the other for one-half the cost of the permanent bridge; the former on the theory that the temporary bridge was in the nature of repairs to the one destroyed, the latter on the theory that the defendant was a joint party with the plaintiff to a contract with a third party, under and in pursuance of
The statutory provisions for the construction and repair of bridges over streams on roads on county lines are found in chapter 78 of the Compiled Statutes, of which the following sections alone concern us at this time:
“Sec. 87.* Bridges over streams which divide counties, and bridges over streams on roads on county lines, shall be built and repaired at the equal expense of such counties; Provided, That for the building and maintaining of bridges over streams near county lines, in which both are equally interested, the expense of building and maintaining any such bridges shall be borne equally by both counties.
“Sec. 88. For the purpose of building or keeping in repair such bridge or bridges, it shall be lawful for the county boards of such adjoining counties to enter into joint contracts; and such contracts may be enforced in law or equity, against them jointly, * * * by any parties interested in such bridge or bridges, for any neglect pf duty in reference to such bridge or bridges, or for any damages growing put of such neglect; Provided, That if either of such counties shall refuse to enter into contracts to carry out the provisions of this section, for the repair of any such bridge, it shall be lawful for the other of said counties to enter into such contract for all needful repairs, and recover by suit from the county so in default such proportion of the costs of making such repairs as it ought to pay, not exceeding one-half of the full amount so expended.
“Sec. 89: If the county board of either of such counties, after reasonable notice in writing from the county board of any other such county, shall neglect or refuse to build or repair any such bridge, when any contract or agreement has been made in regard to the same, it shall be lawful for the board so giving notice to build or repair the same, and*842 to recover, by suit, one-half (or such amount as shall have been agreed upon) o£ the expense of so building or repairing such bridge, with costs of suit and interest from the time of the completion thereof, from the county so neglecting or refusing.”
It will be conceded that if the defendant be liable in this case, it is liable by virtue of some of the foregoing provisions, unless it be on the theory of estoppel, which we shall notice presently. McCann v. Otoe County,9 Nebr., 324, 331. Through no fault of counsel, the plaintiff has wholly failed to bring itself within those provisions, in that it has failed to show that the defendant ever entered into any contract for the construction or repair of the bridge, or that it ever refused to enter into a contract for the repairs. The contract for the construction of the permanent bridge was in writing. It was between the plaintiff and a third party exclusively. While the evidence shows that a member of the board of the defendant county was present at a meeting of the board of the plaintiff when the bids for the erection of the bridge were opened and when the contract was let, and that he participated in the proceedings, there is no evidence that he was authorized to act for the defendant in that behalf, if, indeed, such authority to do so could be delegated to one member of the board. The only competent witness called to show that he was thus authorized (the record of the county board is silent on the matte- ) was one who was clerk of the board. His testimony is to the effect that such member was authorized, but whether by the county board, or by some of the individual members thereof, the witness was unable to say. What has been said as to the contract for the permanent bridge is equally true of the other, save that it does not appear that there was any written contract for its construction. If, as claimed by plaintiff, this bridge was in the nature of repairs, still, as to it, the plaintiff must fail, because it does not appear that the defendant ever made or refused to enter into a contract therefor. See sections 88 and 89, supra-
“First — Because of their attempting, at least, to cooperate and contract with Saline county in the building of the bridge.
“Second — Because of their standing by and seeing Saline county expend its money and complete the bridge and then taking possession thereof and grading the approaches thereto, and aiding in keeping the same in repair and fit for public travel.
“Third — Because that after the bridge was completed, accepted and appropriated by Gage county and by every taxpayer as well, the board of supervisors of Gage county duly examined, audited and allowed the bill claimed by Saline county for one-half cost of building the bridge.”
As to the first ground, we think that has been already disposed of. There is no evidence that the defendant ever attempted to participate and contract with the plaintiff in the matter. So far as the record shows, whatever attempt of that kind was made, was made by an individual acting without authority to bind the defendant.
As to the second, we are wholly unable to see that the defendant was under any legal or moral obligation to prevent the plaintiff from expending its money in the construction of the bridge, in pursuance of its own contract with a third party. By grading the approaches to the bridge, it merely put one of its highways in condition for travel. This certainly would not operate as an estoppel.
As to the third ground, it is a mere begging of the question. The order of the county board allowing the claim was in the nature of a judgment. The taxpayer, in the exercise of a statutory right, appealed therefrom. To hold him, or the county, estopped by the order appealed from, would render the statute, granting such right, nugatory.
We are thoroughly satisfied that the judgment of the district court is right and recommend its affirmance.
By the Oourt: For the reasons stated in''the foregoing opinion, the judgment of the district court is
Affirmed.
The following opinion on rehearing was filed December 2, 1903.’ Judgment below reversed:
Commissioner’s opinion, Department No. 1.
This is a rehearing after a decision in the same case found on page 889, ante. The facts are there sufficiently stated, except the circumstance that before the plaintiff county entered into the contract for the building of the bridge in question, it notified the county board of Gage county of its intention so to do, and demanded of it co-operation in so doing, with which demand the board neglected to comply, although, as is shown in the opinion cited, sonje ineffectual attempt at compliance was made. The main
' It is therefore recommended that the former judgment of this court be vacated and set aside, and that the judg-
Bj the Court: For the reasons stated in the foregoing opinion, it is ordered that the former judgment of this court be vacated and set aside, and that the judgment of the district court be reversed and the action dismissed.
REVERSED AND DISMISSED.
Sections 87, 88 and 89 correspond to 6085, 6086 and 6087 of. Cob-bey’s Annotated Statutes.