83 A.D.2d 777 | N.Y. App. Div. | 1981
Order unanimously affirmed, without costs. Memorandum: Petitioner commenced a proceeding in Supreme Court for the acquisition of approximately seven acres of respondents’ land to provide access to a proposed county park. Petitioner already owned 571 acres of the proposed total park area of 680 acres. The petition alleges that the county is exempt from the requirements of article 2 of the Eminent Domain Procedure Law (EDPL) because of the acquisition’s minimal effect on the environment. Respondents deny that allegation in their answer and further allege that petitioner must comply with the notice and public hearing requirements of article 2. In granting the petition, Special Term held that petitioner is exempt from the notice and hearing requirements under EDPL 206 (subd [A]). Preliminarily, we note that respondents’ remedy to contest petitioner’s determination of exemption is not by way of answer in an acquisition proceeding but is pursuant to a proceeding for judicial review