80 Ga. 489 | Ga. | 1888
The question made by the record is, whether, seven years having elapsed after the erection of a bridge, which had been let out to the lowest bidder by the county authorities, no bond having been taken by the latter as required by the statute, the county is liable for damages caused by the defective condition of the bridge.
Judgment reversed.