County of Monroe Ex Rel. Monroe Community Hospital v. KaladjianCounty of Monroe Ex Rel. Monroe Community Hospital v. Kaladjian
OPINION OF THE COURT
The issue in this case is whether the Department of Health’s (DOH) decision to deny petitioner Monroe County’s request, on behalf of its County hospital operation, for additional Medicaid reimbursement due to the difference between petitioner’s estimated electric utility costs for 1983, a rate base year, and actual usage in 1990, wаs arbitrary and capri *188 clous. Concluding that DOH’s determination was not arbitrary and capricious, we reverse the order of the Appellate Division that allowed recovery of such costs.
Petitioner, Monroe Community Hospital (Hospital), is an institution for extended care and treatment of the chronically ill. Under provisions of аrticle 28 of the Public Health Law, acute care hospitals such as petitioner receive reimbursement for services rendered to Medicaid-eligible pаtients
(see,
Public Health Law § 2807 [3]). Pursuant to
When DOH reviewed petitioner’s 1983 costs, petitioner was sharing an electrical meter with three other facilities operated by Mоnroe County. In complying with the regulatory scheme petitioner estimated its share of those costs at 6,929,954 kilowatt hours. In 1990, after petitioner installed a meter to determine its actual electrical usage, petitioner assumed that it had underestimated its usage for 1983 because, according to the meter, its actual kilowatt hours were 8,761,200. Because its electrical costs would, in the future, reflect actual rather than estimated usage, petitioner sought increased reimbursement for 1991.
Petitioner sought this adjustment, however, based on what it referred to as an increase in "the electric usage” due to "[u]pdating and modernizing of electric systems.” DOH recommended denial of petitioner’s request because petitioner had failed to seek prior DOH authorization for "updating and modernizing” of the electric systems, in contravention of the regulatory scheme. The Director of the Bureau of Hospital Reimbursement concluded that the project "resulted from a management decision * * * [and] no authority [exists] in regulation for additional reimbursement in this case, and no adjustment [was] warranted.”
Petitioner requested a hearing as authorized pursuant to
DOH’s rate reviеw officer determined that the governing regulations made "no provision for additional reimbursement due to a change in the method of capturing costs.” Because petitioner’s "appeal and reappeal raise[d] no issues of fact,” the officer denied petitioner’s request for a hearing.
Petitioner then cоmmenced this CPLR article 78 proceeding. Supreme Court annulled DOH’s determination as arbitrary and capricious and remitted the matter to DOH requiring it to redetermine pеtitioner’s reimbursement rate in light of petitioner’s 1990 metered figures. DOH appealed to the Appellate Division and that Court affirmed, with two Justices dissenting. DOH appeals, аs of right, to this Court pursuant to
Here, petitioner argues that the prior courts’ findings are supported by the record and applicable law. Appellant DOH contеnds that the prior courts had no authority to direct it to calculate petitioner’s Medicaid reimbursement based on the 1990 metered figures and that the courts’ determinаtions were not supported by the record and conflict with relevant law.
The appropriate standard of review here is whether DOH’s determination was arbitrary аnd capricious. This settled standard requires the Court to assess whether the action in question was taken "without sound basis in reason and * * * without regard to the facts”
(see, Matter of Pell v Board of Educ.,
We conclude, and agree with the dissenters at the Appellate Division, that DOH’s determination denying petitioner’s reаp-peal was not arbitrary or capricious. As DOH contends, several reasons support its decision to deny petitioner’s request.
Aside from its explanations concerning its revised cost-capturing procedure, petitioner failed to sufficiently allege how its 1983 metered readings of its utility costs contain "error” for purposes of the regulation
(see,
Pursuant to
Additionally, notwithstanding petitioner’s contentions to the contrary, the difference betweеn petitioner’s first and second level appeals consisted of more than a mere "clarification” of the basis of the appeals; petitioner сhanged the substance of the grounds for the relief it sought and its second claim was raised in an untimely manner. At the first appeal, petitioner claimed that the "updating аnd modernizing” of its electric systems caused the increase in its electric usage. At its second stage appeal, petitioner claimed that the increase in its electric costs was due to inaccurate estimates of its 1983 usage. Assuming for the moment that this ground constitutes an "error,” the regulations specify that rates may be аdjusted where errors are "brought to the attention of the commissioner within 120 days of receipt of the commissioner’s initial rate computation sheet”
(see,
Accordingly, the order of the Appellate Division should be reversed, with costs, and the petition dismissed.
Chief Judge Kaye and Judges Simons, Bellacosa, Levine and Ciparick concur; Judge Titone taking no part.
Order reversed, etc.