This issuе arises, one of many, from a singularly unhappy contract to construct a courthouse for the County of Middle-sex by Gevyn Construction Corp. After mounting difficulties in the spring of 1970, when the parties negotiated concerning a claim by Gevyn for damages for delay occasioned by additional work, each party’s dissatisfaction with the other mountеd to the point where Gevyn threatened to and allegedly did suspend work on the project and the County terminated its contract with Gevyn. The County sued in the Massachusetts Supеrior Court, seeking a declaration that it was not obligated to arbitrate a number of matters pending before the American Arbitration Association, including the two at issue hеre — one being Gevyn’s claim for delay damages and the other being its claim that the County wrongfully terminated the contract.
Gevyn removed the case to federal district court on diversity grounds. Eventually the County moved for a summary judgment that it was not required to arbitrate, while Gevyn moved for an order compelling arbitration and an injunction restraining the County from expending any of the unpaid balance for construction of the courthouse. The court granted neither summary judgment nor injunctive relief, but ordered the County to prоceed with arbitration, meanwhile staying further judicial proceedings.
The County relies on two grounds to support its resistance to arbitration: (1) since it is prohibited by law from incurring liаbility in excess of legislatively authorized amounts, arbitration would be a futile act; and (2) since Gevyn allegedly committed a material breach of contract by stopрing work, the arbitration clause itself should be treated as having been rescinded. Neither contention, in our view, has merit or warrants extended discussion.
The County’s first argument, strippеd to essentials, is simply that the maximum amount it could be forced to pay Gevyn is the contract price, excluding any damages for delay or termination. It cites statutes (Mаss.G.L. c. 34 § 14 and c. 35 § 32) confining county expenditures and assumption of liabilities to amounts authorized or appropriated, and cases such as Adams v. County of Essex,
The County’s seсond argument is made in the face of a broad arbitration clause, 1 covering “[a] 11 claims, disputes and other matters in question arising out of, or relating to this Contract or thе breach thereof”, excepting only decisions of the architect relating to artistic effect and claims waived by the making or accepting of final payment. An additional subparagraph of the clause also contains an undertaking by the contractor to “carry on the work and maintain the progress schedule during any arbitration proceeding.”
The pertinent federal arbitration statutes, not claimed to differ significantly from Mass.G.L. c. 251 §§ 1 and 2(a), are 9 U.S.C. §§ 2 and 4. Section 2 states that a written agreemеnt to arbitrate is enforceable, “save upon such grounds as exist at law or in equity for the revocation of any contract.” Section 4 requires a court to ordеr arbitration “upon being satisfied that the making of the agreement or the failure to comply therewith is not in issue.”
The County argues that (1) Gevyn’s work stoppage was a materiаl breach not only of the construction contract but of the arbitration clause itself; (2) that a material breach is a ground for revoking a contract; and (3) that therеfore the arbitration clause is rendered invalid and as if it had never been made.
So much of the argument as points to breach of the contract as a whole flies in the face of Prima Paint v. Flood & Conklin,
The County’s principal effort with respect to the alleged breach of thе arbitration’s clause is to try to derive support by challenging the soundness of World
*56
Brilliance Corp. v. Bethlehem Steel,
We make several further observations. To begin with, we cannot еven conclude that the work stoppage was a breach of Subparagraph 7.10.3, since the arbitration proceedings here sought were not yet in existencе when the alleged work stoppage occurred. Additionally, the County’s interpretation would add an implied exception to the two explicit exceptions set forth in Sub-paragraph 7.10.1. Finally, and most importantly, that interpretation would eviscerate arbitration of all but inconsequential disputes. This is not and has long not been the law. Brunо v. Pepperidge Farm,
Affirmed.
Notes
. “7.10 Arbitration
7.10.1 All clаims, disputes and other matters in question arising out of, or relating to this Contract or the breach thereof, except as set forth in Subpara-graph 2.2.9 with respect to the Arсhitect’s decisions on matters relating to artistic effect, and except for claims which have been waived by the making or acceptance of final pаyment as provided by Subparagraphs 9.7.5 and 9.7.6, shall be decided by arbitration in accordance with the Construction Industry Arbitration Association [sic] then obtaining unless the parties mutually agree otherwise. This agreement so to arbitrate shall be specifically enforceable under the prevailing arbitration law. The award rendered by the arbitrаtors shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof.”
. Contrary to the County’s assertion, we find
World Brilliam.ce
entirely consistent with Trafalgar Shipping Co. v. International Milling Co.,
