153 Minn. 268 | Minn. | 1922
The short facts are these: County Ditch No. 5 was duly established in Brown county, Minnesota, in 1905. It was an inexpensive open ditch, with 5 branch ditches. Two branches were added afterwards. Ten years later defendants, property owners within the territory served by this ditch, petitioned the board of county commissioners to repair, deepen and widen the same. A bond in the penal sum of $1,000, executed by defendants to plaintiff as obligee, accompanied the petition. Thereupon the board appointed an engineer to investigate and report. Later, viewers were appointed. When the reports came in, a public hearing was had and the board dismissed the petition. The county disbursed over $4,000 in publication fees and for the services of the engineer and viewers in the matter. Defendants declined to pay any part thereof, and this action on the bond followed. When the evidence was in, both sides moved for a directed verdict. Defendants’ motion was granted. Thereafter plaintiff moved for judgment notwithstanding the verdict or a new trial. The motion was denied and judgment entered from which plaintiff appeals.
Respondents contend that no bond was required by law, and therefore there is no consideration. Section 5552, Gf. S. 1913, as amended by chapter 300, p. 425, Laws 1915' (G. S. 1917 Supp. § 5552),' does not in terms provide for a petition and bond in a case where it is needful to repair, widen and deepen existing drainage systems. The section in its original form made it the duty of the board of county commissioners to maintain duly established county or judicial drainage systems in the condition originally constructed. . No deepening or widening was provided for. It still provides for maintenance repairs without calling for a petition or bond. But, by the amendment of 1915, repairs are given a broader scope so as to include widening or deepening the original ditches to take care of additional waters thrown therein by subsequent drainage operations.
But we sustain the contention of respondents that the expenses for which a recovery is sought were not incurred for the purpose of repairing, deepening and widening the original ditch, but for the greater part to establish a new drainage system, and that plaintiff failed to prove what part of such expense was properly chargeable to the project petitioned for. The bond recites that petitioners have filed a petition praying for the repairing, deepening and widening of Public Ditch No. 5 of Brown county, heretofore established 'and constructed according to maps, plans and specifications on file. It is conditioned to pay all expenses in case the board of county commissioners “shall fail to establish said proposed repairing, deepening, and widening of said Ditch No. 5.” The petition states that Ditch No. 5, including all its branches, is not of sufficient capacity to carry off the excess of surface water and rainfall, “in the basin it was constructed to drain;” that it “is not deep enough nor wide-enough to carry off such waters and leaves large quantities of water, some places two feet deep on the land which it should drain; that what water it does carry off drains off so slowly as to cause great damage to the crops and renders large quantities of land waterlogged and useless and in a swampy condition.”
The “general description of the proposed starting point, route and terminus of said ditch is as follows: As shown by map and records
No doubt some of the expenses incurred by the county came within the terms of the bond, but there is evidently no way of determining what these were, and no proof was offered to that end.
There was no error in excluding testimony that the surveyor sought and followed the advice of the county attorney. No official
Judgment affirmed.