COUNTY OF BREVARD, Petitioner,
v.
MIORELLI ENGINEERING, INC., et al., Respondents.
Supreme Court of Florida.
*1050 E.A. "Seth" Mills, Jr., Hala A. Sandridge, Jeffrey M. Paskert of Fowler, White, Gillen, Boggs, Villareal and Banker, P.A., Tampa, for Petitioner.
Dana G. Toole, Tampa, Robert A. Hingston, Coral Gables, for Respondent.
GRIMES, Justice.
We have for review County of Brevard v. Miorelli Engineering, Inc.,
On January 5, 1993, Miorelli Engineering Inc. ("MEI") contracted with Brevard County ("County") to design and build a spring training facility for the Florida Marlins. MEI began developing the facility. Subsequently, a dispute arose between the County and MEI. The County terminated the contract and withheld amounts due under the contract. MEI sued the County, asserting a variety of claims including a breach of contract claim seeking damages for extra work it had done on the facility which was beyond that described in the contract.[1] In a motion for partial summary judgment, the County argued that the extra work claim was barred by the doctrine of sovereign immunity because the extra work was outside the terms of the express contract and no written change orders, as required by the contract, had been issued authorizing the extra work. The trial court denied the County's motion as to the extra work claims. The Fifth District Court of Appeal affirmed that portion of the order which denied the motion for summary judgment on the claim for damages for extra work.[2]
The legislature has explicitly waived sovereign immunity in tort for personal injury, wrongful death, and loss or injury of property. See § 768.28, Fla. Stat. (1995). Although no express legislative waiver has been granted for contract claims, this Court in Pan-Am Tobacco Corp. v. Department of Corrections,
We would also emphasize that our holding here is applicable only to suits on express, written contracts into which the state agency has statutory authority to enter.
Id. at 6.
Subsequently, the Second District Court of Appeal held that under Pan Am, sovereign immunity barred a contractor's claim for payment for additional work where that work was not included in the original contract or any subsequent written instrument. Southern Roadbuilders. Later, in Champagne-Webber, Inc. v. City of Fort Lauderdale,
Virtually every contract contains implied covenants and conditions. For example, every contract includes an implied covenant that the parties will perform in good faith. In construction contract law an *1051 owner has (a) an implied obligation not to do anything to hinder or obstruct performance by the other person, Gulf American Land Corporation v. Wain,166 So.2d 763 , 764 (Fla. 3d DCA 1964), (b) an implied obligation not to knowingly delay unreasonably the performance of duties assumed under the contract, Southern Gulf Utilities Inc. v. Boca Ciega Sanitary District,238 So.2d 458 , 459 (Fla. 2d DCA 1970), cert. denied,240 So.2d 813 (Fla.1970), and (c) an implied obligation to furnish information which would not mislead prospective bidders, Jacksonville Port Authority v. Parkhill-Goodloe Co. Inc.,362 So.2d 1009 (Fla. 1st DCA 1978).
... It seems neither logical nor within the principles of fairness enunciated in the Pan-Am Tobacco case to construe the restrictive language of that case to mean that the defense of sovereign immunity is waived only for the state's breach of an express covenant or condition of an express, written contract, but that the defense is not waived for the state's breach of an implied covenant or condition of such contract, while the other contracting party remains liable for a breach of both the express and the implied covenants and conditions.
Champagne-Webber,
While we agree with Champagne-Webber's interpretation of Pan Am, we cannot agree with Champagne-Webber`s further observation that its opinion conflicted with Southern Roadbuilders. Binding the sovereign to the implied covenants of an express contract is quite different from requiring a sovereign to pay for work not contemplated by that contract. See Phillips & Jordan, Inc. v. Department of Transp.,
Contrary to the court below, we conclude that the instant case falls outside the parameters of Champagne-Webber. In Champagne-Webber, the contractor agreed to construct a bridge for the City of Fort Lauderdale. The city represented to the contractor that the soil at the construction site was sand only. Once work commenced, the contractor discovered that the soil contained both sand and rock. Thus, the key issue was whether the city had misrepresented the soil conditions at the construction site and whether the contractor had justifiably relied on the misrepresentation. In the case at bar, MEI's extra work claims are for work totally outside the terms of the contract. Without a written change order, the doctrine of sovereign immunity precludes recovery of the cost of the extra work.
One final point must be addressed. MEI asserts that the County waived the written change order requirement by directing work changes without following its own formalities. We decline to hold that the doctrines of waiver and estoppel can be used to defeat the express terms of the contract. Otherwise, the requirement of Pan Am that there first be an express written contract before there can be a waiver of sovereign immunity would be an empty one. An unscrupulous or careless government employee could alter or waive the terms of the written agreement, thereby leaving the sovereign with potentially unlimited liability.
Accordingly, we approve the rationale of Southern Roadbuilders and Champagne-Webber. We disapprove Interamerican Engineers & Constructors Corp. v. Palm Beach County Housing Authority,
It is so ordered.
OVERTON, HARDING and WELLS, JJ., concur.
ANSTEAD, J., concurs in part and dissents in part with an opinion in which KOGAN, C.J., and SHAW, J., concur.
ANSTEAD, Justice, concurring in part and dissenting in part.
For the reasons expressed below, I conclude that both waiver and estoppel may sometimes be applied against the sovereign, and as a consequence, the majority's opinion, *1052 to the extent it addresses these issues, is flawed. I am most concerned that we are intervening to overturn an order denying a motion for summary judgment at a point in the proceedings when the facts have not been fully developed. We are, in essence, rendering an advisory opinion, largely in a factual vacuum.
The majority opinion holds that the doctrine of sovereign immunity precludes recovery, as a matter of law, of the cost of the contractor's extra work under Pan-Am Tobacco Corp. v. Department of Corrections,
MEI asserts that the County waived the written change order requirement by directing work changes without following its own formalities. We decline to hold that the doctrines of waiver and estoppel can be used to defeat the express terms of the contract. Otherwise, the requirement of Pan Am that there first be an express written contract before there can be a waiver of sovereign immunity would be an empty one. An unscrupulous or careless government employee could alter or waive the terms of the written agreement, thereby leaving the sovereign with potentially unlimited liability.
Majority op. at 1051. Hence, without citation to authority, and with virtually no analysis, the majority holds that the doctrines of waiver and estoppel cannot be applied to the sovereign in any disputes arising out of a contractual relationship.[4] It is interesting to compare appellate opinions and note how quickly the perspective may change with the specific circumstances being considered. For example, compare the majority's language here with that of the First District, in another case involving the application of the doctrines of waiver and estoppel to the government:
If the rule were not as so announced a governmental agency could purposefully fail to comply with some statutory prerequisite to the execution of a contract, avail itself of the benefits of that contract until such time as it arbitrarily and capriciously chose to ignore it, and then do so with no fear that any court could compel it to honor its agreement. It is just such a theory that the City asserts in this case and it is because of such conduct on the part of unscrupulous parties that the doctrine of equitable estoppel has become engrained as a cornerstone of the jurisprudence of a majority of the states of this nation.
Killearn Properties, Inc. v. City of Tallahassee,
Initially, I disagree with the majority's contention that allowing waiver and estoppel *1053 in this situation is somehow incompatible with Pan Am's requirement that an implied waiver of sovereign immunity applies only to "suits on express, written contracts into which the state agency has statutory authority to enter."
Further, this Court has consistently recognized that a contracting party may waive, either orally or by conduct, a stipulation in a construction contract providing that alterations or extra work must be authorized by a written change order. See, e.g., Charlotte Harbor,
In Killearn Properties, the First District, while recognizing that "the doctrine of estoppel is no stranger to the jurisprudence of Florida," quoted an informative passage by the Supreme Court of California on the application of estoppel against the government. The district court wrote:
It is settled that "the doctrine of equitable estoppel may be applied against the government where justice and right require it." Correlative to this general rule, however, is the well-established proposition that an estoppel will not be applied against the government if to do so would effectively nullify "a strong rule of policy, adopted for the benefit of the public." The tension between these twin principles makes up the doctrinal context in which concrete cases are decided.
....
... After a thorough review of the many California decisions in this area, as well as a consideration of various out-of-state decisions, we have concluded that the proper rule governing equitable estoppel against the government is the following: The government may be bound by an equitable estoppel in the same manner as a private party when the elements requisite to such an estoppel against a private party are present and, in the considered view of a court of equity, the injustice which would result from a failure to uphold an estoppel is of sufficient dimension to justify any effect upon public interest or policy which would result from the raising of an estoppel.
In summary, I would approve the Fifth District's opinion and allow this case to proceed past the summary judgment stage. While the government may ultimately prevail, we should not intervene at such an early stage of the proceedings and before the facts have been fully developed. The majority's opinion does not analyze the issues of waiver or estoppel separately, nor does it use the framework this Court has previously developed for analyzing these issues. The majority's justification for its holding, the protection of public funds from negligent or unscrupulous government employees, seems unconvincing when one considers that we have already held that waiver *1055 and estoppel may only be applied in limited circumstances against the government.
KOGAN, C.J., and SHAW, J., concur.
NOTES
Notes
[1] The validity of the remaining claims is not before us.
[2] The Fifth District Court of Appeal accepted jurisdiction of this nonfinal order based on Department of Transportation v. Wallis,
[3] Pan Am held that sovereign immunity from contractual suits is only waived to suits on express written contracts into which the state agency has the authority to enter.
[4] Waiver has been defined as "the intentional relinquishment of a known right." Gilman v. Butzloff,
Estoppel is the doctrine "by which a person may be precluded by his act or conduct, or silence when it is his duty to speak, from asserting a right which he otherwise would have had." Taylor,
[5] Further, the weight of authority from other states also suggests that the government can waive a written change order requirement in public works contracts. Moreover, most states have no bar against suing the sovereign in contract actions. In this regard it has been noted:
While it might be plausibly argued that stipulations in contracts for public work requiring written orders for alterations and extras should be more strictly enforced and that more rigid rules should protect the government against the effect of a waiver of the provisions than are enforced and applied to private contracts, such arguments find little if any direct support in the decided cases. It is established generally that in the absence of a statute, a government or municipality may, when acting through its proper officers or representatives, waive or agree to the modification of a stipulation in public works requiring that alterations and extras be authorized or ordered in writing in order to entitle the contractor to recover additional compensation therefor. Accordingly, it is widely held that the provision in a public building or construction contract that alterations or extras must be ordered in writing can be avoided by the parties to the contract where their words, acts, or conduct would amount to a waiver or modification of such provision, or where the public entity by acts or conduct of its proper officer or representative is estopped to rely on it, although a contrary conclusion has apparently been reached in at least one case involving a contract under seal.
65 Am.Jur.2d Public Works and Contracts § 193 (1972) (citations omitted) (emphasis added). The author of this same treatise explains that:
Although most of the cases recognizing the possibility of a waiver or modification of a stipulation or provision requiring a written order for extras or alterations have not made any general distinction between public contracts and private contracts respecting such a waiver or modification, in some cases it has been explicitly recognized that such a stipulation or provision should be more strictly enforced in public contracts that in private contracts, and that therefore in the case of public contracts more rigid rules should be applied in determining whether such a stipulation or provision has been waived or modified.
Id., § 195 (citations omitted).
[6] See Florida Livestock Bd. v. Gladden,
[7] The Supreme Court of Wisconsin has stated that "[i]t is ... quite well settled that, when the state makes itself a party to an action or to a contract or grant in its proprietary capacity, it is subject to the law of estoppel, as other parties litigant or other contracting parties." Chicago, St. Paul, Minneapolis & Omaha Ry. Co. v. Douglas County,
