*1
Knecht,”
reweigh
not
we do
testimony
findings, did not have owner- Doeden disputed property. in the We
ship interest did not clear- conclude
therefore
ly finding Stubstad did convert err property
Doeden’s
III our resolution of the Because of
[¶ 21] issue, necessary it is not
conversion argument about dam- Doeden’s
address attorney or fees.
ages
TV district court We affirm the
[¶ 22]
judgment. WALLE, VANDE GERALD W. BOHLMAN, S.J.,
C.J., MARY BRUCE MAKING, CAROL
MUEHLEN KAPSNER, DALE V.
RONNING
SANDSTROM, JJ., concur. E. The Honorable BRUCE S.J.,
BOHLMAN, sitting place J., CROTHERS, DANIEL J.
Honorable
disqualified. *3 Hankla, McGee, Dobrovolny, P.
Collin Minot, N.D., for Dobrovolny, Backes & plaintiff appellee. Lillehaug, Maring A. Williams
Duane Office, N.D., Fargo, for defendants Law appellants. SANDSTROM, Justice. (“Nu- Industries, Inc. Balzer, Balzer,
Tec”), Rudy J. Ronald appeal judgment Balzеr James Coughlin awarding amended (“Coughlin”), Company, Inc. Construction costs, for damages, and fees They contract. breach of construction denying their an order appeal from also con- findings. We amended motion for damages court’s award of clude the district is not erroneous and the Coughlin court did used the 24-inch HDPE pipe piercing pulled err veil of and installed an addi- tional 300 feet of iron pipe. Nu-Tec. affirm. ductile We In July sued Nu- I damages Tec for on the basis theories of contract, breach of guarantee, negli- May Coughlin, On as the gence. Coughlin sought compensation for contractor, general entered into a contract installing the cost of the remainder of the City (cid:127)with the of Minot to construct line, 24-inch water it per- the work Underpass Project 16th Railroad Street *4 equipment provided, formed and it and for for approximately Coughlin million. $3.1 acceleration costs incurred. Coughlin also Nu-Tec, accepted a from as a bid subcon- sought pierce corporate the veil of Nu- tractor, to install two replacement 600-foot Tec and hold its personally shareholders project water lines on the for approximate- liable. $99,000. ly plans specifications The and During trial, [¶ 5] bench Nu-Tec authorized the use directional drilling argued the pipe 24-inch became stuck be- install the new water lines with 20-inch cause of unanticipated soil conditions. high-density and 24-inch polyethylene Coughlin presented expert testimony that (“HDPE”) pipe. Although Nu-Tec was to the pipe became stuck because Nu-Tec Coughlin install the pipe, was responsible failed to add water pipe ballast to the and for purchasing pipe and fusing the pull tried to it through ground with together parties’ sections under the stan- under-powered machinery. The district agreement. dard Coughlin subcontract court found the opinion Coughlin’s ex- supplied pipe the HDPE in 50-foot sec- pеrt witness was persuasive more and tions, it single which fused into 600-foot ruled Nu-Tec had breached its subcon- pieces before began Nu-Tec installation. tract Coughlin with failing perform. began [¶ Nu-Tec installing 3] the wa- The $119,675.85 Coughlin awarded 24, ter lines on June 2002. Nu-Tec suc- damages $31,446.15 fees, and in costs and cessfully installed the 20-inch HDPE wa- for a total plus inter- ter line pipe but problems encountered est. The court also ruled it appropri- was while attempting to install the 24-inch pierce ate to Nu-Tec, veil of pipe. On June the 24-inch pipe closely-held family corporation consisting approximately became stuck at one-half of Balzers, of the and held the jointly Balzers way through the pull. During 600-foot liable for judgment. The court denied month, the following Nu-Tec unsuccessful- Nu-Tec’s motion to amend the findings ly attempted to or install extract the 24- judgment. and inch pipe ground. from the Coughlin, ex- [¶ jurisdiction 6] district court had ercising rights its under the subcontract Const, VI, under 8, N.D. § art. agreement, notified Nu-Tec that it was § N.D.C.C. 27-05-06. The appeal of Nu- terminating employment and that Nu- Tec and the is timely Balzers under Tec obligated would to pay be the costs 4(a). N.D.R.App.P. juris- This Court has Coughlin incurred for installing the re- Const, VI, diction under §§ N.D. art. pipe. mainder the 24-inch Coughlin 6, § and N.D.C.C. 28-27-01. completed installation of the 24-inch water II
line with employees its own and equipment using open trench techniques construction and the argue Balzers pipe ductile iron couplers. fusion the district court erred аas matter of law Second, appellants’ impermis- it N.W.2d damages, because awarding recovery attorney is not the same attor appeal a double on sibly granted trial, 24- ney of the them at represented the installation who completing for appeal is limited to new counsel on pipe. inch counsel would have prior same issues that the Balzers ar Nu-Tec and Wiest, E.g., v. able raise. State been installing twice for paid gue Coughlin ¶ 6 2, 812; n. 2001 ND 632 N.W.2d it because received pipe feet of the 300 Greenwood, 738, 743 Klem v. 450 N.W.2d for com City of Minot payment (N.D.1990). Third, this Court does work, it was part pleting raised for the first time address new issues of its full amount damages for the awarded Mining River appeal. E.g., Coal Knife installa completing the expenses for extra 606, Neuberger, v. Co. it have tion, kept amount would (N.D.1991). example, For Robert Re paid work. otherwise ¶ 14, Co., Inc., Inv. 1998 ND Aircraft 32-03-36, § which lying on N.D.C.C. claimed the appellant person can recover “no part, states in in a repair damages for cost of tort amount *5 damages for the breach greater amount by reduced the sal case should have been person could have obligation than the of an and vage engine, propeller, value of an thereof,” performance by the full gained to core. This declined address Court re Coughlin impermissibly they contend for the because a “reduction value issue $27,000 than it would have more ceived trial,” at and salvage sought wаs not perform Nu-Tec’s full through received “ that were questions not consider ‘[w]e do ance of the contract. and that presented not to the trial court the Balzers and ” [¶ 9] appeal.’ time on are raised for the first expressly acknowledge issue was not this Bender, ND (quoting Id. Messer v. 1997 court in the district any point raised at ¶ 291). 103, 10, The situation 564 N.W.2d damages contend “the but proceedings, other no different. As with this case is very by parties both framed ‘battle’ was trial, objections during a issues that аrise duty court had a to and the general terms” in the district must be raised damages to proper law on the correctly apply appellate to issues for preserve court those ar damages to the facts and measure of review. damages calculation. at a correct rive at- reject appellants’ We persuasive, not because argument This is the first time this issue for tempt to raise well-established it conflicts with several it. decline to addrеss appeal First, their appellate review. principles judges that district court argument implies correct arrive at obligated to Ill regardless input damages amount of argue the Balzers Nu-Tec and However, parties. objections by the to erroneously failed off- the district “engage who “are not ferrets”
judges
for the value
damages by
set the
record for evi
unassisted searches
They claim
pipe.
24-inch
the unused
position.”
litigant’s
support
to
dence
dam-
duty mitigate
to
Coughlin, under its
¶
Noack,
2007 ND
v.
State
pipe.
the unused
ages, should have sold
Moreover,
not review
we do
N.W.2d
by the
injured
“A
novo,
person
but
apply
de
damages
issue
duty
has
wrongful acts
another
of review.
clearly
standard
erroneous
¶
damages and
Boeder,
or minimize the
mitigate
2007 ND
v.
E.g., Hanson
‘protect
must
himself if he can do so with
selling that pipe?
you
Could
have sold
at trifling
reasonable exertion or
expense,
that pipe to
city, county,
another
or
can
delinquent
recover from the
party
may
someone who
have needed 300 or
not,
such
he
only
damages as
could
of plastic
350 feet
pipe?
”
effort,
Boeder,
reasonable
have avoided.’
A I seriously doubt
I could’ve
¶20, 8,
2007 ND
However, president the of Coughlin testi proposed [T]he “fixes” outlined in the fied the pipe could not be used on the preceding paragraph were never offi- project and had no value: cially to anyone communicated in au-
Q. [I]s there a market or thority was there a Coughlin at by anyone in author- market pipe for that to ity be sold to at be Nu-Tec. There may well have HDPE, used pipe as water or high pres- been some informal discussions about pipe, sure after it had been togeth- fused possibility the doing of things, these but er and then cut off and then it up cut does appear not that these discussions again? any resulted in proposals from definite Coughlin.... However, A. It to extremely would have been even hard (2) if these two “fixes” pipe sell that had been legitimately in the mar- official- ly to Coughlin, I communicated in ketplace. would’ve had to a time- tell the manner, ly persuaded truth that it cut Court is had been not and refused— that either of then, that was them obvious. And would have been the fact “the answer” problem. that to this had been stretched and there were some concerns about that. And it both As John and Alan Estvold fairly up by scratched the time it (the Field Engineer on project) this gotten had out yard. to the bone out, pointed there would have been little Q. your upon experience Based in the or no roоm for Nu-Tec to have drilled business, construction was there value entirely an new hole. Nu-Tec would
873
exist,’
in reality
do
and ‘there
at least three
holder
not
to have moved over
have
hole,
inequitable
if
in
(3)
existing
must be an
result
the acts
west of the
feet to the
underground
question
corpo-
are treated as those of the
with the number of
”).
in
immedi-
ration alone.’
already
place
facilities
re-drill, there
proposed
of
ate area
factors to be con
20] Thе
(3)
extra three
feet
just wasn’t an
whether
sidered when
court determines
to accommodate a new
soil
undisturbed
pierce
corporate
veil are set forth
hole.
Skwarok,
v.
Hilzendager
335 N.W.2d
pipe be pulled
As
that
suggestion
Klemm,
(N.D.1983),
Jablonsky
up” with
and “married
from the north
(N.D.1985).
Hilzendager,
In
N.W.2d
ground,
stuck
pipe
which was
at
we
said:
Haugen, John
testimony
Duane
significant
considered
deter-
[F]actors
Alan
Hugh
Coughlin,
O’Donnell
disregard
or not to
mining whether
this
Estvold convinces
Court
corporate entity includе:
insufficient
difficult,
extremely
would have been an
capitalization
of the
purposes
for the
process
time-consuming
expensive
corporate undertaking,
failure
ob-
only marginal chance of
which offered
formalities,
corporate
nonpayment
serve
success.
dividends, insolvency
of the debtor
findings
court’s
The district
at
corporation
the time of the transac-
Cough-
clearly erroneous and establish
not
question, siphoning
tion in
funds
mitigate
damages.
not fаil to
lin did
shareholder,
nonfunction-
dominant
directors,
ing
other
ab-
conclude
court’s award
officers
[¶ 17] We
records,
and the exis-
damages
erroneous.
sence
corporation
merely
as
tence
dealings.
facade for individual
Victoria
IV
Co.,
Co. v. Meriden
Elevator
Grain
argue
and the Balzers
(Minn.1979).
the law in
misapplied
district
*7
564,
veil.
we add-
corporate
Jablonsky,
Nu-Tec’s
In
377 N.W.2d at
piercing
injustice, inequity
that “an element of
ed
Although
the officers
present
must
or fundamental unfаirness
be
corporation generally
are not
directors of
may
the
properly pierce
before
ordinary
corpora
of a
hable for the
debts
corporate veil.”
Chillemi,
tion,
2007 ND
Axtmann v.
Intercept Corp.,
In
¶ 12,
corporate
the
veil
740 N.W.2d
¶
(cita
180, 15, 741
2007 ND
entity
legal
may
pierced when the
be
omitted),
explained:
tions
we
convenience, justify
public
used to defeat
establishing
of
the neces-
fraud,
In
The burden
protect
or defend crime.
wrong,
Fin.,
corporаte
LLC,
sary
piercing
for
elements
Corp. v. Calima
tercept
¶
asserting the
180, 15,
209;
party
on the
see also
veil rests
ND
heavily
Hoot, Inc.,
Resolving
claim.
the issue is
Inc. v.
Wings,
Red River
(citation
¶
and, therefore, is within the
fact-specific
tion Nu-Tec’s Board taken of Directors which the claim arises a consensu ¶ $60,000.00 authorizing transaction, Axtmann, distribution of 14; the al see at Jab 2003, likely one of the worst lonsky, dividends 1, 377 at n. underсapi- N.W.2d years company experi- the ever revenue talization a remains relevant factor in a court found enced.” The that “Nu-Tec is contract case. See Fontana v. TLD Build (and been) appears always has it alter ers, Inc., 491, Ill.App.3d 298 Ill.Dec. ego of Balzer” because Ronald there was (2005). 840 N.E.2d 779-80 It is any no that “hint other shareholders difficult imagine to how can be predi error actively running were involved in th[e] on cated a court’s placing emphasis undue company.” Finally, the court found “it any on single factor it when has found all unfair, unjust would be inequitable piercing nine factors favor corporate allow shareholders hide Nu-Tec’s be- veil. hind corporate shield avoid re- argue [¶29] and the Balzers sponsibility payment any judgment despite that the district court’s detailed against entered this case.” findings, merely the court erred it because Contrary assertions inability focused on the of Nu-Tec to satis- Balzers, of Nu-Tec and the the district fy judgment when it was In entered. findings supported by court’s the evi ¶ Axtmann, 179, 16, 2007 ND Although dence. Nu-Tec and the Balzers 838, a majority upheld of this Court siphoning corpo contend there was no pierce district court’s decision to the cor- attempt
rate funds to attribute the porate veil when the district court found precipitous decline in the financial condi three factors supported piercing and the tion of Nu-Tec to “bad luck” with other corporation “was insolvent and could not jobs Florida, undertaken in the district pay its debts at the time the Axtmanns’ court find explanations did not these credi years and for several before The credibility ble. district court decides judgment.” The same is true here. trial, issues in a bench and we will not findings district court’s de- credibility appeal. reassess B.J. Kadr pict a dominant corpora- shareholder a mas, Inc., LLG, v. Oxbow Energy, who, through tion the issuance of dividends ¶ 7, 270. N.W.2d and bonuses and the repayment of undocu- disagree with [¶ We also con- “loans,” mented attempted to bleed the that the district misapplied tention corporation of assets so would not be Nu-Tech and argue law. the Balzers to satisfy able corporate liability. known placed the court emphasis undue on insuf- We conclude the district court’s decision to capitalization, ficient because Nu-Tec was pierce is veil adequately capitalized when it entered into erroneous. agreement subcontract work, performed and because this V than contract rather a tort action. [¶ 31] The judgment, judg- amended However, is a continuing obligation there ment, and order are affirmed. provide adequate risk capital from in- corporation throughout corporation’s ¶ Axtmann,
existence. 2007 ND WALLE, 32] GERALD W. VANDE 838; Jablonsky, C.J., BOHLMAN, S.J., 377 N.W.2d at BRUCE E. DALE Furthermore, although undercapital- SANDSTROM, V. and CAROL significant ization is less KAPSNER, contract case RONNING JJ. *10 BRUCE E. Honorable S.J.,
BOHLMAN, sitting place of
MAKING, J., disqualified. Justice,
CROTHERS, concurring spe-
cially. results this agree with the I sup of the rationale and most
case separately I write
porting these results. this my disagreement with
to reiterate “undercapitaliza application
Court’s pierc veil analysis
tion” used Chillemi, See Axtmann v.
ing cases. (Croth ¶¶ 40-41,
ND
ers, part concurring however, Here, overwhelming evi
part). corpo Nu-Tec’s supports piercing
dence factors, remaining veil under the
rate undercapitalization of its
any consideration superfluous. Daniel Crothers J. individually ONGSTAD, and as
Astrid Family Trust, Ongstad
Trustee of and all of themselves behalf similarly situated, Plaintiffs
others Appellants CO., & Defendant
PIPER JAFFRAY Appellee.
No. 20070260.
Supreme Court of North Dakota.
Sept.
