38 Ct. Cl. 536 | Ct. Cl. | 1903
delivered the opinion of the court.
By contract of the parties, executed March 2, 1899, plaintiffs undertook to provide, furnish, and deliver at their own risk and expense, at the harbor of Honolulu, Hawaiian islands, beginning and within thirty days from the date of the contract, all the necessary materials and labor, tools, and appliances for the construction and completion, in all respects, of two wharves, and to complete the same in twelve calendar months from the date of the signing the contract, in strict accordance with, and subject to, all the conditions and requirements of the plans and specifications appended to and made a part of the contract, for the sum of $49,900.
Previous to the making of the contract notice or request for proposals for the wharves referred to in the contract, and the excavation of slips for same, had been issued by the Bureau of Equipment, Navy Department, Washington, such proposals to be based upon the plans and specifications which are now attached to the contract. The contract for the dredging was separately let to Buckman & Campbell, and because the wharves could not be built until the dredging was sufficiently advanced to enable the work to proceed, nothing could be clone within thirty days, as provided in the contract, and this time limit was disregarded -by the parties, and the time for the completion of the work was from time to time extended, and the wharves were not finished until December, 1900, a delay of more than eight months beyond the time stipulated, caused, as it is contended, bj^ the.fault of the dredging contractors in failing to do that work in time, and for which the defendants’ officers under the terms of the contract with the dredgers penalized them for such delay in the sum of $16,150.
Petitioners completed the work required of them by the contract and were paid in full by the defendant without prejudice to the claims for which thejr seek to recover in the present suit, which latter, as described in the petition, consist of damages on account of delays and interruptions due to the failure of the defendants to complete the necessary dredging and other preliminary work, in consequence of which they were compelled “to retain their machinery idle, and employees unemployed at Honolulu, all at a loss, for a great part of
As regards the item of waling, the specifications require it, but it is not disputed it was directed to be omitted by the officer in charge, and was not estimated by petitioners in their bid for the work, but by some inadvertence the specification was left unchanged in that respect, and the wale was put on by plaintiffs’ workmen because of the neglect of information that it was to be omitted. This item, therefore, resulted from petitioners’ own inattention, and for such reason they can not recover.
The item for the expense of additional sheathing is based upon the fourth specification, entitled “Dredging,’’ which provides that the whole area of each slip bounded by the lines shown on the plan shall be dredged to a depth of 28 feet below mean low water. The sides of the dredged area shall be finished vertical if the material will stand. In measuring-quantity, excavation below 28.5 feet and 'beyond slopes of 4 vertical to 1 horizontal will be deducted and not paid for. It
That there -was delay in the dredge work that prevented plaintiffs from completing the wharves is beyond dispute. That it was unreasonable delay by the dredge contractors is evidenced by the fact that the defendant deducted from their pay upon the contract $16,150. That plaintiffs were not at fault in the delay of the completion of the wharves is evidenced by the fact that defendant extended from time to time
The measure of the damages to plaintiffs should be the actual and direct loss to them occasioned by the delay, as near as it- can be ascertained, not remote or speculative damages that would not have been anticipated by the parties upon the happening of the events that caused the dela,y. Without discussing the various elements in plaintiffs’ contention, composing these damages, we think it is a sufficient statement of the proper rule to be applied that the plaintiffs are entitled to receive the value of the services of their employees and machinery during the time of the delay in the business in which they were then engaged, diminished by compensation actually received by them for other services performed during the same period. It is not without difficulty that this amount can, from the evidence, be ascertained. We have, however, the basis of the petition to start with, which gives ninety-four working days for the period of ioss for idle machinery and unemployed employees. Upon the whole evidence this number of days is, we think, clearly proved. In the cross-examination of one of the claimants he fixed the value of the