Costle v. Pacific Legal FoundationCostle v. Pacific Legal Foundation
delivered the opinion of the Court.
This case, in a sense, is a tale of a great city’s — and the Nation’s — basic problems in disposing of human waste. “How” and “where” are the ultimate questions, and they are intertwined. The issues presently before the Court, however, center in the administrative processes by which the city and the Nation seek to resolve those basic problems.
I
Respondent city of Los Angeles owns and operates the Hyperion Wastewater Treatment Plant located in Playa Del Rey, Cal. Since 1960, the Hyperion plant has processed most of the city’s sewage, and has discharged the wastes through three “outfalls” extending into the Pacific Ocean. The shortest outfall terminates about one mile from the coastline in 50 feet of water. It is operative only during emergencies caused by increased sewage flow during wet weather or by power failures at the pumping plant. The second outfall terminates about five miles out. Approximately 340 million gallons of treated wastewater are discharged every day into the ocean, at a depth of 187 feet, through that outfall. This wastewater receives at least “primary treatment,”
1
but about
The Hyperion plant is operated under permits issued by the Environmental Protection Agency (EPA) and the California Regional Water Quality Control Board (CRWQCB). Such permits are issued pursuant to the National Pollutant Discharge Elimination System (NPDES), established by § 402 of the Federal Water Pollution Control Act (FWPCA), as added by the Federal Water Pollution Control Act Amendments of 1972, 86 Stat. 880, and as amended,
As one means of reaching that goal, Congress in § 301 (a) of the FWPCA provided: “Except as in compliance with this section and sections 302, 306, 307, 318, 402, and 404 of this Act [
The EPA has promulgated regulations providing for notice and public participation in any permit proceeding under the NPDES. Those regulations, implementing the statutory requirement that any NPDES permit be issued “after opportunity for public hearing,” are the focus of this case. The regulations state: “Public notice of the proposed issuance, denial or modification of every permit or denial shall be circulated in a manner designed to inform interested and. potentially interested persons of the discharge and of the proposed determination to issue, deny, or modify a permit for the discharge.”
Following the issuance of public notice the EPA Regional
Any interested person, within 10 days following the date of the determination, may request an “adjudicatory hearing” or a “legal decision” with respect to the determination. § 125.36 (b). A request for an adjudicatory hearing is to be granted by the Regional Administrator if the request “[s]ets forth material issues of fact relevant to the questions of whether a permit should be issued, denied or modified.” § 125.36 (c) (1) (ii). Issues of law, on the other hand, are not to be considered at an adjudicatory hearing. If a request for an adjudicatory hearing raises a legal issue, that issue is to be referred by the hearing officer to the EPA’s Assistant Administrator for Enforcement and the General Counsel for resolution. If a request for an adjudicatory hearing raises only legal issues, a hearing will not be granted and the Regional Administrator will refer those issues to the aforementioned officers. § 125.36 (m).
Ill
The EPA and the CRWQCB first issued a joint permit to the city of Los Angeles for discharges of. treated sewage
In July 1976, the EPA notified Los Angeles that its 1975 NPDES permit would expire on February 1, 1977, and that a new permit would be needed if discharges were to continue beyond that date. Record 44. The city filed an application for a new permit on July 30.
Id.,
at 45-80. Thereafter, in September 1976, the CRWQCB suggested to the EPA that the city’s current permit might be extended for six months to take into account any effect of pending federal legislation that would modify the FWPCA’s mandatory compliance dates
On June 10, 1977, the PLF filed a Freedom of Information Act request with the regional enforcement division of the EPA, seeking information concerning the proposed extension of the expiration date of the Hyperion permit and, specifically, whether that extension had been approved.
Id.,
at 157. When informed by telephone on June 13 that the EPA’s final determination had been made on June 2, and that a request for an adjudicatory hearing*could be accepted only if filed that day, see
“1. Whether the requirements of the permit should be modified in that the project that is the subject of the compliance schedule set forth in NPDES permit CA010991 ■ [the Hyperion permit] is being evaluated in an EIS by the EPA pursuant to the requirements of NEPA, the compliance schedule should not be mandated in an NPDES permit until the NEPA study is completed; and
“2. Whether the procedures used and the record developed were adequate [for the] issuance of an NPDES permit.” App. 160.
Within 10 days of receiving Kilroy’s request, the Regional Administrator responded by certified mail, stating his determination that the request did not set forth material issues of fact relevant to the question whether the permit should be extended. Thus, he concluded that Kilroy’s request had not met the requirements of
The Court of Appeals remanded the matter to the Administrator for the holding of a “proper hearing.”
“The fact that no one requested a hearing prior to the decision is appropriately considered in this analysis, but it is not decisive. It must be shown that the material facts supporting the decision are not subject to dispute.” 586 F. 2d, at 658-659 (footnotes omitted).
On the record before it, the Court of Appeals concluded that “the reasonableness of the EPA’s compliance schedule [incorporated within the Hyperion NPDES permit] depends upon facts that may be disputed and with respect to which the record in this case is silent.”
The Administrator of the EPA petitioned .this Court for review of the question whether § 402 (a)(1) requires the EPA to conduct an adjudicatory hearing before taking action on an NPDES permit issuance or modification where, after notice of the proposed action, no one requested a hearing before the action was taken and the only request filed subsequently raised no material issue of fact.
11
We granted certiorari to review this important issue in a rapidly developing area of the law.
y
A
Petitioner’s basic contentions are that the EPA was entitled to condition the availability of a public hearing on the extension of the Hyperion permit on the filing of a proper request, and that it similarly was entitled to condition an adjudicatory hearing following its extension decision on the identification of a disputed issue of material fact by an interested party. We agree with both contentions.
Initially, we must state our disagreement with respondents’ characterization of the holding of the Court of Appeals. They argue that the court’s decision was based on a finding that the EPA in this case did not comply with its own regulations governing public participation in the NPDES permit issuance process, rather than on a legal conclusion that the regulations
Moreover, it is important to note that the regulations described in Part II of this opinion,
supra,
were designed to implement the statutory command that permits be issued “after
opportunity
for public hearing.” § 402 (a)(1), 86 Stat. 880,
Neither can we ignore the fact that under the standard applied by the Court of Appeals, the EPA would be required to hold hearings on most of the actions it takes with respect to NPDES permit issuances and modifications. Hearings would be required even in cases, such as this, in which the proposed action only extends a permit’s expiration date without at all affecting the substantive conditions that had been considered during earlier hearings. The Administrator advises us that each year the EPA grants about 100 requests for adjudicatory hearings under the NPDES program, issues about 2,200 permits, and takes thousands of actions with respect to permits. Brief for Petitioner 34-35; see
United States Steel Corp.
v.
Train,
We recognize the validity of respondents’ contention that the. legislative history of the FWPCA indicates a strong congressional desire that the public have input in decisions concerning the elimination of water pollution. The FWPCA itself recites:
“Public participation in the development, revision, and enforcement of any regulation, standard, effluent limitation, plan, or program established by the Administrator .. . under this Act shall be provided for, encouraged, and assisted by the Administrator.” § 101 (e), 86 Stat. 817,33 U. S. C. § 1251 (e) .
Nonetheless, we conclude that the regulations the EPA has promulgated to implement this congressional policy are fully consistent with the legislative purpose, and are valid. Respondents, in fact, do not contest seriously the proposition that the EPA’s regulations are valid on their face; the thrust of their arguments before this Court has been that the EPA, in this instance, failed to apply its regulations consistently with their purpose.
B
Having rejected the Court of Appeals’ invalidation of the EPA’s public participation regulations, we turn to the issues framed by respondents. First, PLF and Kilroy contend that the EPA’s regulations required the Regional Administrator to hold a public hearing in this case because there was a “significant degree of public interest” in the extension of the Hyperion permit. See
“Where the opportunity for public hearing is called for in the Act, and in other appropriate instances, a public hearing shall be held if the hearing official finds significant public interest (including the filing of requests orpetitions for such hearing) or pertinent information to be gained. Instances of doubt should be resolved in favor of holding the hearing, or if necessary, of providing alternative opportunity for public participation.” 40 CFR § 105.7 (c) .
Notwithstanding the orientation of these regulations toward the encouragement of public participation in the NPDES permit issuance process, our examination of the record leads us to reject respondents’ contention that the EPA failed to comply with .its regulations in this case. It is undisputed that the most controversial aspects of the Hyperion permit — the compliance schedule for secondary treatment, the “sludge-out” requirement, and the resultant requirement that the city develop an alternative method of sludge disposal — were all included within the 1975 permit. That permit was issued following EPA publication of advance notice of its tentative determination to revise the initial 1974 permit, and a hearing on the proposed revisions. None of the respondents objected to the issuance of the 1975 permit or requested an adjudicatory hearing. We agree with the position advanced by petitioner that respondents may not reopen consideration of substantive conditions contained within the 1975 permit through hearing requests relating to a proposed permit modification that did not even purport to affect those conditions.
The EPA’s determination to modify the 1975 permit by extending its expiration date to December 17, 1979, was made following newspaper publication of the proposed action, including notice of an opportunity for submission of comments and hearing requests. Respondent Los Angeles received an individual notice of the EPA’s tentative determination to extend the permit, and raised no objection. Respondents PLF and Kilroy, whq argue that the EPA was aware of their interest in the Hyperion permit and their opposition to the Interim Sludge Disposal Project, could have received such individual notice if they had asked to be placed on the EPA’s
Second, respondents suggest that the EPA’s provision of notice to the general public concerning the proposed permit extension was inadequate. The PLF and Kilroy argue that notice by newspaper publication was not adequate to apprise interested parties of the EPA’s tentative determination, and was inconsistent with the policy of encouraging public participation that underlies the statute and regulations. Based on our conclusion that the EPA’s regulations implementing the rather amorphous “opportunity for public hearing” requirement of § 402 are valid, we have no hesitancy in concluding that the form of notice provided in this case, fully consistent with the regulations, was not inadequate.
Los Angeles argues that it was not given adequate notice of the proposed extension of its permit because it was never informed that the EPA regarded the federal “sludge-out” compliance schedule contained in the 1975 permit not to have been modified by subsequent orders of the CRWQCB. See n. 6,
supra.
This argument was not addressed directly by the Court of Appeals. It would be appropriate, therefore, for this Court not to attempt to resolve it here, even if we had an adequate record to do so. More fundamentally, however, an additional reason dictates that the city’s argument not be resolved in the context of this lawsuit at all. Los Angeles claims that the more lenient sludge-out schedule adopted by
The enforcement action seeks to enjoin the city from violating the conditions of its permit and to impose civil penalties against the city for past failures to comply with the permit’s schedules. App. 181. It has been stayed by the Court of Appeals pending the outcome of this case. Brief for Petitioner 17, n. 13. The argument that the city raises here concerning its understanding of the compliance schedules will be resolved far more effectively in the Government’s enforcement action than in the adjudicatory hearing the Court of Appeals would have awarded respondents in this case. 13 Furthermore, even if the city had raised its argument in a public hearing on the proposed permit extension, that argument would have had little relevance to the EPA’s final determination because the EPA’s proposed action did not purport to change the substantive conditions that are the focus of the city’s complaint.
Finally, respondents suggest that the EPA erred in not holding an adjudicatory hearing on the issues raised in respondent Kilroy’s request. We agree with petitioner, however, who contends that Kilroy’s request raised legal, rather
C
In sum, we hold that the Court of Appeals erred in concluding that the EPA is required to hold a public hearing on every NPDES permit action it takes unless it can show that the material facts supporting its action “are not subject to
It is so ordered.
Notes
Under applicable regulations, the Environmental Protection Agency defines “primary treatment” as “the first stage in wastewater treatment where substantially all floating or settleable solids, are removed by floatation and/or sedimentation.”
The agency by its regulations describes “secondary treatment” as that treatment which will attain “the minimum level of effluent quality . . . in terms of . . . parameters [sic].” These so-called “parameters” (but compare any dictionary’s definition of this term) are specified levels of biochemical oxygen demand, suspended solids, and pH values.
In March 1973, the EPA and the California State Water Resources Control Board entered into an understanding that gave the State primary responsibility for administering the NPDES program in California, with the.EPA retaining jurisdiction over discharges beyond the limits of the territorial sea, that is, more than three miles out from the coastline. EPA permits are thus required for the Hyperion plant’s discharges through the 5- and 7-mile outfalls. The CRWQCB, acting pursuant to California's Porter-Cologne Act,
A general description of the original Federal-Water Pollution Control Act passed in 1948, 62 Stat. 1155, the events that led to the 1972 Amendment, and the operation of the NPDES program, with particular emphasis on its implementation in California, is set forth in
EPA
v.
State Water Resources Control Board,
Although the EPA has taken the position in this litigation that § 301 (b)(1)(B) required the city to end the Hyperion plant’s discharge of sludge into the ocean by July 1, 1977, the compliance schedule incorporated in the 1975 NPDES permit required the city to achieve total “sludge-out” by April 1978. The EPA asserts that this less stringent compliance schedule was necessitated by the practical inability of Los Angeles to meet the FWPCA’s requirements. Reply Brief for Petitioner 8, n. 5. Congress subsequently has acted to permit the operator of a publicly owned treatment works, in certain circumstances, to request the
The EPA’s public participation regulations were modified after the events central to this case took place. 44 Fed. Reg. 32854 (1979). Many features of the regulations that are at issue here, however, have been retained. See
On December 1, 1975, the CRWQCB issued an order modifying the city’s compliance schedule for alternative sludge disposal. That order announced that “concept approval” had been given on October 1, 1975, and fixed definite dates for achieving the elimination of sludge discharge into the ocean. Total "sludge-out” was to be achieved by April 1, 1978. App. 51. In subsequent orders, the CRWQCB found that the city had failed to meet several deadlines for the submission of plans and specifications for various phases of the sludge discharge elimination project. The CRWQCB then modified the relevant compliance dates, and extended the deadline for total “sludge-out” to April 1, 1980. Id., at 57. The city has taken the position in this litigation that the CRWQCB’s extension of the deadline for total “sludge-out” has been incorporated within the compliance schedule of the Hyperion plant’s federal permit as well. See injra, at 218-219.
In the meantime, a significant public controversy had developed concerning the EPA’s approval of the city’s alternative sludge disposal project. That project, to be funded by construction grants awarded under Title II of the FWPCA, 86 Stat. 833,
The PLF then attempted, unsuccessfully, to prevent the EPA from funding the Interim Sludge Disposal Project without preparing an EIS on its decision to do so. See
Pacific Legal Foundation
v.
Quarles,
Still another PLF lawsuit relating to the Hyperion permit and its “sludge-out” schedule is pending. In that action the PLF has sued officials of the EPA and the Department of the Interior claiming that those agencies have failed to carry out their statutory obligations under the Endangered Species Act of 1973, 87 Stat. 884,
We, of course, express no view on the merits of these related PLF challenges to the Hyperion permit’s compliance schédules.
The Administrator of the EPA has the authority to issue NPDES permits “for fixed terms not exceeding five years.” §§ 402 (a)(3), (b)(1)(B), 86 Stat. 880, 881,
The following were the issues of law certified by the Regional Administrator to the General Counsel:
“1. Must EPA conduct an informal public hearing prior to taking action to extend the expiration date of an NPDES permit where public notice of the proposed action was published more than 30 days in advance of the action?
“2. Must a detailed factual record be developed prior to modification of an NPDES permit where the only modification made to the permit is the extension of the permit’s expiration date?
“3. May the expiration date of an NPDES permit be extended where a project covered by the compliance schedule is being evaluated by EPAin an Environmental Impact Statement for the purpose of determining whether a grant should be made to assist in the construction of the project?” App. 168.
Following the parties’ presentation of written briefs on these and related issues, the General Counsel ruled against respondent Kilroy. She concluded that the EPA has the authority to extend the expiration date of an NPDES permit through modification, and that an opportunity for a public hearing on such a modification must be provided. A hearing is to be held, however, only if the Regional Administrator finds a significant degree of public interest in the proposed modification. The General Counsel refrained from addressing the second certified issue because Kilroy’s brief did not challenge specifically the adequacy of the record supporting the permit modification. Finally, she ruled that the EPA has the authority to extend the expiration date of a permit requiring the implementation of a project, even though funding for that project is undergoing evaluation in an EIS. The General Counsel relied on the District Court’s decision in Pacific Legal Foundation v. Quarles, see n. 7, supra, as support for the latter ruling. App. 194.
The Court of Appeals in December 1977 stayed the compliance schedules incorporated within the Hyperion plant’s NPDES permit pend
Respondents PLF and Kilroy suggest that the writ of certiorari should be dismissed as having been improvidently granted because petitioner has inserted issues in his brief on the merits that were not included within the question presented in his petition for certiorari. We decline the invitation to dismiss the writ. We note, however, that a decision in this case does not require us to resolve petitioner’s contention, challenged by respondents as a “new issue,” that Congress did not intend adjudicatory hearings under § 402 of the FWPCA to be governed by the formal requirements of an adjudication “on the record” set forth in the Administrative Procedure Act,
To the extent the Court of Appeals’ holding to the contrary relied upon the decision in
Independent Bankers Asm.
v.
Board of Governors,
170 U. S. App. D. C. 278,
The Court of Appeals’ stay of the compliance schedules incorporated within the 1975 permit did not remove the basis for the Government’s enforcement action. That action challenges several alleged violations of the Hyperion NPDES permit that predated January 1, 1977. App. 183-187. See n. 10, supra.
Respondents’ litigation strategy throughout the proceedings culminating in this opinion seems to have been based, at least in part, on a fear that the EPA may evade further public scrutiny of the compliance schedules incorporated within the 1975 NPDES permit by issuing continued extensions of that permit rather than acting upon the city’s application for a new permit. See
supra,
at 205-206. If that potential for evasion ever did exist, it was a limited one. Under § 402 (b) (1) (B) of the FWPCA, the EPA could have set the expiration date for the initial 1975 permit as late as August 1980, and the agency actions that culminated in this lawsuit would have been unnecessary. Now that the outside date for extensions of the 1975 permit is approaching, any additional extension for purposes of avoiding further hearings on the permit’s compliance schedules would have little practical impact. We note, as well, that Los Angeles, under the Administrative Procedure Act,