This is аn action between a contractor and a homeowner. The contractor, Costa and Sons Construction Company, Inc., alleges the homeowners, Paula аnd Lonnie Long, owe money to the company for renovations to their home. The Longs deny the allegations and counterclaim for damages as a result of poor construction by Costa. The case was heard by the court without a jury. The trial judge rendered a judgment in favor of Costa and against the Longs. They appeal. We affirm.
I.
Morrow Costa, a principal in Costa and Sons Construction Company, and the Longs were friends. Lonnie Long is an architect. He and his wife had previously purchased houses аnd renovated them for resale purposes. The Longs purchased a house in Charleston County and approached Costa for assistance in estimating the cost of renovations. They originally planned to do the renovations themselves. Costa gave the Longs an estimate of $55,464 based upon plans prepared by Long. Costa testified the estimate of labor, and materials was not a formal bid by his company but was an effort on his part to assist friends in determining the cost of planned renova
The trial judge awarded Costa judgment of $23,330.10. Costa testified and introduced an exhibit which utilized the original estimate and calculated amounts for extras and сredits to arrive at a figure Costa claimed was still owed. Costa included in his calculation a figure for overhead. Mr. Long denied any agreement on overhead. The trial judge held the parties had not agreed to include overhead and therefore deleted this amount from Costa’s claim to arrive at the award.
The Longs argue the triаl court erred in interpreting the evidence regarding their agreement with Costa. Costa testified the agreement was his company would be compensated for material and labor to perform the work. He also testified the Longs agreed to compensate him for “overhead.” The Longs contend they had a lump sum contract with Cоsta for $55,464. They agreed Costa would be reasonably compensated for changes to the original plans but they contend many of the extras claimed by Costa werе or should have been included in the original estimate. They also claim Costa did not give them proper credit for changes in the plans which constituted deductions from thе original contract.
From the trial judge’s cursory order it appears he concluded there was no meeting of the minds as to an express contract. He then prоceeded to find an implied in law or quasi-contract. He inferentially determined that the reasonable value of the work performed by Costa was $81,830.10 (i.e. the $58,500 already received by Costa plus $23,330.10 awarded in the trial court’s order).
It appears to us the long and short of these parties’ contentions as to the vаlue of the labor and materials furnished by Costa involves a question of credibility of the witnesses and the weighing of other evidence. The trial judge believed Costa’s evidencе over that of the Longs. We recognize that in an equity case we may make our own findings of fact based on the preponderance of the evidence.
1
As a рractical matter, however, we are impotent to determine questions of credibility and must defer to the good judgment of the trial court who heard and observed the witnesses.
Buffkin v. Strickland,
As pertains to the counterclaim, we affirm the trial court. We note again that like their defense to Costa’s complaint, the Longs base their counterclaim on a breach of an express agreement between the parties. Thе efficacy of their claim wanes with the unappealed finding that there was no express
II.
The Longs also appeal the denial of their post-trial motion. They filed a motion under S.C. Rule of Civil Procedure 59 asserting the court should set aside the judgment because Costa and Sons Construction Company was not a licensed general contractor nor a licensed residential homebuilder. Under
S.C. Code Ann.
§ 40-59-130 (Rev. 1986), an unliсensed residential homebuilder may not bring an action to enforce the provisions of a contract.
Wagner v. Graham,
The Longs did not plead lack of a license in their answer. The issue was not raised during the trial. The Longs argue application of the statute related to subject matter jurisdiction which can be raised at any time. We disagree. Thе court of common pleas has subject matter jurisdiction over quasi-contractual disputes. The statutory prohibition is in the nature of an affirmative defense precluding enforcement of the contract which should be pled by a homeowner. Rule 8(c), SCRCP. The Longs seem to argue the lack of a license was newly discovered evidence after trial. The trial court found a lack of diligence by the Longs. The transcript of the motion hearing indicates the Longs received information by letter from the Licensing Board. It does not indicate when the Longs requested the information. We affirm the trial court’s denial of the motion on this basis. There is no
Finally, we agree with the trial judge thаt maintenance of a general contractor’s license by Morrow Costa, who testified he owned Costa and Sons Construction Co., Inc., is sufficient compliance with S.C. Code Ann. § 40-59-140 (Rev. 1986). This section exempts any person licensed as a general contractor from the requirements of the residential home builders statutes.
The decision of the trial court is affirmed.
Notes
Implied in law or quasi-contrаcts are not considered contracts at all, but are akin to restitution which permits recovery of that amount the defendant has been benefited at the expense of the plaintiff in order to preclude unjust enrichment.
Ellis v. Smith Grading and Paving, Inc.,
