88 N.J.L. 324 | N.J. | 1915
The opinion of the court was delivered by
A building contract entered into between Luigi Coppola, contractor, and Sebastiano Grande, owner, plaintiff and defendant, respectively, in the court below, contained a clause, as follows: “Should the contractor, at any time during the progress of said work, refuse or neglect to supply a sufficiency of materials and workmen, the owner shall have power to provide materials and workmen after three days’ notice, in writing, being given, to finish the said works, and the expense shall be deducted from the amount of the contract.”
This clause was put into operation before the building was completed by such notice being given by the defendant to the plaintiff.
The contract was for $6,634. At the time the notice was given, and ihe defendant undertook to finish /the contract, the defendant had paid to the plaintiff, on the contract, $3,100. Stop-notices to the amount of $2,466.52 had been served upon the plaintiff by the subcontractor.
The plaintiff brought his action to recover from the defendant the difference remaining between the amount paid him by the defendant on the contract, plus the expense the defendant was put to in completing the building and the contract price of $6,634.
Before the cause was ordered on for trial counsel for defendant moved the court that the claimants under the stop-notices be admitted as parties to the action, which motion was refused, and this refusal is alleged as error and is one of the grounds of appeal relied on by the appellant.
In whatever aspect the ease may be viewed, it is apparent that the claimants under the stop-notices were not necessary parties.
And while on this topic, though out of the chronological order in which the grounds of appeal are presented, it will, however, be germane to the matter discussed to consider here the insistence of counsel for appellant that it was error for the trial judge to refuse to permit the defendant to be credited with the amount of certain stop-notices to the extent of $2,466 served upon him by the subcontractor. The trial judge instructed the jury that as it did not appear that the defendant had paid anything on the stop-notices he was not entitled to any credit.
This declaration of the legal rule is fully supported by the reasoning of that eminent jurist, Vice Chancellor Van Fleet, in Wightman v. Brenner, 26 N. J. Eq. 489. On page 493, the learned Vice Chancellor said: “The owner’s right to deductions, or allowances, by tire statute, is restricted to payments. Until actual payment, or something which in law is equivalent, no allowance can be made. Notice creates a right against both owner and contractor, but does not constitute a payment or operate as a credit.”
This view was substantially adopted by this court in Carlisle v. Knapp, 51 N. J. L. 330, 331.
Another ground urged for reversal of the judgment is that the trial judge improperly excluded testimony offered by the defendant tending to establish the sums of money for which two contractors offered to perform the work required for the completion of tire contract.. The testimony offered was in the nature of two paper’s showing other bids higher than the one accepted by the defendant fox the completion of the work
A further ground of attack upon the validity of the judgment, advanced by counsel for appellant, is that the court improperly excluded a record of the East Orange .District Court of a proceeding between the plaintiff and defendant relating to the same subject-matter in controversy and wherein it appeared by the pleadings that the plaintiff had made a statement after he had ceased work under the contract, as to what it would cost to complete the contract. At the time the testimony was offered, counsel for defendant stated its purport to he to prove an admission made by the plaintiff as to what it would cost to complete the contract. The. record shows that the offer of this testimony was objected to by plaintiff’s counsel and that the objection was sustained by Ihe court.
And it further appears that counsel for defendant made no objection to the ruling of the court, and, therefore, under Kargman v. Carlo, 85 N. J. L. 632, there is no legal question before us to consider. See, also, Miller v. Delaware River Transportation Co., Id. 700.
Counsel for the appellant next argues that the court erroneously charged the jury that if there was anything included in Hie finishing of the contract not contemplated by the plans and specifications to he completed by the plaintiff that should not he included. We perceive no error in this. Eor it must, be borne in. mind that the owner’s right under the contract was to finish the work left undone under the contract and to deduct the expense from the contract price. The owner was not entitled to build a larger or different building, or in any manner add to the work as mapped out and described by the plans and specifications.
An exception was taken by counsel for appellants, to that part of the court’s charge wherein the court instructed the jury as follows: “So, that if .you should find that this would be tlie reasonable cost of the completion of this building according to the plans and specifications, and that tlie plaintiff’ was wrongfully deprived of the opportunity to complete his
Counsel for appellant, at the time when the attention of the trial judge was called to that part of the charge by the exception then taken, conceded that taking the plaintiff’s figures as the basis of the calculation made, tire result arrived at* by the trial judge was correct, but the appellant made the further claim that it appeared in the testimony of the case that the plaintiff had omitted work which was required by the contract to be done, and therefore the verdict could in no event be as large as that.
It is obvious from what the trial judge said preceding that part of his charge excepted to by appellant, that the exception is unsubstantial. The trial judge was directing the attention of the jury to what the plaintiff claimed, as disclosed by the testimony introduced by him, and instructed the jury, in substance, that if the plaintiff’s version was accepted as representing the truth of the case, a finding to the effect indicated in the excepted portion of his charge should result under the contract.
Another ground urged for reversal, by counsel for appellant, 'is that tire court erroneously charged the jury as follows: “I can see no difference in your consideration of the case whether you find that plaintiff was wrongfully or rightfully excluded from this building.”
Keeping in mind that the ease was tried by the parties to the litigation, as disclosed by the record, upon the theory that the 'plaintiff was entitled to recover the contract price, less payments made and less the costs of completion, it was, therefore, of no consequence whether or not the plaintiff was rightfully or wrongfully excluded from finishing the work, since the breach if committed by tire plaintiff by force of the contract subjected him only to have the expense incurred by the owner in the completion of the contract deducted from the contract price. And furthermore, the defendant did not terminate the contract, but, on the contrary, he upheld it and
Judgment will be affirmed, with costs.
For affirmance—The Chancellor, Chiee Justice, Garrison, Sivayze, Trenchard, Parker, Bergen, Minturn, Kalisch, Black, Vredenburgh, Terliune, IIeppbnheimer, Williams, Taylor, JJ. 15.
For reversal—None.