Cooley v. Snake River Imp. Co.

152 P. 1190 | Or. | 1915

Me. Justice Buenett

delivered the opinion of the court.

The defendant argues that the question of faulty construction was not involved in the Idaho suit, and that it is privileged to litigate that question in counter*387claim against the plaintiff’s demand for extra work. On the other hand, the plaintiff urges that his right to receive the bonds depended upon his showing completion of the undertaking according to its terms; that the defendant was bound to put in all grounds of its opposition to their delivery in the interpleader suit; and that, having alleged damages for failure to finish the plant in the time required, it cannot now allege another element of injury, namely, the imperfect condition in which the system was left. In other words, the plaintiff argues that the defendant had no right to split its cause of defense in the interpleader suit, and pleads the decree of the Idaho court in that proceeding as an estoppel against the present contention of the district.

1. It is true that a party is bound by a judgment on all questions which were actually litigated or might have been determined in the proceeding; but this proves, if anything, too much for the position of the plaintiff here.

2. Estoppels by judgment to be effective must be mutual: Furgeson v. Jones, 17 Or. 204 (20 Pac. 842, 11 Am. St. Rep. 808, 3 L. R. A. 620); Gordon v. San Diego, 101 Cal. 522 (36 Pac. 18); Freeman v. Thayer, 29 Me. 369; Alexander v. Walter, 8 Gill (Md.), 239 (50 Am. Dec. 688); Blackwood v. Van Vleit, 30 Mich. 118; Hempstead v. Easton, 33 Mo. 142; Gardner v. Sharp, 4 Wash. C. C. 609, 9 Fed. Cas. No. 5236.

3. It is disclosed by the contract pleaded by the plaintiff in the reply as follows:

“Article III. No alteration shall be made in the work except upon the written order of the engineer; the amount to be paid by the district or allowed to the contractor by virtue of such alteration to be stated in such order. Should any alteration increase the cost of *388construction or in materials, the same shall Be treated as materials and force work, and to he furnished hy the contractor at actual cost plus ten per centum profit to the contractor. ■ Should the district and the contractor not agree as to the amount to he paid or allowed, the work shall go under the order above required, and in case of failure to agree, the determinations of all of said amounts shall be referred to arbitration as hereinafter provided.”

In the same instrument Article VIII reads thus:

“It is mutually understood and agreed that the sum to be paid by the district to the contractor for said work, materials and removal of fences shall he forty-two thousand five hundred dollars, payable in lawful money of the United States, or, at the option of the district, in its coupon bonds heretofore authorized and issued, hearing date May 1, 1912, in denominations of five hundred dollars each, bearing interest at the rate of six per centum per annum, payable semi-annually as evidenced hy coupons attached thereto; it being distinctly understood however that all coupons of said bonds due and payable to the first day of May, 1913, are to be detached from said bonds and by the district retained and properly canceled, subject to additions or deductions as hereinbefore provided, and that such sum shall he paid by the district to the contractor, either in such money or bonds, at the option of the district, and only upon the certificate of the engineer, as follows. # # ”

Other details in this subdivision refer to the times of payment and discharge of liens which are not important here.

4. It thus appears that it was optional with the district to pay its obligation with its bonds,- and that the coupons payable May 1,1913, were to be retained subject to the additions or deductions otherwise provided in the contract. The proper construction of this provision is to make those coupons a fund applicable to *389the payment of extra work. In the Idaho snit the effort of the plaintiff was to obtain possession of the bonds as payment for his services. It was as obligatory npon him to do the extra work provided in Article III, as to perform any other condition of the agreement, and, so far as his right to the bonds depended npon performance of his engagements, it was necessary for him to urge his whole contention in that proceeding. He conld no more split his cause of suit there than the defendant could split its cause of defense. By the very token that he would prevent th,e defendant from urging a different ground of damages he himself is forbidden to plead an additional cause of action which he might have stated, if his theory is true, in the Idaho suit. If it was necessary for the defendant to state all its claims for damages in that suit or to be precluded here from relying on one not there mentioned, for the same reason the plaintiff ought to be held to have alleged all his cause of suit in Idaho. His answer in the interpleader suit, which appears in the record as one of his exhibits in this proceeding, specifically excludes any claim for extra work done under his contract. If it was incumbent upon him to allege the performance of the work originally required in order to obtain the bonds, it was equally obligatory upon him to aver what was otherwise directed by the engineer to be performed under the provisions of Article II. His complaint here amounts to a waiver of the estoppel. In other words, he attempts to open the case for the purpose of recovering for extra work, and he cannot complain if the defendant is also allowed to reopen it to put in its defense against his claim here alleged. He here demands money in face of the option of the defendant to pay in bonds. He cannot spring this new demand without *390letting in any defense which was proper in the beginning. This action is tantamount to setting the estoppel at large, and his plea of the Idaho proceeding is a departure from the theory advanced in his complaint. It was consequently error under the state of the record to refuse the defendant the privilege of showing the faulty construction of t'he work involved in the contract.

For these reasons, the judgment of the Circuit Court is reversed and the cause remanded for further proceedings.

Reversed. Rehearing Denied.