1 N.Y.S. 498 | N.Y. Sup. Ct. | 1888
This was a proceeding instituted by the plaintiff to foreclose a mechanic’s lien, filed on December 19, 1884, against the property of the appellant. It appears that on the 31st day of March, 1884, the defendant Florus F. Dieffenbacher entered into an agreement with the defendant the Odd Fellows’ Fraternal Union of the City of Bochester to erec* and furnish all the carpenter, joiner, and other work, in accordance with drawings, details, etc., of a five-story annex to the building known as the “ Odd Fellows’ Fraternal
The first question which it becomes necessary to determine is whether or not the stipulated damages for the non-performance of the contract within the time stipulated were embraced in the contract as one of the subjects to be determined by the arbitrators. The language, as we have seen, is that, in case dispute arises as to the true value of the alterations, deviations, additions, or omissions in the work or material contracted for, it shall be determined by the arbitrators, etc. The language used in this clause is identical with that used in the former paragraph of the agreement in which it is provided that the Odd Fellows’ Fraternal Union shall have the right and privilege, at any time during the progress of the building, “to make any alterations, deviations, additions, or omissions in the work or materials. ” The matter thus agreed to
A large mass of evidence was taken upon the subject of delays in completing the work. The referee has found as a fact that there were 90 days’ delay in the entire completion of the work, 50 of which arose from the acts or default of Dieffenbaeher or the plaintiff. This finding is severely criticised by the appellant, and it is claimed that the delay was greater than that found. But this finding cannot be very material if the referee is correct in his conclusion that the -appellant had waived any claim for damages by reason of the non-completion of the work within the time specified in the contract. This conclusion is based upon the facts, which were also found by the referee, to the effect that the delay was occasioned, in part, by the plaintiff not furnishing the materials needed as the work progressed, in part by alterations and additions made by the owner and contractor, and in part by delay on the part of other contractors having in charge work other than carpenter work; that,
Barker, P. J., and Bradley and Dwight, JJ„ concurred.