53 Wis. 250 | Wis. | 1881
[EDITORS' NOTE: THE PUBLICATION STATUS OF THIS OPINION IS GOVERNED BY WIS. STAT. RULE
CONTRACTS. (1) House destroyed while in process of construction: whoseloss? (2) Measure of contractor's damages. (3) Contract construed as totime when payment was due.
REVERSAL OF JUDGMENT: (4) For improper compulsory reference.
1. Where there was not an absolute and indivisible contract to build a complete house for a specified sum, but only a contract to do a part of the work and furnish a part of the materials, the remainder to be otherwise provided for, from time to time, by the land-owner (although the price was a fixed aggregate sum, and no payment was to be made until after the house was completed), and the part built was destroyed by fire before the completion of the whole, and was not restored by the land-owner: Held, that the contractor might recover for work and materials actually done and furnished by him — especially where the land-owner had treated the house as his own, by procuring insurance thereon and receiving the insurance money.
2. The measure of the contractor's damages in such a case is primafacie a pro rata share of the contract price.
3. Under an agreement to pay a certain sum on the completion of work, and the remainder of the price within sixty days thereafter, without interest, a further provision that, if such remainder is not paid within six months after the work is completed, a specified rate of interest shall be paid thereon, does not prevent the debt from falling due at the end of the sixty days.
4. Where the trial court, upon the undisputed evidence, might have directed a verdict for the respondent for the full amount awarded him by the judgment, the fact that a reference for trial was improperly ordered without appellant's consent, is not ground of reversal. *251 Neither party offered to furnish materials, and rebuild and restore the portions of the building destroyed by the fire. On the contrary, each insisted upon the other suffering the loss. A large number of cases are cited in support of the proposition that in case of an entire and indivis ible contract for the building of a house for a specified sum, to be paid on its completion, and where the edifice is destroyed by fire during the progress of the work, the builder must bear the loss and be to the expense of repairing the damages. The principle underlying the proposition contended for, to a certain extent, is undoubtedly correct.
In Brecknock Canal Co. v. Pritchard, 6 Durnf. East., 750, the bridge which the contractor agreed to build was broken down by an extraordinary flood, and KENYON, O. J., said: "If the defendants had chosen to except any loss of any kind, it should have been introduced into the contract by way of exception." So it was held, on the authority of Lord Chief Justice HALE, that "the lessee of a house, who covenants generally to repair, is bound to rebuild it if it be burned by an accidental fire."Bullock v. Dommitt, id., 650. See Walton v. Waterhouse, 2 Saunders, 420; S. C., 3 Keble, 40; 2 Williams' Notes to Saunders' R., 826; McKenzie v. McLeod, 10 Bing., 385; Phillips v. Stevens,
Such cases are distinguishable from one where the contractor agrees to repair another's house already built, and it burns before completion of the repairs. Lord v. Wheeler, 1 Gray, 282; Wells v. Calnan,
But the case at bar is not one of an entire contract to complete an entire building. It is more like Brumby v. Smith,
The opinion in that case is based upon Cutter v. Powell, 6 Durnf. East, 320, and Menetone v. Athawes, 3 Burr., 1592. In Cutter v.Powell the sailor was to be paid the sum named, "provided he proceed, continue, and do his duty on board for the voyage;" and that case, in the language of ALLEN, J., in Wolfe v. Howes,
In Niblo v. Binsse, 3 Abb. N. Y. Ct. Ap. Dec., 375 (S. C., 1 Keyes, 476), it was held that, "if the owner of a building contracts for labor upon it, he is under an implied obligation to have the building ready and in a condition to receive the labor contracted for; and if, before the work is completed, the building is destroyed by fire, without the fault of the contractor, the owner is in default, and the contractor can recover for all that was done up to the time of the fire." In that case, as well as this, the time of performance had been extended by the mutual assent of the parties to the contract. Schwartz v. Saunders,
In Rawson v. Clark,
Hollis v. Chapman,
Taylor v. Caldwell, 3 Best Smith, 826, was a case of destruction by fire of a music hall engaged for concerts, and it was held that both parties were thereby excused from performance, because the general rule requiring absolute performance "is only applicable when the contract is positive and absolute, and not subject to any condition, either express or implied." It was there also held that, "where, from the nature of the contract, it appears that the parties must from the beginning have known that it could not be fulfilled, unless, when the time for the fulfillment of the contract arrived, some particular specified thing continued to exist, so that, when entering into the contract, they must have contemplated such continuing existence as the foundation of what was to be done, there, in the absence of any express or implied warranty that the thing shall exist, the contract is not to be construed as a positive contract, but as subject to an implied condition that the parties shall be excused in case, before breach, performance becomes impossible from the perishing of the thing without the default of the contractor. VOL. LIII — 17 *258
In the case at bar, as stated, Cook, Brown Co. were not to do any of the carpenter work, joiner work, painting or glazing, and only to perform so much of the stone, brick and mason work, and furnish so much of the materials therefor, as was not to be furnished and performed byMcCabe, who expressly agreed to furnish upon the ground all the sand and stone and twenty-four barrels of lime, and to haul all the brick, and to furnish all good suitable materials. It is evident from the contract that the materials for the mason work and the labor thereon were to be furnished and performed by Cook, Brown Co. and McCabe, acting in conjunction with each other. The completion of the mason work, which was thus to result from their joint action, must necessarily have been dependent more or less upon the performance of the painting, glazing, carpenter and joiner work, with each and all of the persons doing the several kinds of work occupying the building, or portions of it, at the same time. With much of the material and the land belonging toMcCabe, and the materials furnished by Cook, Brown Co., together with the value of their labor thereon, becoming a part of the realty as fast as the same became attached to the soil, it would seem that no injustice can be done and no legal principle violated by treating the structure, as far as completed, as the property of McCabe, especially as he so treated it himself, and got it insured for his own benefit, and when burned received the insurance therefor.
The facts stated clearly distinguish the case from Jackson v.Cleveland,
With our construction of the contract, the defendant was entitled to sixty days within which to make payment of the balance of the contract price, without interest; but if he delayed payment for six months, then he agreed to pay seven per cent., and if one year, then ten per cent. These provisions for interest and an increase of interest were, in our opinion, merely to stimulate the defendant to pay promptly at the end *260 of sixty days, or, at the most, within six months, and not for the purpose of giving an absolute credit of one year.
The measure of damages in such a case is, prima facie, the prorata share of the contract price. Trowbridge v. Barrett,
We are inclined to think that counsel for the appellant is right in contending that this was not a proper case for a forced reference; but with our view of the law the court would have been authorized, upon the undisputed evidence, to direct a verdict for the plaintiffs; and as the amount, under such evidence, could not have been less than the amount found by the referee, the defendant has in no way been injured, and therefore, upon a well-established principle, we should not disturb the judgment.
By the Court. — The judgment of the circuit court is affirmed.
*110