281 F. 981 | 4th Cir. | 1922
The appellee, Portsmouth Cotton Oil Refining Corporation, complainant below and herein so called, has been the owner for several years of a tract of land on the northerly side of Paradise creek, in Norfolk county, Va., where it has an extensive plant and carries on a large and lucrative business. Its operations require the use of large quantities of water, which it obtains from this creek under the riparian rights incident to its ownership of the adjacent land. Paradise creek is a small tidewater stream, which flows into the southern branch of the Elizabeth river. Prior to the acts complained of it was navigable, by vessels drawing up to around 5 feet of water, for some distance above complainant’s property, and was in fact used by such vessels more or less frequently.
In April, 1919, the United States entered into contract with H. P. Converse & Co. for dredging certain areas in the Navy Yard at Norfolk, "and_ doing certain other work, in accordance with detailed plans and specifications. The dredged material was to be deposited on lands described as H, I, and J; the first two belonging to the United States Housing Corporation and the third to complainant. This contract, or the work to be done under it, was sublet to the United Dredg
During the progress of the work a great deal of mud and other material escaped from the dumping grounds into Paradise creek, with the result that its waters were polluted and its navigability destroyed. Indeed, the creek seems to have been filled up to such an extent as to hold very little water at low tide. In consequence there was expensive interruption of complainant’s business, caused by lack of water, and considerable injury to its plant and mechanical equipment.
Accordingly, in June, 1920, while the work was still going on, complainant brought this suit, to restrain defendants from continuing to allow the dredged material to get into the creek, to recover the damages already suffered, and to require defendants to restore the creek to its former depth and condition. A temporary injunction, motion to vacate which was denied, stopped the deposit of material on the areas named and compelled defandants to dispose of it elsewhere. In due course answer was filed and the case tried. The trial court held, for reasons stated in its opinion, that the evidence sustained the allegations of the bill and entitled complainant to the relief prayed for, and referred the matter to Col. John C. Oakes, a United States Army Engineer, as special master, to inquire and report: (a) What was necessay to restore Paradise creek to its depth and condition before the work was begun; (b) what damage complainant had already sustained ; and (c) what further damage it would sustain if the creek could not be restored to its former condition. In March, 1921, after extended hearing, the special master reported: (a) That complainant had been damaged to the amount of $8,753.56; (b) that the creek • could be restored to its former condition at a cost of approximately $13,000; and (c) specifying the work to be done to accomplish that result.
Objections were filed to this report, and in July following the cause was recommitted to the special master to ascertain and report, among other things, whether complainant could be provided with sufficient water by reopening the old basin, or opening a new basin, in front of its plant, the size and cost of such a basin, and whether it could be maintained in future for the needed purpose. Some further testimony was taken, and a supplemental report submitted in September, to the effect, in substance, that the proposed method was impracticable and would not afford permanent relief. It is also stated in this report that the creek could not be placed in the same condition as before the dumping commenced, because the mud “was distributed over the whole bed of the stream, including the ordinary channel and the side slopes to the limit of high water”; that the only thing that can now be done is to excavate to an equivalent waterway; that the necessary size of a new channel had been carefully considered in making the former report; and that the dredging therein specified would provide an equivalent stream and give complainant as large a supply of water as it had before defendants began their operations. A further brief report in October contains nothing of importance, and reference thereto may be omitted.
“The court doth further order and enjoin the defendants to proceed forthwith to restore Paradise creek in Norfolk county, Va., to the depth and condition in which it was immediately before they began the work mentioned in the bill of complaint, in accordance with the plan suggested in said reports, by excavating and removing from the bed of said creek sufficient material, to provide a clear channel 50 feet wide and 3 feet deep at mean low water, with side slopes of not less than one vertical and three horizontal from the mouth of said creelt to a point 1,000 feet above the site of complainant’s plant, with a widening of the channel for 300 feet opposite complainant’s plant, to form a basin from and including the channel to a line drawn parallel to the direction of the channel and passing through the suction of complainant’s intake pipe.”
From this decree defendants appeal.
The correctness of this proposition may be conceded when the incidental injury is the necessary and unavoidable consequence of doing the work; that is to say, when the work cannot be done without inflicting the injury. If the desired improvement of this Navy Yard could have been made in no other way than by depositing the dredged material where it would escape into Paradise creek, and thus deprive complainant of its needful supply of water, it might well be argued that the contractors could not be held responsible. Gibson v. United States, 166 U. S. 269, 17 Sup. Ct. 578, 41 L. Ed. 996; Scranton v. Wheeler, 179 U. S. 141, 164, 21 Sup. Ct. 48, 45 L. Ed. 126. But plainly that is not the case in hand. The improvement in question involved no necessity for filling up Paradise creek, néarly a mile distant, or affecting in any way the natural flow of its waters; nor did the government, in planning the improvement and providing for its execution, contemplate or intend any impairment of the creek or of the rights of riparian owners. This is evident from the provisions of specification No. 3844, made a part of the contract, which invited proposals for doing the work. Bidders were advised that they would have the option of using the hydraulic method, in which case the dredged ma
“Areas H and I are the property of the United States Housing Corporation, and area J is the property of the Portsmouth Company. While permission to dump on their land has been obtained informally from b-th corporations, each bidder will be required to make his own arrangements as to the dumping of the dredged material, and shall submit with his bid complete information regarding all arrangements which have been made.”
And a letter from Converse & Co. to the Bureau of Yards and Docks, under date of April 14, 1919, three days before the contract was signed, says:
“Referring to deposit of waste material, we have obtained permission from the United States Housing Corporation and the Portsmouth Company for the disposal of the material on their lands.”
This clearly shows that the deposit of material on the areas mentioned in 'the specification was not of the least importance to the undertaking, and justifies the inference that, if defendants had failed to make satisfactory arrangements with the owners of those areas, they would have been free to provide themselves with other available dumping grounds, of which there were many, subject only to approval of the officer in charge. They did procure others when the temporary injunction was continued, and apparently without difficulty and with,out any objection on the part of the government. In short, the obtaining of dumping grounds was a matter with which the government was not concerned, and for which contractors were required to make their own arrangements. Confirming this view and refuting, as we think, the defendants’ contention is the following provision in the contract itself, typewritten ,in the printed form:
“It is agreed and understood that any arrangements, agreements, or contracts with property owners or others, which may be necessary in connection with the pumping and depositing of the dredging material ashore, shall be an obligation assumed by the party of the first part under this contract, and, further, that failure on the part of any property owner or others to comply with the terms of such agreements or contracts shall not operate to release the party of the first part from the dredging obligation assumed in this contract. It is further agreed and understood that the party of the first part assumes all responsibility for the adequacy of bulkheads, dikes or other construction which may be placed by him for the retention of dredged material, and further that any damage which may result from the inadequacy of such construction, or which otherwise may result from the pumping or filling operations, shall be made good by the party of the first part.”
This broad language manifestly covers not only the particular areas designated in the specification, but likewise all other areas for which arrangements had been or might be made by defendants. And the meaning of the provision as a whole seems too plain for discussion, especially so when account is taken of the purpose of the contract and the alternate methods allowed for its performance. The evident
“There was no permit granted the complainant for the structure in question. However, it is unfair to the complainant not to state in this connection that, while the law requires that all structures in navigable water must be approved by the yVar Department, such approval may be obtained after the structure has been built, and in the majority of cases of small structures in small streams no permit is taken out by the parties building the structures, nor is a permit required by the United States when such structures are discovered, unless some objection exists to the structures as they exist.”
It would be enough to observe further that the unlawfulness of this insignificant structure, if it be unlawful, was purely a matter between the United States and complainant, and therefore furnishes no defense to the suit; but to this may be added that the substantial and valuable right of which complainant has been deprived is the right of a riparian owner to take water from the creek in a lawful manner. The particular method is unimportant, if it be one to which the War Department makes no objection, and surely complainant should not be denied redress for the injury it has suffered because, and merely because, the method employed by it was not sanctioned by formal permission. And this applies as well to the suggestion that complain
Some attempt is made to show that the special master reached conclusions not supported by any evidence, but careful scrutiny of the record satisfies us that the claim is not well founded. He not only took a large amount of testimony himself, but had before him all the previous testimony, together with the numerous maps, drawings, blueprints, and other data which had been introduced. To the consideration of this evidence he brought the expert knowledge of a trained engineer, aided by personal familiarity with the situation. The reports bear witness to his painstaking study of the case and to his considerate treatment of defendants. We find in them nothing of material import which is not fairly inferable from the proofs.
The other contentions of defendants are covered by what has already been said, or are not deemed of sufficient importance to be made
The decree appealed from will be affirmed.