Lead Opinion
OPINION
The questions presented in this case are whether the district court abused its discretion in certifying an order as a final partial judgment under Minn. R. Civ. P. 54.02 (“Rule 54.02”), and if so, whether an erroneously certified order results in a judgment that is immediately appealable. The case arises from a dispute over a construction contract entered into between appellant Contractors Edge, Inc. (“Contractors Edge”) and respondent City of Mankato (“the City”). Contractors Edge sued the City alleging breach of contract, equitable estoppel, and violation of the Prompt Payment Act, Minn.Stat. § 471.425 (2014). By 2012 only the breach of contract and the Prompt Payment Act claims remained. The City moved for summary judgment and the district court dismissed the breach of contract claim on October 3, 2012, in an order (“October 2012 order”) that is at the center of this appeal. Although neither party asked for a certification of final judgment under Rule 54.02, the district court concluded the October 2012 order by stating, “THERE BEING NO JUST REASON FOR DELAY, LET JUDGMENT BE ENTERED ACCORDINGLY.” Summary judgment on the claim was entered on the same day. The parties eventually settled the remaining Prompt Payment Act claim and the district court administrator entered final judgment on January 6, 2014.
Contractors Edge appealed on February 7, 2014, seeking review of the October 2012 order.
I.
The court of appeals dismissed Contractors Edge’s appeal, concluding that it was late. Contractors Edge, Inc. v. City of Mankato, No. A14-0223, Order at 3 (Minn.App. filed Mar. 18, 2014). Under Minn. R. Civ.App. P. 104.01, subd. 1, a judgment entered “pursuant to Rule 54.02” must be appealed within 60 days of the date the judgment is entered if the “trial court makes an express determination that there is no just reason for delay and expressly directs the entry of a final judgment.” Consistent with the appellate rule, if the district court properly certified the October 2012 order under Rule 54.02, Contractors Edge’s appeal, which was not filed until February 2014, was late and the court of appeals did not have jurisdiction. See Tischendorf v. Tischendorf,
Minnesota Rule of Civil Procedure 54.02 allows a district court to direct the entry of a final judgment “as to one or more but fewer than all of the claims” if it determines “there is no just reason for delay.” In the October 2012 order, the district court used the language set forth in Rule 54.02. But the court did not explain its reasons for certifying under Rule 54.02. Contractors Edge argues that it is an abuse of discretion for a district court to fail to provide reasons for its decision and that without a recitation of reasons for the certification, the requirements of Rule 54.02 are not met. The City argues that although articulated reasons are an aid to review, they are not a requirement for a proper Rule 54.02 certification.
The parties’ arguments require us to interpret procedural rules. We review the construction and application of procedural rules de novo. Commandeur LLC v. Howard Hartry, Inc.,
A.
Rule 54.02 provides that the district court “may direct the entry of a final judgment as to one or more but fewer than all of the claims ... only upon an express determination that there is no just reason for delay and upon an express direction for the entry of judgment.” Minn. R. Civ. P. 54.02. Black’s Law Dictionary defines “express” as “[c]learly and unmistakably communicated; stated with directness and clarity.” Black’s Law Dictionary 701 (10th ed.2014). It defines “determination” as “a final decision by a court.” Black’s Law Dictionary 544 (10th ed.2014). Further, Webster’s Third New International Dictionary defines “determination” as “[t]he resolving of a question by argument or reasoning.” Webster’s Third New International Dictionary 616 (2002). These definitions do not support the argument that an “express determination” must include an explanation of the district court’s reasoning. See Elliott v. Archdiocese of N.Y.,
Cases interpreting Rule 54.02 and Fed. R.Civ.P. 54(b), the analogous federal provision, also support the conclusion that Rule 54.02 does not require an explanation for the certification. In terms of our precedent, we have never held that articulated reasons are required for a valid certification under Rule 54.02. And most federal courts reviewing the issue have held that although stated reasoning from the district court is preferred, it is not necessary for proper certification.
We agree with those courts that have concluded that it is a preferred practice for the district court to provide a written explanation for the certification decision. The failure to provide such articulated reasons, however, is not by itself an abuse of the district court’s discretion. This is so because the record might otherwise disclose why the certification was appropriate. See Bank of Lincolnwood,
We turn then to the record here to determine whether the record supports the certification. We review the record through the lens of the abuse-of-discretion standard of review. T.A. Schifsky & Sons, Inc. v. Bahr Constr., LLC,
B.
Contractors Edge argues that the district court abused its discretion in this case because there are “no substantial and compelling reasons” in the record that would justify an immediate appeal of the October 2012 order. The City responds that the district court’s certification was reasonable because, as reflected in the record, the two claims were independent of one another and the breach of contract claim was the substantive claim, which warranted immediate review. We agree with Contractors Edge that the record does not provide a basis for certification.
A district court has discretion to “allow a piecemeal appeal if the parties or claims are clearly separable and no prejudice would result from appeal.” Novus Equities Corp. v. EM-TY P’ship,
One such appropriate case is when a district court certifies an order based on the possibility of hardship that could result from a delayed appeal. See Novus Equities Corp.,
Administrative concerns, such as the parties’ desire to adjudicate one claim fully before deciding whether to continue to trial on another, may also support a certification. See, e.g., Cold Metal Process Co. v. United Eng’g & Foundry Co.,
We agree with the principle discussed in these federal cases that, in general, closely related claims should not proceed separately on appeal. The certification at issue in this case runs afoul of that principle because the record establishes that the claims at issue were closely related. Specifically, both of Contractors Edge’s claims arose out of its contractual relationship with the City. Contractors Edge argued that the City owed it compensation for the extra work it performed that was not included in the original contract and brought a breach of contract claim to recover that compensation. Contractors Edge also claimed that the City did not timely pay the percentage of the contract price the City withheld as retainage following completion of the project and that Contractors Edge was therefore entitled to interest, costs, and attorney fees under the Prompt Payment Act. Both claims required the court to interpret the parties’ contract: first to determine whether the City owes Contractors Edge under the contract’s claims procedure, and then to determine when Contractors Edge’s work was substantially completed under the contract. As both claims arose from the same set of facts, certification is discouraged. See, e.g., Hayden,
In urging us to reach the opposite conclusion, the City argues that the claims have no bearing on one another and are therefore independent. The legal analyses
Notwithstanding the fact that the claims are closely related, certification could still be permissible under Rule 54.02 if there were others factors that outweighed our policy against piecemeal appeals. But the record discloses no such countervailing considerations. Indeed, neither party in this case even requested Rule 54.02 certification and neither party has made any showing of hardship to justify a piecemeal appeal. Finally, nothing in the record suggests either party would have been prejudiced by waiting to appeal the district court’s decision until the final resolution of both claims.
In sum, our review of the record provides no basis for a “determination” that certification was warranted under Rule 54.02. Because the claims arose out of the same facts, there is no showing of hardship or injustice, and the district court gave no indication of its reasons for certifying, we hold that the district court abused its discretion in certifying the October 2012 order.
II.
Having decided that the district court erred in certifying the October 2012 order pursuant to Rule 54.02, we turn to whether, as the dissent contends and the court of appeals held, Contractors Edge nevertheless had to appeal the resulting judgment immediately. Contractors Edge argues that its appeal was timely because the district court’s certification was improper and therefore the October 2012 judgment was not immediately appealable. The correct time to appeal, Contractors Edge argues, was following the entry of a final judgment on the last remaining claim, which did not occur until January 6, 2014. Because Contractors Edge appealed within 60 days of-the entry of final judgment, it contends its appeal was timely. The City argues that appeals from a Rule 54.02 judgment must be taken immediately, even if the certification is later determined to be improper.
Whether an improperly certified Rule 54.02 order results in a judgment that is immediately appealable is an issue of first impression in Minnesota. The federal courts are split on the question. Under the rule adopted in the Ninth Circuit, orders that are improperly certified nevertheless result in immediately appealable judgments. See Lindsay v. Beneficial Reinsurance Co.,
While our Rule 54.02 cases have not resolved the precise question presented here, the result we reach is more solidly grounded in the logic of our Rule 54.02 jurisprudence than the approach the Ninth Circuit has adopted and that the dissent advocates. For example, in T.A. Schifsky & Sons, Inc. v. Bahr Construction, LLC,
We have also held that a failure to state the required language does not result in an immediately appealable judgment. See, e.g., Pederson v. Rose Coop. Creamery Ass’n,
In T.A. Schifsky & Sons and Pederson, we addressed orders that were erroneously certified because the district court did not comply with the textual requirements of Rule 54.02. In T.A. Schifsky & Sons, the district court exceeded its power under the rule, by certifying an order in a single-claim case. See
The Eighth Circuit noted that appellate courts have broad power to determine whether a district court has properly certified an order for immediate review. Id. The court then stated that “[wjhile, technically, the period for taking an appeal begins to run from the time the district court enters final judgment ... if the certification is erroneous, there is, in fact, no proper final judgment from which a party must appeal.” Id.; see also Fed. Deposit Ins. Corp. v. Tripati,
Both the Second Circuit and the Idaho Supreme Court follow the rule applied in Page. In Ansam Associates, Inc. v. Cola Petroleum, Ltd.,
The dissent attempts to distinguish Page, because Page involved a single claim, whereas Contractors Edge pleaded multiple claims. But the Page rule has been applied in cases that involved multiple claims. See, e.g., Tripati,
Our rule does not, as the dissent asserts, create a new category of “mostly final judgments” and blur a “bright-line” rule. Our rule is clear: if the certification is improper, the resulting judgment is not immediately appealable. Under our rule, therefore, a judgment is either final or it is not final.
The dissent’s rule, on the other hand, is hardly the beacon it claims to be. Under the dissent’s rule, some orders that are improperly certified under Rule 54.02 result in immediately appealable judgments and some do not. The distinction apparently hinges on an appellate court’s determination as to whether the order at issue is “facially valid,” a determination that begs as many questions as it answers. See Page,
The purpose behind Rule 54.02 also supports our interpretation. We have recognized that the purpose of Rule 54.02 is “to reduce piecemeal appeals by limiting appeals from judgments that resolve only part of the litigation.” T.A. Schifsky & Sons,
In contrast to our approach, the dissent’s approach encourages piecemeal appeals by insulating the district court’s Rule 54.02 certification from review unless an immediate appeal is taken. See 15A Charles A. Wright et al., Federal Practice and Procedure: Jurisdiction and Related Matters § 3914.7 (2d ed.1992) (encouraging parties who believe that the district court made an improper Rule -54(b) certification to take a “protective appeal” in which they request that the appellate court dismiss that very appeal). Under the dissent’s approach, even in the situation before us today, which we hope is unique, when neither party requested a Rule 54.02 certification and the district court gave no reason for its certification, an immediate piecemeal appeal would be necessary. Rather than an immediate appeal in such a situation, the better practice is for parties to pursue the question with the district court in order to resolve uncertainties as to the basis for the court’s certification.
Considering our precedent and the purpose behind Rule 54.02, we conclude that an order that is improperly certified under Rule 54.02 does not result in an immediately appealable judgment. Applying that rule here, the October 2012 order did not result in a final partial judgment because the district court abused its discretion in certifying the order. Accordingly, the October 2012 order was not immediately ap-pealable, and we hold that Contractors Edge’s appeal from the final judgment in 2014 was timely.
Reversed.
Notes
. Although Contractors Edge’s notice of appeal stated that Contractors Edge appealed from the October 2012 order, which was not an appealable order under Minn. R. Civ.App. P. 103.03, we construe notices of appeal liberally in favor of their sufficiency. Kelly v. Kelly,
. We have stated that "[w]here the language of the Federal Rules of Civil Procedure is similar to language in the Minnesota civil procedure rules, federal cases on the issue are instructive.” T.A. Schifsky & Sons, Inc. v. Bahr Constr., LLC,
. In Curtiss-Wright Corp. v. General Electric Co., the U.S. Supreme Court noted in dicta that claims arising out of the same facts may be properly certified, if "the district court ... find[s] a sufficiently important reason for nonetheless granting certification."
. The South Dakota and Alabama Supreme Courts have adopted the Ninth Circuit’s rule. See Wallace v. Belleview Props. Corp.,
. The dissent correctly notes that the Second Circuit requires that a Rule 54(b) certification be accompanied by articulated reasons, an approach we have rejected. That rule, however, does not determine whether an improperly certified order is nevertheless immediately appealable. See, e.g., Lindsay,
. Idaho Rule of Civil Procedure 54(b) is analogous to our Rule 54.02. And contrary to the dissent's assertion that Watson was decided on provisions unique to Idaho’s rules of civil procedure, the Idaho Supreme Court’s reasoning is applicable here. The district court in Watson had the power to certify the judgment, see Joyce Livestock Co. v. Hulet,
Dissenting Opinion
(dissenting).
By the plain words of Minn. R. Civ.App. P. 104.01, subd. 1, the time to appeal from a partial judgment entered as final is 60 days: no ifs, ands, or buts. The deadline starts to run from the entry of judgment if the' district court has made' an express determination that there is no just reason for delay and has directed the entry of final judgment. The deadline starts to run regardless of whether the district court’s express determination was wise or ill-considered. Until today what was a final judgment, for the purpose of appeal and every other purpose, was crystal clear. Because the majority opinion creates a new, murky category of “mostly final” judgments, I respectfully dissent.
L
Contractors Edge, Inc. sued the City of Mankato in 2010 on claims arising out of a construction project. As is common in construction litigation, there were multiple claims and motions. By 2012, the parties had made motions for summary judgment in the district court, argued an appeal, and returned to the district court. Contractors Edge, Inc. v. City of Mankato, No. A11-916,
On remand from the court of appeals, there remained two claims: a contract claim of about $252,000 for extra work; and a statutory claim, under the Prompt Payment Act, Minn.Stat. § 471.425 (2014), for alleged failure to pay retainage.
As directed, the court administrator promptly entered final judgment, as shown on the Register of Actions. The court administrator then sent to counsel a Notice of Filing of Order and Entry of Judgment. The notice advised that “Summary Judgment was entered on October 03, 2012.” Counsel received with the notice a copy of the judgment, stating that it had been “ADJUDGED AND DECREED that Judgment is entered” on the City’s contract claim.
Contractors Edge did not appeal from the judgment within 60 days. Nor did it seek explanation or clarification from the district court. The record does not explain why no appeal was taken.
More than a year later, the parties settled the remaining statutory claim. The district court entered judgment on January 6, 2014. Less than 60 days later, Contractors Edge appealed from the October 3, 2012, order that had granted summary judgment to the City on the contract claim.
The City moved to dismiss the appeal as untimely. On March 18, 2014, the court of appeals, by order signed by the chief judge, granted the motion. Contractors Edge, Inc. v. City of Mankato, No A14-0223, Order at 3 (Minn. App. filed March 18, 2014). We granted review.
II.
This appeal turns on the meaning of Minn. R. Civ.App. P. 104.01, subd. 1. As we explained recently in Walsh v. U.S. Bank, N.A.,
Rule 104.01, subd. 1, captioned “Time for Appeal,” establishes a bright-line rule for appeals from judgments. A judgment is appealable, and must be appealed, within 60 days after its entry. This deadline is jurisdictional. See Jesmer Co. v. Wurdemann-Hjelm Corp.,
The second paragraph of Rule 104.01, subd. 1, addresses judgments entered as final under Minn. R. Civ. P. 54.02. It provides:
An appeal may be taken from a judgment entered pursuant to Rule 54.02, Minnesota Rules of Civil Procedure, within 60 days of the entry of the judgment only if the trial court makes an express determination that there is no just reason for delay and expressly directs the entry of a final judgment. The time to appeal from any other judgment entered pursuant to Rule 54.02 shall not begin to run until the entry of a judgment which adjudicates all the claims and rights and liabilities of the remaining parties.
In other words, under Rule 104.01, when a judgment is entered on fewer than all of the claims, the judgment may or may not be appealable. If the trial court does not make an “express determination that there is no just reason for delay,” it is not appealable. But if the trial court makes an “express determination,” and expressly directs entry of final judgment, it is appeal-able. While Rule 104.01 uses the term “may,” the 60-day requirement is mandatory; to be timely, the appeal must be taken within 60 days. T.A. Schifsky & Sons, Inc. v. Bahr Constr., LLC,
Here, the district court granted the motion for summary judgment on one of the two claims and made the express determination required by Rule 104.01, subd. 1, for entry of a final, appealable judgment. The court administrator correctly entered judgment based on the express direction of the district court and gave notice to the parties. Every predicate for finality and appealability was satisfied, so the 60-day deadline for appeal began to run. Thus, applying the plain words of the appellate rule, an appeal from the final judgment of October 3, 2012, was required on or before December 2, 2012, 60 days after the entry of partial final judgment. Contractors Edge waited until January 6, 2014, to appeal. Its appeal was more than a year late.
By failing to read Rule 104.01, subd. 1, straightforwardly, the majority adds a new condition to it. By making appealability of the judgment under the appellate rule conditional on an appellate court’s later determination that the trial court properly exercised its discretion pursuant to the underlying civil rule, the majority essentially inserts words into, and thereby rewrites, the appellate rule. Based on the majority holding, Minn. R. Civ.App. P. 104.01, subd. 1, now reads: “An appeal may be taken from a judgment entered pursuant to Rule 54.02, Minnesota Rules of Civil Procedure, within 60 days of the entry of the judgment only if the trial court without abusing its discretion makes an express determination that there is no just reason for delay and expressly directs the entry of a final judgment.” (Additions emphasized.)
We do not add words or phrases to unambiguous Minnesota rules. Walsh,
III.
The case law on which the majority relies in no way requires that our appellate rule be twisted in this way. The Minnesota precedent cited by the majority is easily distinguishable. In T.A. Schifsky, a dis
We observed that a district court has no authority to make an express determination unless the lawsuit is based on more than one legal theory or states more than one group of operative facts giving rise to relief. Id. at 787. Noting that attorney fees were “not a separate claim independent of the merits of the action, namely,the validity of the lien and the fair and reasonable value of the lien,” we decided that entry of judgment under Rule 54.02 was “unnecessary.” Id. at 789. “Nevertheless,” we held: “by operation of law that judgment became final and appealable upon its entry. Accordingly, the court of appeals correctly ruled that [the losing party’s] appeal of the judgment determining the validity and amount of the liens was not timely.” Id.
This case is not T.A. Schifsky, in which the district court directed entry of judgment on all claims under the mistaken rubric of Rule 54.02. In this case, unlike T.A. Schifsky, there is no question (and the majority does not dispute) that the district court directed entry of final judgment on fewer than all of the claims. The common-law contract claim for extra work and the statutory Prompt Payment Act claim for retainage were separate claims for the purpose of Rule 54.02. See Stearns v. Consol. Mgmt., Inc.,
While T.A. Schifsky’s reasoning does not control this case, its result — appeal dismissed — sends a clear message directly relevant to this case: if a party has doubts about the appropriateness of, or rationale for, any final judgment, the party fails to appeal or seek clarification at its peril. If Contractors Edge doubted that the entry of judgment was proper, it had two choices: it could have appealed on that ground,
By holding that partial final judgment on fewer than all claims, valid on its face and entered upon the district court’s express determination and direction, did not start the time for appeal, the majority declines to follow the great weight of appellate and scholarly authority to the contrary. This line of precedent is completely consistent with the plain meaning of our appellate rule and is directly applicable to the facts of this case.
In Lindsay v. Beneficial Reinsurance Co.,
Three state supreme courts have considered the time for appeal in cases involving partial final judgments on fewer than all claims in which the express determination was argued to be an abuse of discretion. All three courts agreed with the Ninth Circuit that the appeal deadline runs from entry of judgment, regardless of whether the express determination was an abuse of discretion. See Wallace v. Belleview Props. Corp.,
Not only do the Ninth Circuit and the supreme courts of Alabama, South Dakota, and Utah agree, so do commentators. Moore’s treatise on civil procedure speaks to the precise situation here: “A Rule 54(b) judgment begins the running of the time to appeal regardless of the propriety of the entry of that judgment. In other words, whether or not the court abused its discretion in entering judgment is irrelevant to the parties’ obligation to timely appeal.” 10 James W. Moore et al, Moore’s Federal Practice § 54.26[1] (3d ed.2012) (emphasis added). “An aggrieved party must appeal a Rule 54(b) judgment within the time permitted ... and may not seek review of the judgment after the remaining claims have been adjudicated.” Id. The Wright treatise on federal procedure similarly indicates that time for ap.peal of a judgment certified under Rule 54(b) should be measured from the entry of judgment, as long as the court provides an express determination that there is no just reason for delaying review:
The requirement in Rule 54(b) that the court make an express determination that there is no just reason for delaying the review of a judgment on fewer than all of the claims ... eliminates any doubt whether an immediate appeal may be sought. Conversely, it makes clear when an appeal must be sought or the right to appeal will be lost, since the time for appeal begins to run from the entry of an order that meets the requirements of the rule.
10 Charles A. Wright et al., Federal Practice and Procedure § 2654 (3d ed.1998) (emphasis added).
Instead of following this strong authority, the. majority relies on Eighth Circuit precedent, Page v. Preisser,
The other cases cited by the majority help hardly at all. For example, Watson v. Weick,
In sum, the majority’s holding is contrary to the plain language of the rule and applicable authority. The majority has created for Minnesota a new category of “mostly final” judgments: final judgments valid on their face that can be miraculously resuscitated for appeal after the time for review has expired.
IV.
Because I read Minn. R. Civ.App. P. 104.01, subd. 1, to be clear and unambiguous, I am under no obligation to discuss the implications of the majority’s erroneous creativity. But I feel compelled to do so, because the harmful results are easily foreseeable.
Until now, a final judgment, valid on its face, entered in a Minnesota court upon express determination and direction but not appealed was truly final. It was final, not just to the litigants involved, but to the world. It was final for accrual of judgment interest, for a judgment lien, for execution on the judgment, and for the doctrine of res judicata. It could not be undone except for a limited number of very good and substantial reasons. See Minn. R. Civ. P. 60 (relief from judgment or order).
By holding that a final judgment valid on its face can be appealed and undone even after the time to appeal has expired, the majority creates a great deal of confusion. What the court of appeals had assumed to be a bright line
Parties, attorneys, lower courts, and businesses that rely on facially valid judg
The majority asserts that its holding will discourage piecemeal appeals. Instead, it will encourage litigation over late appeals. The majority’s new “mostly final” judgment category creates a “danger of hardship and denial of justice through delay if each issue must await the determination of all issues as to all parties before a [truly] final judgment can be had,” Dickinson v. Petroleum Conversion Corp.,
V.
I need not reach, and the majority did not have jurisdiction to reach, the question of whether the district court abused its discretion in making its express determination and direction. I need not reach, and the majority should not have reached, whether the proper remedy for the district court’s lack of explanation is reversal or a remand to the district court to explain its reasoning. Because this appeal was untimely by more than a year, I would affirm the court of appeals’ decision to dismiss it.
. After substantial completion in 2009, the City allegedly held $23,365.60 in retainage. All but $100 of that amount was paid on November 10, 2010.
. Neither party had asked for entry of final judgment under Minn. R. Civ. P. 54.02 and the district court did not explain why it made its express determination sua sponte. Certainly it would have been good practice for the district court to have explained its reasoning. But the majority holds, and I agree, that under both Minn. R. Civ.App. P. 104.01, subd. 1, and Minn. R. Civ, P. 54.02, no explanation was required.
. The notice of appeal stated that Contractors Edge appealed "from the Order granting, in part, Defendant City of Mankato’s Motion for Summary Judgment, issued and filed by the Blue Earth County District Court in the above entitled matter on October 3, 2012.” Oddly, it did not refer to either judgment. The order itself is not of the type from which one can appeal. See Minn. R. Civ.App. P. 103.03. But I do not disagree with the majority that, in this particular instance, we should construe the notice of appeal liberally to reference the second judgment entered.
. Federal Rules of Civil Procedure 54(b) and Minn. R. Civ. P. 54.02 are similar in all relevant respects.
. If a party believes that a partial final judgment has been erroneously entered based on an abuse of the trial court’s discretion, it can appeal from the judgment. When presented with a timely appeal, the court of appeals has reversed and vacated such judgments. See, e.g., Sterling State Bank v. Maas Commercial Props., LLC,
. Contractors Edge does not argue that it pleaded only a single claim. The majority determines that the two claims are "closely related,” but, correctly, does not deny that there were "multiple claims.” The "closely related” standard goes to whether the district court properly exercised its. discretion when it made its express determination under Minn. R. Civ. P. 54.02, not to whether the time to appeal has started to run under Minn. R. Civ.App. P. 104.01, subd. 1.
. On the new category, compare The Princess Bride (Act III Communications 1987) (Miracle Max exclaims: "Whoo-hoo-hoo, look who knows so much. It just so happens that your friend here is only mostly dead. There’s a big difference between mostly dead and all dead.... Mostly dead is slightly alive.”)
.See Javinsky v. Comm’r of Admin.,
. If, as the majority surmises, district courts have ignored our cautionary notes in opinions such as T.A. Schifsky, and they routinely and thoughtlessly make judgments final with boilerplate language, the better solution might be to consider an amendment to Rule 54.02 that would require district courts to explain their express determinations. Such an amendment could be considered in a transparent rulemak-ing process.
Dissenting Opinion
(dissenting).
I join in the dissent of Justice Lillehaug.
