Opinion
Introduction
In this eminent domain proceeding, Contra Costa Water District (Water District) acquired approximately 3,500 acres of 6,000 acres owned by Vaquero Farms, Inc. (Vaquero) to be used by the Water District for the Los Vaqueros Reservoir Project (Reservoir Project). The issues on appeal involve the compensation awarded Vaquero for the taking of the property. Specifically, Vaquero contends: 1) the Water District must condemn its
*888
windpower rights, with a corresponding legal obligation to pay just compensation, even though the Water District chose to sever the property’s wind-power rights and reserve them to Vaquero; 2) the court erred in failing to award damages for the Water District’s unreasonable precondemnation activities under
Klopping
v.
City of Whittier
(1972)
We conclude it was permissible for the Water District to sever and reserve to Vaquero its windpower rights. We also affirm the trial court’s finding that Vaquero was not entitled to recover damages for precondemnation activities, and the jury’s severance damage award.
Background
The Vaquero property is located approximately six miles north of the City of Livermore, and approximately six miles south of the City of Brentwood. The property fronts over three miles of Vasco Road, which is a north-south traffic corridor. The 6,000 acres owned by Vaquero were and are primarily undeveloped. It varies tremendously in topographical features, ranging from relative flatlands adjacent to Vasco Road to steep ridge areas in the center and rugged ravines in the parcel’s eastern portion. The property has been used as a working cattle ranch for nearly 50 years. In 1984, large portions of the ranch (over 2,100 acres) were leased for windpower electrical production and about 260 wind turbines have been installed on the property.
The Water District filed its complaint in eminent domain on June 14, 1993. By this action, the Water District sought to acquire four separate parcels of Vaquero’s property, totaling approximately three thousand five hundred acres, for the Reservoir Project. The Reservoir Project is a major public work including a reservoir, diversion facilities, pumping plants, and pipelines to convey water for storage and use. It is the largest public works project ever undertaken by the Water District. The Reservoir Project’s primary purposes are to improve the quality of water supplied to the Water District’s customers, to minimize seasonal changes in water quality, and to improve the reliability of the Water District’s supply by providing for emergency storage. The Reservoir Project’s secondary purposes include providing flood control benefits, maintaining and enhancing fish and wildlife resources, and offering recreational opportunities.
Each of Vaquero’s four condemned parcels will be committed to a different use in connection with the Reservoir Project’s implementation:
*889 Parcel 1—a 2,743-acre parcel to be used for reservoir and watershed purposes;
Parcel 2—a 697-acre environmental mitigation parcel outside the reservoir/watershed area to be used to mitigate the environmental effects of the Reservoir Project on the habitat of the kit fox, an endangered species, and to mitigate the Reservoir Project’s effect on the wetlands;
Parcel 3—a 4.8-acre parcel at the extreme southeast comer of the property to be used for road relocation. The proposed reservoir will inundate old Vasco Road, which provides the property’s only public road access. Vasco Road will be relocated to the east of the reservoir and east of the property;
Parcel 4—a 52-acre area to be used as a combination cultural resource and environmental mitigation parcel outside the reservoir/watershed area.
Vaquero did not contest the right of the Water District to take its property. Instead, the focus of its answer to the complaint was the amount of “just compensation” to which appellant was entitled. Furthermore, in response to the complaint, Vaquero sought additional compensation for alleged damages sustained as a result of the Water District’s precondemnation delays and other activities, and for severance damages.
By stipulation, the parties agreed to bifurcate the proceeding and to submit the precondemnation damages claim to a court trial in advance of the trial of other issues. The only issues which proceeded to trial by jury involved the fair market value of the property taken, generally measured by the highest and best use for which it is geographically and economically adaptable (Code Civ. Proc., § 1263.320, subd. (a) [all future undesignated statutory references are to this code];
County of San Diego
v.
Rancho Vista Del Mar, Inc.
(1993)
The jury returned a verdict in the total sum of $14,428,327. This verdict was comprised of $13,428,327 representing the fair market value of the *890 property taken and $1 million representing severance damages to the land remaining in Vaquero’s ownership by reason of the taking. After Vaquero’s motion for new trial was denied, this appeal followed.
Severance of Windpower Rights
Vaquero advances the proposition that the Water District could not acquire the fee interest in its property while at the same time severing the windpower rights and windpower leasehold interests and reserving them to Vaquero. Before proceeding to a discussion of Vaquero’s arguments, we note our rejection of the Water District’s claim that Vaquero waived its right to press this issue on appeal because it withdrew funds deposited by the Water District as probable compensation. Specifically, the Water District relies on section 1255.260, which provides: “If any portion of the money deposited pursuant to this chapter is withdrawn, the receipt of any such money shall constitute a waiver by operation of law of all claims and defenses in favor of the persons receiving such payment except a claim for greater compensation.”
Vaquero’s arguments on this subject are presented with the express purpose of exacting from the Water District an additional incremental payment representing the value of its windpower rights. Therefore, Vaquero is making a claim for “greater compensation” which was not waived under section 1255.260 when Vaquero withdrew the deposited funds. (Cf.
San Diego Gas & Electric Co.
v.
3250 Corp.
(1988)
As noted, portions of the area being acquired and portions of Vaquero’s remaining property are subject to leases with various companies engaged in the enterprise of generating and selling electricity derived from wind blowing across the property. At the time of trial, over 2,100 acres of the Vaquero property were subject to windpower leases, and approximately 260 wind turbines were built on that acreage between 1984 and 1986.
In anticipation of having to place a monetary value on these windpower rights, the Water District hired a windpower consulting firm charged with estimating the value of the existing machines to their operators, valuing the undeveloped windpower leases, and valuing Vaquero’s present and future rental income streams. The consultants’ findings are summarized by the Water District as follows: “Unfortunately, the range of values for the present worth of the future windpower income stream was highly speculative and *891 varied wildly, depending on assumed long-term future energy prices, possible future royalty rates, and discount rates. It was not until 1991 that [the Water District] decided to attempt to avoid the problem entirely by reserving all windpower rights to the landowners.”
The Water District’s June 1993 resolution of necessity states that it is necessary to take Vaquero’s fee interest but the Water District “does not, by the passage of this resolution of necessity, intend to acquire any of the windpower rights . . . .” Therefore, the Water District’s complaint was limited to the acquisition of “[a]ll rights and incidents of the fee ownership interest vested in Vaquero Farms, . . . excepting and reserving to such defendants and their successors, and present and future assigns all rights for wind energy power conversion and the transmission of power generated by wind, including (1) the exclusive and perpetual right, ... to develop, construct, install, maintain and operate windpower facilities, including but not limited to windmills, transmission lines and other facilities, necessary or advantageous for the purposes of generating or transmitting electric power from wind on the real property . . . .” The severance included reserving to Vaquero the exclusive right “to develop, construct, install, maintain and operate windpower facilities,” the exclusive right to sell electric power generated by windmills, and the exclusive right to sell or lease the wind-power rights. Vaquero was granted continued access to the property through nonexclusive easements for “roadway, ingress and egress, and utility purposes . . . .”
By subsequent amendment to the complaint, the Water District acquired all the windpower rights in certain areas where it was determined Vaquero’s use of these rights would be inconsistent with the Reservoir Project’s proposed uses. Specifically, the Water District decided to acquire Vaquero’s rights in the following areas: 1) the 245-acre portion of parcel 1 that the Reservoir Project will actually flood, 2) the area within parcel 1 containing utility line relocation easements ; and, 3) all of parcel 3, the right-of-way for new Vasco Road. As a result, Vaquero’s windpower rights were ultimately reserved in areas generally remaining undeveloped open space after the transfer from private to public ownership.
Vaquero filed a general demurrer to the Water District’s complaint alleging it failed to state a cause of action because the Water District was prohibited, as a matter of law, from condemning the fee interest and severing the windpower rights. In opposition to the demurrer, the Water District contended that it was legally permissible to acquire the land needed for the Reservoir Project without appropriating the windpower rights because California law authorizes the condemner to sever rights it has determined are *892 unnecessary for the public use. The court overruled Vaquero’s demurrer, allowing the Water District to acquire the fee interest in the subject property while reserving and excepting the windpower rights to Vaquero.
The question before us may be stated as follows: When a public entity acquires property through eminent domain, are the windpower rights capable of segregation or are they so affixed to the underlying land that they must be acquired by the condemning authority? While the parties’ dispute presents a question of first impression, its answer can be found by applying the reasoning of well-established California eminent domain law to this neoteric factual setting.
Under California’s condemnation statutes, . . any person authorized to acquire property for a particular use by eminent domain may exercise the power of eminent domain to acquire any interest in property necessary for that use . . . .” (§1240.110; see also §§ 1235.125, 1235.170.) The “interests” susceptible to condemnation under the statute, embrace “any right, title, or estate in property.” (§ 1235.125.) Our Supreme Court has chronicled the interests considered to be property for condemnation purposes as including fee interest.
(County of San Diego
v.
Miller
(1975)
A review of the case law reveals California eminent domain law authorizes the condemner to select which right or combination of rights it needs to acquire from the full panoply of private ownership rights held within a fee simple estate. (See
Federal Oil Co.
v.
City of Culver City
(1960)
When closely examined, the gravamen of Vaquero’s argument rests on the premise that windpower rights must be rooted to the fee interest because no case, to date, has recognized windpower rights as capable of segregation or severance. In
Sacramento etc. Dist.
v.
Pac. G.&E. Co., supra,
By parity of reasoning, windpower rights are “substantial rights” capable of being bought and sold in the marketplace, as evidenced by a 30-year lease which was entered into between Vaquero and a windpower developer, Altamont Energy Corporation, long before the Water District’s condemnation action was initiated. The lease stands as irrefutable evidence that one may have a right to use windpower rights without owning any interest in the land. It memorializes Vaquero’s agreement to convey the right to harness and develop windpower on its property until the year 2014 in exchange for monetary compensation, including a share of the gross annual revenue generated from the sale of electricity. Having itself derived economic benefit from the dissection of its property rights by separately leasing windpower rights to a third party, Vaquero’s claim that these same rights are inextricably linked to the fee interest is unconvincing. Windpower rights clearly are *894 “substantial” rights and thus may be condemned, or excluded from condemnation, despite their factual novelty under present law.
Vaquero complains that as a result of this partial take, its position has changed from fee owner with full and exclusive power over the use of the property to “an uncompensated lessor of land it does not own, with the theoretical right to develop wind production on someone else’s property.” According to Vaquero, this change of position prevents it from exercising even limited dominion as a lessor because “wind rights are dependent on control of the surface.” Vaquero suggests to the court it can no longer give its windpower lessees authority to construct new windmills or relocate old windmills on land “it no longer owns.”
These arguments are based on the erroneous premise that the Water District has acquired the sole right to occupy and use the entire surface of the land for public purposes to Vaquero’s exclusion. As we have detailed earlier in this opinion, the record reflects otherwise. After the condemnation proceeding Vaquero will own all windpower rights in each of the affected parcels, together with an easement for ingress and egress and such other access rights as may be required for the maintenance and development of these windpower rights. Based on our request for supplemental briefing on the compatibility of the parties’ joint use of the property, we are satisfied that private windpower generation is fully compatible with the Water District’s public uses for the land being taken. The parcels involved are not physically encroached by the intended body of water and instead serendipitously must remain undeveloped to meet the environmental mitigation requirements of the Reservoir Project.
Vaquero’s doubts that it could carry on windpower operations without ownership of the surface rights can be quelled by a simple comparison. It is well settled that subsurface minerals, gas and oil are distinct property rights which may be conveyed separately from the fee.
(Federal Oil Co.
v.
City of Culver City, supra,
179 Cal.App.2d at pp. 96-97;
Kennecott Corp.
v.
Union Oil Co.
(1987)
*895
Even without the assurances of the Water District, the law implies such surface rights of possession as are necessary and convenient to exercise the right to exploit the particular profit, estate or interest reserved. (See
Callahan
v.
Martin
(1935)
In conclusion, Vaquero’s contention that the Water District cannot, as a matter of law, reserve windpower rights from a condemnation of property ignores the solidly established tenet of California law that a condemnation of property for public use need not be unqualified, total, and unconditional. For this reason, the authorities relied upon by Vaquero, which all involve fee simple takings without reservations, have little bearing on the issues at hand. (See
People
ex rel.
Dept. Pub. Wks.
v.
Lynbar, Inc.
(1967)
Improper Precondemnation Conduct
Notwithstanding the trial court’s conclusion that no precondemnation liability was proven under
Klopping
v.
City of Whittier, supra,
As we have noted, the trial was bifurcated, with the first phase limited to a court trial on the narrow issue of whether the Water District engaged in improper precondemnation conduct entitling Vaquero to damages under
Klopping.
(See
Redevelopment Agency
v.
Contra Costa Theatre, Inc.
(1982)
The Water District’s evidence revealed that it was engaged in a project of immense proportions, totaling roughly the square mileage of San Francisco, requiring acquisition of property from many separate ownerships and obtaining numerous permits and approvals legally required to implement such a project. Water District personnel testified that the acquisition of Vaquero’s property was the most difficult and complex property acquisition for the entire project. For example, until mid-1990 the size and configuration of the property required from Vaquero was unknown. The Water District insisted it expeditiously sought to negotiate with Vaquero after the Water District determined the location, exact size, and configuration of the property needed from Vaquero and after it obtained the necessary environmental approvals for the relocation of Vasco Road and approval of specific access to serve Vaquero’s remaining property. The Water District contended that if there *897 was “delay” the delay was reasonable and prudent conduct, given the unique uncertainties and problems that the acquisition of Vaquero’s property posed and that it would have been “foolhardy and rash” to have acquired the property earlier.
The court issued a 25-page statement of decision reflecting a conscientious effort to parse complicated and extensive evidence. It contains the following ultimate finding: “There was neither an unreasonable delay following the resolution of intention to condemn, nor unreasonable conduct, nor unreasonable delay prior to condemnation. Further the court found no damages by loss in market value attributable to any actions of the [Water District]; . . (Original italics.) The court, in effect, found Vaquero had failed to prove any of the essential Klopping components—unreasonable delay, unreasonable conduct, and diminution in market value—which would entitle Vaquero to precondemnation damages.
Whether there has been unreasonable delay by the condemner and whether the condemner has engaged in unreasonable conduct are both questions of fact. (Klopping,
supra,
Vaquero has filed an extensive brief in which it allegedly does not question the sufficiency of the evidence to support the trial court’s findings but contends that the court made certain errors of law which unfairly dictated an erroneous result. Although Vaquero’s arguments are directed toward alleged legal errors in the court’s analysis, when closely examined, they merely reflect disagreement with how the court resolved conflicts in the evidence.
The first alleged “legal error” is assigned to the court’s selection of June 1993 as the commencement date under Klopping for assessing the reasonableness of any delay in pursuing the “take.” The record reflects that on June 9, 1993, the Water District’s board of directors passed a “resolution of *898 necessity,” a necessary precursor before formal condemnation proceedings can be initiated (§ 1240.030). The Water District filed this eminent domain action on June 14, 1993.
The court’s selection of June 1993 was significant because in order to evaluate whether the condemner has unreasonably delayed initiating condemnation proceedings, the finder of fact must establish at what point the governmental entity’s planning activities converted into acquisition activities. As explained by the court in
Terminals Equipment Co.
v.
City and County of San Francisco
(1990)
The trial court correctly noted that the property owners in Klopping were found to have met the official action requirement by showing the governmental entity had issued a formal resolution expressing its intention to acquire plaintiffs’ property. Armed with that knowledge the court here similarly found: “The ‘announcement of intent to condemn’ as defined in Klopping, to wit, a formal resolution to proceed to eminent domain action, was adopted by [the Water District] in this case in June, 1993.”
Vaquero insists the trial court’s “reliance on a formal resolution of condemnation to trigger a
Klopping
violation is pure error.” In arguing the court erred, Vaquero relies upon
People
ex rel.
Dept. Pub. Wks.
v.
Peninsula Enterprises, Inc.
(1979)
In several
post-Peninsula Enterprises
decisions, official action constituting an intent to condemn without a formal resolution has been found where the condemner unduly delayed acquisition proceedings or engaged in other unreasonable conduct which significantly invaded or appropriated the use or enjoyment of private property. (See
Tilem
v.
City of Los Angeles
(1983)
It is significant to note, however, that the
Peninsula Enterprises
doctrine has been invoked sparingly to remedy the most egregious examples of official overreaching. It has been expressly found inapplicable to those situations where the condemning authority “has not acted unreasonably or capriciously, and has followed orderly procedures, . . .”
(Cambria Spring Co.
v.
City of Pico Rivera, supra,
It cannot be said as a matter of law that this dispute is one of the exceptional cases where justice requires the invocation of the doctrine announced in Peninsula Enterprises. The trial court’s final statement of decision properly recognized the critical difference between acceptable planning activities and unacceptable acquisition activities which significantly interfere with the landowner’s interest, finding: “[T]he continuing activities of [the Water District], although lasting beyond their original time table, and although not involving direct communication with the representatives of *900 [Vaquero], were directly aimed at further defining the amount of the necessary take from all the parcels involved, the necessary relocation of Vasco Road, meeting environmental concerns, confronting the many issues raised by the agencies whose permits were required, and seeking financing and other potential partnership arrangements.” The court also noted, “As of the time of this trial, the entire project had still not received all of the final permits and approvals necessary from all of the various agencies involved.” The findings conclude by emphasizing Vaquero’s interest and permissible use of its property had not in any way been changed or reduced by the Water District’s precondemnation activities. In applying Peninsula Enterprises, the court expressly found “neither direct intentional interference” with the exercise of any of Vaquero’s property rights nor conduct “aimed at and/or impinging on the value of the land, short of those acknowledged and permitted” by the case law.
Therefore, the court properly evaluated whether the Water District’s planning activities resulted in the sort of “special and direct interference” with Vaquero’s property which would be legally tantamount to an announced intention to condemn for purposes of establishing delay-based
Klopping
damages. The court’s rejection of this claim was supported by substantial evidence and was in complete conformance with cases finding on similar facts the condemnor’s activities never went beyond the planning stage and did not reach the level of acquisition. (See
Cambria Spring Co.
v.
City of Pico Rivera, supra,
171 Cal.App.3d at pp. 1097-1098 [recordation of redevelopment plan, sale of bonds and application for federal grant did not amount to announcement of intent to condemn];
Smith
v.
State of California
(1975)
As another assignment of legal error, Vaquero claims the trial court’s statement of decision relies too heavily upon the factual justifications for the Water District’s delay and pays too little attention to the impact of these delays on the property owner. Thus, Vaquero contends the court applied an incorrect standard of proof in evaluating its claims citing
Tilem
v.
City of Los Angeles, supra,
As Vaquero’s final assignment of “legal error,” it challenges the trial court’s conclusion Vaquero had not suffered any legally cognizable damages due to the Water District’s precondemnation conduct. Once again, the evidence on this point was highly conflicting. Vaquero attempted to prove the Water District made a calculated decision to interfere with the subdivision potential of its property in order to freeze the property’s value pending acquisition. The court instead concluded that the initial timetables were “overly optimistic.”
The cases which have found legally cognizable damages under
Klopping
are generally ones in which the condemning authorities have acted affirmatively to lower the value of the subject property, physically burdened the property, and/or decreased the income the property produced. (See, e.g.,
Jones
v.
People
ex rel.
Dept. of Transportation
(1978)
The trial court found the evidence in this case disclosed no such actions. Specifically, the court found “no damages by loss in market value attributable to any actions of [the Water District]; fitrther there appear to be no lost rentals or other income, since [Vaquero] continued its farming operations and enhanced its other income by the wind power contracts; . . . .” The claimed loss of potential subdivision development profits was dismissed by the trial court as “purely speculative because [Vaquero] decided not to go ahead.” The court also pointed out that despite Vaquero’s contention that the area was “ ‘ripe for development’ ” because of subdivision approvals granted neighboring property owners, “there had been no lot sales in these areas because of the conditions required by the permits.”
*902
Furthermore, Vaquero misunderstands the reach of
Klopping
in arguing the trial court erred by placing undue emphasis on the existing uses of its property and rejecting Vaquero’s evidence that the Water District’s activities impaired the residential development potential of a portion of the property. Additional precondemnation damages under
Klopping
are only for temporary damage actually suffered during the period of unreasonable delay. To award more based on lost potential would render to the property owner a duplicate recovery when the owner is also awarded the fair market value based on the highest and best use of the property taken in the condemnation action. (See
People
ex rel.
Dept. of Transportation
v.
Diversified Properties Co. III, supra,
At all times during the Water District’s alleged unreasonable activities, Vaquero continued to use the property for cattle ranching and for windpower electrical production. The profitability of these uses remained undiminished during this period. Vaquero conceded during pretrial discovery that the Water District did not interfere with any of the existing uses of its land.
(City of Los Angeles
v.
Property Owners
(1982)
There is no evidence Vaquero ever took any preparatory steps toward developing the property for residential use or selling it to a developer for that purpose. No development applications, proposals, plans or permits were ever prepared or filed with the County of Contra Costa or any other governmental agency. Vaquero never attempted to change the property’s zoning from agricultural to residential. Although Vaquero’s witnesses insisted none of these steps were taken because the Water District’s precondemnation statements and activities made residential development futile, we believe the court was entitled to disregard such assertions, especially considering the *903 fact, highlighted in the court’s findings, that there had been no lots sold in the vicinity of defendant’s property “because of the conditions required by the permits.”
Therefore, there was substantial evidence to support the conclusion that the particular scheme to develop the property existed only in Vaquero’s contemplation and that the opportunity to reap profits from residential development was not lost because of anything the Water District did or did not do. (See
Jones
v.
City of Los Angeles
(1979)
In conclusion, we reject Vaquero’s argument that the trial court’s findings denying a recovery of damages under Klopping demonstrate fatal defects in the court’s reasoning. To the contrary, the court’s factual findings were fully supported by the evidence and guided by legal principles and policies entirely appropriate to precondemnation liability cases as explained in Klopping and its progeny.
Severance Damages
As noted, the fair market value for the property was fixed by the jury at $13,428,327. We need not refer to it further, as this amount is not challenged on appeal. Vaquero challenges the jury’s award of $1 million in severance damages for the diminution in value of the approximately 2,500 acres remaining in its possession. Vaquero claims this amount “was inadequate because there was no basis of any kind in the evidence for such a low award.”
When a condemnation action severs the land by taking only a part of it, the owner may be entitled to an additional sum as compensation for the economic effect of the condemnation on the value of the remaining property. (§ 1263.410, subd. (a).) Severance damages are measured by the difference in value of the remaining portion of the property before and after the taking.
(City of San Diego
v.
Neumann, supra,
6 Cal.4th at pp. 738, 745;
City of Hollister
v.
McCullough
(1994)
Here, witnesses for both Vaquero and the Water District testified to specific dollar amounts of severance damage. The Water District’s experts *904 testified that the severance damages awarded in this case reflected the costs attributable to improving the property’s accessibility after Vasco Road’s relocation. They also testified that the severance damage for this type of loss ranged from $500,000 to $600,000. Vaquero’s experts asserted a completely different theory. They claimed severance damages should be assessed based on the lost potential of the remaining property for use as a landfill site. Vaquero’s witnesses testified the eastern portion of Vaquero’s property was eminently suitable for a landfill but the landfill potential was lost because of the property’s proximity to the Reservoir Project and the possibility of groundwater contamination. Vaquero’s witnesses testified that the severance damage for the loss of landfill potential ranged from $12.7 million to $16.1 million.
The trial court properly instructed the jury they could not return a verdict lesser or greater than the value shown by the testimony of the witnesses. (BAJI No. 11.80) Thus, evidence of severance damages ranged from $500,000 to $16.1 million. The record does not reveal how the jury arrived at $1 million.
Vaquero argues the jury’s award of severance damages is “inadequate and not supported by credible evidence.” Vaquero’s characterization of the award as “inadequate,” indicates the unbelievability of the Water District’s witnesses and the proficiency of its own witnesses. We will not reweigh the evidence nor judge the credibility of witnesses. Vaquero’s argument the jury’s award is “not supported by the credible evidence” is predicated on the assumption that the jury was bound to award an amount only within the two ranges of valuation. In effect, Vaquero argues the jury is prohibited from assessing damages anywhere in the middle of the two opposing theories because such an amount cannot be tied to the valuation testimony of any witness.
In
City of Pleasant Hill
v.
First Baptist Church
(1969)
Disposition
The judgment is affirmed.
Haerle, Acting P. J., and Lambden, J., concurred.
