Continental Heller Corp. v. Amtech Mechanical Services, Inc.Continental Heller Corp. v. Amtech Mechanical Services, Inc.
- Reporters:
- ,
- Before:
- Johnson
OPINION
JOHNSON, J.
In this case, we hold an аgreement by a subcontractor to indemnify a general contractor for loss “which arises out of or is in any way connected” with the subcontractor‘s “acts or omissions” in the performance of its work does not require a showing the subcontractor was at fault in causing the general contractor‘s loss or that its performance was a “substantial” or “predominating” cause of the loss. We also concur in the trial court‘s finding the subcontractor is liable to the contractor for its attorney fees in prosecuting this action to recover under the agreement.
FACTS AND PROCEEDINGS BELOW
In 1978, Oscar Meyer hired the Continental Heller Corporation (Cоntinental) as its general contractor on a project to expand a meat packing plant. Continental subcontracted with the Ralph Manns Company for the installation of an ammonia refrigeration system in the expanded plant. While Manns was working on the refrigeration system, it was acquired by Amtech Mechаnical Services, Inc. (Amtech), which assumed the assets and liabilities of Manns including the subcontract with Continental.
In 1989, an explosion occurred at the plant causing property damage and injuring several Oscar Meyer employees. The explosion was caused by the failure of a valve manufactured by the Wolfе-Linde Company and installed by Amtech in the course of its work on the refrigeration system.
Numerous complaints and cross-complaints followed the explosion. Continental tendered defense of the claims against it to Amtech pursuant to an indemnity agreement contained in the subcontract. Amtech declined to accept the tender of defense. Continental then settled the claims against it for $20,000 and brought this action against Amtech for contractual indemnity seeking to recover the $20,000 settlement plus its costs and attorney fees in defending the claims against it and in prosecuting this action.
Based on the language of the indemnity agreement, which we discuss in detail below, the trial court concluded Continental was entitled to the full recovery it sought from Amtech. The court specifically found Amtech was not negligent in installing the valve and Amtech did not “proximately cause” the leak and subsequent explosion. However, the court concluded, under the indemnity agreement between the parties it was not necessary for Continental to prove fault or a causal connection between the work performed by Amtech and the subsequent leak and explosion in order to establish a duty on the part of Amtech to defend and indemnify Continental. The court awarded
On appeal, Amtech argues to trigger its duty to indemnify Continental there must have been a “failure of performancе in the work” it undertook and this failure of performance must have been a “substantial factor” or “predominating cause” of the loss. Alternatively, it argues Continental was not entitled to attorney fees incurred in prosecuting this action.
For the reasons explained below, we reject both arguments.
DISCUSSION
I. Continental‘s Losses Are Within the Scope of Indemnity Defined in the Contract.
A. The Standard of Review
(1) The parties agree that where, as here, the trial court construed the indemnity provision at issue without the aid of extrinsic evidence the interpretation of this provision is a question of law subject to our de novo review. (Four Star Electric, Inc. v. F & H Construction (1992) 7 Cal. App.4th 1375, 1380 [10 Cal. Rptr.2d 1].)
B. The Scope of Indemnity Under the Contract
(2) Indemnity agreements are construed under the same rules which govern the interpretation of other contracts. (Myers Building Industries, Ltd. v. Interface Technology, Inc. (1993) 13 Cal. App.4th 949, 969 [17 Cal. Rptr.2d 242].) Accordingly, the contract must be interpreted so as to give effect to the mutual intention of the parties. (
(3) “In interpreting an express indemnity agreement, the courts look first to the words of the contract to determine the intended scope of the indemnity agreement.” (Smoketree-Lake Murray, Ltd. v. Mills Concrete Construction Co. (1991) 234 Cal. App.3d 1724, 1737 [286 Cal. Rptr. 435].) The indemnity agreement between Continental and Amtech requires Amtech to indemnify
There is no merit to Amtech‘s contention every cause of action for indemnity requires a showing of fault on the part of the indemnitor. On the contrary, courts will enforce indemnity agreements even for losses caused by acts over which the indemnitor had no control. (See Vinnell Co. v. Pacific Elec. Ry. Co. (1959) 52 Cal.2d 411, 416 [340 P.2d 604].) To the extent the case relied on by Amtech, Gouvis Engineering v. Superior Court (1995) 37 Cal. App.4th 642, 647-648 [43 Cal. Rptr.2d 785], suggests fault is an element of every cause of action for indemnity, the statement is pure dictum and taken out of context. In the present case, Continental‘s entitlemеnt to indemnity does not depend on a showing Amtech was at fault in performing its work on the refrigeration system. Rather, Amtech‘s duty to indemnify Continental applies “to any acts or omissions ... on the part of [Amtech]” not just to its “willful misconduct or negligent conduct.” The language of the agreement leaves no doubt the parties intended Amtech should indemnify Continental irrespective of whether Continental‘s loss arose by reason of Amtech‘s negligence or for any other reason except for the sole negligence or willful misconduct of Continental. (See
Nor has Amtech convinced us we should construe the indemnity agreement to require proоf Amtech‘s performance was a “substantial factor” or “predominating cause” of Continental‘s loss in contravention of the agreement‘s express language providing indemnity for loss which “arises out of or is in any way connected” with Amtech‘s performance.
Amtech maintains limiting its liability for indemnity to cases in which its performance was a “substantial factor” or “predominating cause” in the loss is necessary to conform the agreement to the parties’ reasonable expectations
The parties to an indemnity contract enjoy “great freedom of action” in allocating risk, subject to certain limitations of public policy. (E.L. White, Inc. v. City of Huntington Beach (1978) 21 Cal.3d 497, 507 [146 Cal. Rptr. 614, 579 P.2d 505].) We find the risk allocation in the Continental-Amtech agreement is commercially reasonable given that between Amtech and Continental, the formеr was in the better position to protect against loss arising out of its performance of its contract. This is illustrated by the fact it was Amtech, not Continental, which selected and installed the particular valve which subsequently failed leading to the explosion. Moreover, the language of the agreement at issue — “аrising out of or in any way connected” — is commonly found in indemnity agreements between contractors and subcontractors.3
Furthermore, we are dealing here with two large, sophisticated construction enterprises which could be expected to review, understand and bargain over their indemnity agreement. The record shows the parties did in fact negotiate a number of substantive modificаtions to the contract originally offered by Continental. Thus, unless public policy requires a different result, “[w]hen the parties knowingly bargain for the protection at issue, the protection should be afforded.” (Rossmoor Sanitation, Inc. v. Pylon, Inc. (1975) 13 Cal.3d 622, 633 [119 Cal. Rptr. 449, 532 P.2d 97].)
We find nothing unconscionable about the risk allocation in the agreement. This is not a case of a small-time subсontractor being saddled with ruinous liability for the mere privilege of installing a valve in a meat packing plant.4 As we noted above, Amtech is a large, sophisticated company which had the opportunity to, and did in fact, negotiate the terms of its subcontract with Continental. Moreover, Amtech was paid $1.2 million for its wоrk in remodeling the refrigeration plant.
For the reasons stated above, we conclude the trial court properly awarded Continental indemnity for its losses in the good faith settlement of the claims against it and the costs incurred in defending those claims.
II. The Trial Court Properly Awarded Continental Attorney Fees Incurred in This Action to Enforce the Indemnity Agreement.
(4) Amtech argues even if Continental is entitled to indemnity for its losses, including attorney fees, in defending and settling the claims against it, Continental is not entitled to attorney fees incurred in prosecuting this action. Again, we disagree.
To state the obvious: Whether Continental is entitled to recover attorney fees incurred in enforcing the indemnity agreement, as opposed to recovering attorney fees incurred in defending the underlying claims, depends on the language of the contract.
In the cases cited by Amtech, the contract provisions pertaining to attorney fees were limited to attorney fees incurred in defending against the underlying claims. For example, in Hillman v. Leland E. Burns, Inc. (1989) 209 Cal. App.3d 860, 865 [257 Cal. Rptr. 535] the contract provided only that the indemnitor would indemnify “`against all claims, damages, losses and expenses including attorneys’ fees arising out of or resulting from the performance of the Work.‘” (See also Otis Elevator Co. v. Toda Construction, supra, 27 Cal. App.4th at p. 564; Myers Building Industries, Ltd. v. Interface Technology, Inc., supra, 13 Cal. App.4th at pp. 973-974; Meininger v. Larwin-Northern California, Inc. (1976) 63 Cal. App.3d 82, 84 [135 Cal. Rptr. 1]; County of San Joaquin v. Stockton Swim Club (1974) 42 Cal. App.3d 968, 971 [117 Cal. Rptr. 300].)
In contrast, the contract before us expressly provides for attorney fees incurred as the result of any breach of the contract.
Section 11 of the contract provides: “The Subcontractor specifically obligates itself to the Contractor in the following respects ...:” There follow seven subparagraphs defining the subcontractor‘s obligations. Subparagraph (b) contains the indemnity provision which we have discussed above. Included in that indemnity provision is the obligation to indemnify Continental from all loss, damage, etc., “including attorney‘s fees” which “arises out of or is in any way connected with the performance of work under this Subcontract.” If this was the extent of the сontract‘s provision for attorney fees, we would agree with Amtech that Continental is not entitled to attorney fees incurred in prosecuting this action for breach of the indemnity agreement. There is, however, an additional provision on attorney fees.
Following the last subparagraph, section 11 goes on tо state: ”And the Subcontractor shall indemnify the Contractor, and save it harmless from any
Therefore, the trial court properly awarded Continental attorney fees incurred in prosecuting this action.
DISPOSITION
The judgment is affirmed.
Lillie, P.J., and Woods, J., concurred.
A petition for a rehearing was denied March 13, 1997, and appellant‘s pеtition for review by the Supreme Court was denied May 14, 1997.