119 P.2d 618 | Colo. | 1941
AN action by the Rio Grande Fuel Company, defendant in error, plaintiff below, to enforce liability on a *474 contractor's bond executed by the Continental Casualty Company, plaintiff in error, as surety, in compliance with the provisions of section 6, chapter 39, '35 C.S.A., and which was given to insure the performance of a contract awarded to one Carlson by the State Highway Department. Briefly, the stipulated facts are: That plaintiff furnished and delivered the materials, itemized in a bill of particulars, to Carlson, the contractor, who was made a party defendant, but who made no appearance in the trial court, and does not appear here; that Carlson used and consumed the materials in the performance of the construction contract which was dated November 9, 1936; that the bond in question, among all other conditions, stipulated: "And if the said contractor, his sub-contractor or sub-contractors and each and all of them shall duly pay for all labor, materials, team hire, sustenance, provisions, provender and other supplies used or consumed in the performance of the work contracted to be done or any part thereof, these presents shall become void, otherwise to be and remain in full force and effect"; that the project covered by the contract was duly completed by Carlson, and the state highway engineer gave notice by publication as provided by section 7, chapter 39, '35 C.S.A., that final settlement would be made on and after October 15, 1937; that on the last-mentioned date there was a balance on hand in the State Highway Department of $6,238.23 due said Carlson for the performance of said contract, which balance was withheld by the department as retained percentages under the provisions of said section 7, and was paid over to Carlson by the State Highway Department November 17, 1937; that there was due plaintiff from Carlson the sum of $1,852.53, which was reduced by a dividend from the bankrupt estate of Carlson to the sum of $1,668.18; that plaintiff never at any time filed a verified statement of its claim against Carlson with the State Highway Department, and never filed notice of lis pendens; that on the date of payment to said Carlson *475 November 17, 1937, no claims of any kind or character were on file with the State Highway Department by any persons who had furnished labor or materials for the construction referred to above; that March 25, 1938, Carlson was duly adjudged a bankrupt in the federal court, and that this suit was commenced May 13, 1938. Judgment was entered in favor of plaintiff in the amount stipulated.
Counsel for the surety company contend that plaintiff should not recover for the two reasons alleged as affirmative defenses, that is to say: (1) That plaintiff's failure to file its claim with the highway department within the time prescribed by section 7, supra, to preserve its liens against the retained percentages in the hands of the highway department, released the surety from any liability under the bond; (2) that the failure to file suit against the surety under the bond, within ninety days from October 15, 1937, the date fixed for final settlement, barred plaintiff from maintaining this action by virtue of the provisions of said section 7.
Since the surety company primarily relies upon the second ground, we give it first consideration. This involves an examination of sections 6 and 7, supra, which, owing to their importance to a determination of the issue, we quote in full:
"§ 6. Every contractor to whom is awarded any contract for more than $1,000.00 for the construction, erection, repair, maintenance, or improvement of any building, road, bridge, viaduct, tunnel, excavation or other public work for this state, or for any county, city and county, municipality, school district or other political subdivision of the state, shall, before entering upon the performance of any such work included in said contract, duly execute, deliver to and file with the board, officer, body or person by whom such contract was awarded a good and sufficient bond to be approved by such contracting board, officer, body or person in a penal sum not less than one-half of the total amount payable by *476 the terms of the contract; such bond shall be duly executed by qualified corporate surety, and conditioned for the due and faithful performance of the contract, and providing, in addition to all other conditions, that if the contractor, or his or its sub-contractor or sub-contractors fail to duly pay for any labor, materials, team hire, sustenance, provisions, provender or other supplies used or consumed by such contractor or his or its sub-contractor in performance of the work contracted to be done, the surety will pay the same in an amount not exceeding the sum specified in the bond, together with interest at the rate of eight per centum per annum. Unless such bond is executed, delivered and filed as herein provided, no claim in favor of the contractor arising under such contract shall be audited, allowed or paid.
"§ 7. Any person, co-partnership, association of persons, company or corporation that has furnished labor, materials, team hire, sustenance, provisions, provender or other supplies used or consumed by such contractor, or his or its sub-contractor, in or about the performance of the work contracted to be done, and whose claim therefor has not been paid by the contractor or the subcontractor, may at any time up to and including the time of final settlement for the work contracted to be done, which final settlement shall be duly advertised at least ten days prior thereto by publication of notice thereof at least twice in a public newspaper or newspapers of general circulation published in the county or counties wherein the work was contracted for and wherein such work was performed, file with the board, officer, person or other contracting body by whom the contract was awarded, a verified statement of the amount due and unpaid on account of such claim. And upon the filing of any such claim or claims, such board, officer, person, or other body awarding the contract shall withhold from all payments to said contractor, sufficient funds to insure the payment of said claims, until the same have been paid or such claims as filed shall have *477 been withdrawn, such payment or withdrawal to be evidenced by filing with the person or contracting body by whom the contract was awarded a receipt in full or an order for withdrawal in writing and signed by the person or persons filing such claim, or their duly authorized agents or assigns, provided, that such funds shall not be withheld longer than ninety days following the date fixed for final settlement as published in the manner hereinbefore provided, unless an action shall be commenced within that time to enforce such unpaid claim and a notice of lis pendens be filed with the person or contracting body by whom the contract was awarded. At the expiration of such ninety-day period the person or other body awarding the contract shall pay to the contractor such moneys and funds as are not the subject of suit and lis pendens notices, and shall retain thereafter, subject to the final outcome thereof, only sufficient funds to insure the payment of judgments which may result from such suit or suits. Failure on the part of a claimant to comply with the provisions hereof shall relieve the board, officer, body or person by whom such contract was awarded from all and any liability therefor, payment to the contractor having been made; and further provided, that the provisions of this section shall apply to moneys and funds now or heretofore withheld by a board, person or other contracting body on such unpaid claims, and such ninety-day period for the filing of suits shall commence to run at the time sections 5 to 7 of this chapter shall take effect and become a law. At any time within ninety days following the date fixed for final settlement as published in the manner hereinbefore provided, any person or persons, co-partnership, association of persons, company or corporation, or his, their or its assigns, whose claims have not been paid by any such contractor or sub-contractor, may commence an action to recover the same individually or collectively, against the surety on the bond specified and required in the last preceding section." *478
[1-3] Counsel for the surety company urge that since the remedies afforded persons furnishing labor or materials under a public construction contract are purely statutory, they are absolutely limited by the terms of the statute, and therefore, unless plaintiff brought its suit within ninety days, as provided by section 7, supra, it is barred to sue on the bond. In support of this contention they cite State Board of Agriculture v. Dimick,
[4, 5] Since the benefits of our mechanic's lien act do not apply to projects constructed by governmental agencies, for the protection of those furnishing supplies or material for such projects, the legislature provided a remedy somewhat similar to our mechanic's lien statutes by the enactment of said chapter 39. Western Co. v.Golden,
In view of this conclusion, we deem it unnecessary to consider other questions relating to this issue which are set out and discussed in the briefs.
[6] With respect to the first ground referred to above, is there any merit to the affirmative defense of the surety, that plaintiff's failure to file its claim with the highway department within the time prescribed by section 7, to preserve its lien against the retained percentages in the hands of the highway department, released the surety from any liability under the bond? We think not. The filing of a claim is not mandatory under said section 7, as it is under similar laws of some other states. As already stated, the only penalty fixed by the statute for failure to file such a claim is to release the body awarding the contract from all liability. This is not a case in which complainant is seeking to reach an impounded fund, but is a suit on the bond of the surety, the obligations under which the contractor and the surety assumed pursuant to the requirement of section 6, chapter 39, supra. The failure to file the claim *481 by defendant in error did not discharge the surety from this liability. There is no provision in section 6 or 7 which permits such a construction.
The case of School District v. Denver Pressed BrickCo.,
The judgment is affirmed.
MR. JUSTICE BAKKE and MR. JUSTICE HILLIARD concur.
MR. CHIEF JUSTICE FRANCIS E. BOUCK not participating. *482