CONTANGO OPERATORS, INCORPORATED; Certain Underwriters Severally Subscribing to Combined Cover Note JHB-CJP-1718, Plaintiffs-Appellees v. WEEKS MARINE, INCORPORATED; United States of America, Defendants-Appellants.
No. 14-20265.
United States Court of Appeals, Fifth Circuit.
May 28, 2015.
281
Estes has not alleged facts that, when taken as true, permit the Court to infer that JPMC was a lender or holder of the Note as required to state a claim under
CONCLUSION
For the foregoing reasons, the district court‘s judgment is AFFIRMED.
Matthew Francis Popp, Waits, Emmett & Popp, L.L.C., Jefferson Randolph Tillery, Esq., Jones Walker LLP, New Orleans, LA, Imran Raza Zaidi, Trial Attorney, Matthew Miles Collette, Robert E. Kelly, U.S. Department of Justice, Washington, DC, for Defendants-Appellants.
Before SMITH, PRADO, and OWEN, Circuit Judges.
JERRY E. SMITH, Circuit Judge:*
Weeks Marine, Inc. (“Weeks“), and the United States appeal a judgment holding them 40% and 60% liable, respectively, for damages Contango Operators, Inc. (“Contango“), suffered in a dredging accident. Weeks claims that it was not negligent as a matter of law and, alternatively, that it is only 10% liable. The government urges that an exculpatory clause in Contango‘s pipeline permit precludes holding it liable. We affirm.
I.
In November 2007, Contango obtained a permit from the Army Corps of Engineers (the “Corps“) to build a submarine pipeline in the Gulf of Mexico off the coast of Louisiana. Although the application indicated that the pipeline would cross the Corps-maintained Atchafalaya Channel, the Corps‘s Regulatory Division, which approved the pipeline, mistakenly did not forward that information to the Waterways Division, which provides those details to the engineers who prepare dredging contracts for Corps-maintained channels. In April 2008, Contango finished construction and submitted as-built drawings showing the pipeline‘s placement to other government agencies, including the Minerals Management Service (“MMS“) and the Coast Guard, but not to the Corps.
In August 2009, the Corps awarded Weeks a contract to dredge the channel. The project specifications identified five submarine pipelines in or near the channel, but they omitted the Contango pipeline. At the time, National Oceanic and Atmospheric Administration (“NOAA“) charts also did not include the pipeline. That November and December, however, NOAA published updated versions of the two relevant charts on its website based on information it received from MMS; in December, the Coast Guard announced the addition of the pipeline in a local notice to mariners. Nevertheless, Weeks relied entirely on the specifications to locate pipelines and did not consult other materials for that purpose.
In February 2010, Weeks‘s dredging barge, the G.D. MORGAN, struck the pipeline, rupturing it and causing losses. Contango and its underwriters sued Weeks and the United States, alleging negligence under general maritime law. After a bench trial, the court held Weeks liable for 40% of the damages and the United States liable for 60%.
II.
“The standard of review for a bench trial is well established: findings of fact are
III.
Contango asserts that we lack jurisdiction to consider the issues Weeks raises. Contango‘s theory is that the district court dismissed Weeks‘s indemnification crossclaims against the government for lack of jurisdiction and that Weeks has not appealed that dismissal but is nevertheless attempting to maintain the same claims. But Weeks is not seeking indemnification from the government on appeal; instead, it is merely saying it is not liable to Contango. A ruling that the government is liable and Weeks is not would have the effect of requiring the government to pay for the entire amount of the damages, but that would not be indemnification,4 so we have jurisdiction.
IV.
Weeks challenges the district court‘s ruling that it is liable because it breached its duty of reasonable care by relying solely on the specifications to determine pipeline locations.5 The court recognized that it was common practice in the dredging industry to use only the specifications, but it noted that Weeks easily could have downloaded updated NOAA charts and used local notices to mariners to check for new pipelines. It explained that Weeks should have taken those precautions given the minimal burden of doing so and the risk of causing significant damage by striking a pipeline. We agree.
“[N]egligence is an actionable wrong under general maritime law, and the elements of that tort are ‘essentially the same as land-based negligence under the common law.‘”6 “To state a claim for relief . . . the ‘plaintiff must demonstrate that there was a duty owed by the defendant to the plaintiff, breach of that duty, injury sustained by [the] plaintiff, and a causal connection between the defendant‘s conduct and the plaintiff‘s injury.‘”7 “[T]he appropriate standard of care in an allision case is reasonable care under the circumstances.”8 That duty is “owed only with respect to the interest that is foreseeably
Weeks contends that, under Michigan Wisconsin Pipeline Co. v. Williams-McWilliams Co., 551 F.2d 945 (5th Cir. 1977), the district court‘s factual findings mandate the conclusion that Weeks was not negligent. In its view, that case established that a Corps dredging contractor that justifiably relies on specifications provided by the Corps is not liable for damages that result. Weeks says that rule applies because the district court found that the Corps had omitted the Contango pipeline from the specifications, the custom of the dredging industry was to rely solely on the specifications, and no regulation required the crew of the G.D. MORGAN to carry updated NOAA charts or to review local notices to mariners.
Weeks misreads Michigan Wisconsin. There, a Corps dredging contractor struck a pipeline that had been constructed pursuant to a Corps permit. Id. at 946-47. The specifications had omitted the pipeline. Id. at 948. The pipeline owner sued the dredger, alleging negligence under general maritime law, and the dredger impleaded the government. Id. at 949-50. The district court held the dredger liable but dismissed the third-party complaint against the government. Id. at 950. We affirmed the judgment for the pipeline owner, agreeing with the district court that it was faultless. Id. at 947, 953. As for the third-party complaint, we announced a rule that, “if the [Corps] made a representation to the [dredger] on which the latter was justified in relying, and if that representation was the proximate cause of the injury to [the pipeline owner], then the Government must bear the liability.” Id. at 951. We found those requirements satisfied because the Corps‘s omission of the pipeline from the specifications was a positive assertion of its absence and the dredger had justifiably relied on that representation, because it was not required to investigate the existence of pipelines independently. Id. at 951-53. Accordingly, we reversed the dismissal of the third-party complaint. Id. at 954.
The rule in Michigan Wisconsin governs a dredger‘s claim against the government, not a third party‘s claim against a dredger. If Weeks were maintaining a cross-claim against the government, the government would be liable if the specifications were a representation on which Weeks was justified in relying, and the specifications were a proximate cause of Contango‘s injury. But we have no occasion to consider that question, because the only claims before us are Contango‘s claims against Weeks and the government. Michigan Wisconsin is inapplicable.
Weeks‘s only other argument is that a mistake in the specifications was unforeseeable. The district court‘s implicit finding that Weeks could have anticipated an error was not clearly erroneous, particularly given that there have been other cases involving accidents caused by similar omissions.11 Therefore, the court properly
V.
The only issue the United States raises on appeal is whether the exculpatory clause bars recovery. The provision states in relevant part:
Limits of Federal Liability. In issuing this permit, the Federal Government does not assume any liability for the following:
b. Damages to the permitted project or uses thereof as a result of current or future activities undertaken by or on behalf of the United States in the public interest.
The government submits that the clause applies because the Corps‘s dredging project was an “activit[y] undertaken by or on behalf of the United States in the public interest.” We conclude that the clause does not shield the government from liability in this case.
We interpret a permit in the same manner as we would a contract or other legal document. E.g., Piney Run, 268 F.3d at 269. “[W]e first determine whether it is ambiguous; if ‘the language is plain and capable of legal construction, the language alone must determine’ the permit‘s meaning.” Id. at 269-70 (quoting FDIC v. Prince George Corp., 58 F.3d 1041, 1046 (4th Cir. 1995)). “If [it] is ambiguous, however, then we must look to extrinsic evidence to determine the correct understanding of the permit.” Id. at 270.
The language is clear. The introductory phrase “In issuing this permit, the Federal Government does not assume any liability” (emphasis added) refers only to taking on new liability. Accordingly, the clause means that the permit or its issuance does not provide a basis for liability for the types of damages listed; it does not suggest the government is protected from existing sources of liability independent of the permit.12
The government asks us to consider other evidence despite the disclaimer‘s plain language. It says that, in 1986, the introductory phrase was changed from “the United States shall in no case be liable” to “the Federal Government does not assume any liability” but that a comment published in the Federal Register clarified that the change was not intended to narrow the clause‘s scope.13 Separately,
We decline the government‘s invitation to review those materials. The government offers several reasons we should do so despite the permit‘s clear language, but none is convincing.
To begin with, the government suggests the clause‘s history and regulatory background are not extrinsic. They are. The legal definition of “extrinsic” is “From outside sources; of, relating to, or involving outside matters,”14 and a body of contracts caselaw establishes that “extrinsic evidence” is anything outside a contract itself.15 The evidence the government asks us to examine falls squarely within that definition because it appears in the Federal Register and the Code of Federal Regulations, not in the permit itself.
Next, the government claims that we should interpret a regulation in light of the regulations surrounding it and should defer to an agency‘s reasonable interpretation of its own regulation where it is ambiguous. That may be true, but those rules are inapplicable because we are interpreting a permit, not a regulation.
In addition, the United States urges that, under the parol evidence rule, we may look to extrinsic evidence to prove a meaning to which the provision is reasonable susceptible. Even assuming that principle applies, it does not help the government, because the clause is not reasonably susceptible to the government‘s proposed meaning. See supra note 12 and accompanying text.
Finally, the government says there is “no authority to support the proposition that an agency‘s explanatory comments and regulations can be ignored as ‘extrinsic evidence.’ These are not merely additional documents that may inform a party‘s intent in entering a contract; they are law promulgated by an agency. . . .” The government misunderstands the role of the permit in this litigation. The Corps has a duty of reasonable care under general maritime law,16 and Congress waived sov-
By this reading, the clause does not apply here. The Corps‘s liability was based on its duty of reasonable care under general maritime law, just as Weeks‘s was. The district court held the Corps liable because it had failed to exercise that level of care, as it did not include the Contango pipeline in the specifications or notify Weeks of the omission. Thus, liability was not based on the permit or its issuance.
The government responds that the duty of reasonable care extends only to interests foreseeably jeopardized by the negligent conduct and that the Corps could foresee harm to the Contango pipeline only because of the information Contango provided in its permit application. In the view of the United States, that means the Corps‘s duty to Contango arose out of the permit or its issuance, so the disclaimer applies. The government is correct that foreseeability is required, but the tortfeasor need only be able to foresee jeopardy to the “general class” of interests at issue.19 The district court found that “[a]n allision with a submarine pipeline is a foreseeable consequence of dredging when the dredger is not aware of the pipeline.” That finding establishes that the Corps could have foreseen jeopardy to the general class of interests in question—submarine pipelines—so it had a duty to use reasonable care to avoid harming those interests, a duty that was not based on the permit or its issuance.
The government‘s reliance on Southern Natural Gas, 711 F.2d 1251, for the proposition that the Corps‘s duty was based on permitting regulations is also misplaced. There, a dredger struck a submarine pipeline while working on a private project authorized by a Corps permit. Id. at 1253-54. Based on permitting regulations, we determined that the Corps‘s duty of reasonable care in that situation required it to warn permittees of hazards. Id. at 1154-56. We held the government liable for part of the damages because the Corps had failed to do so. Id. at 1157-59.
But the fact that permitting regulations defined the Corps‘s duty of reasonable care in that case does not mean they did so here. What constitutes reasonable care
Nor was the Corps‘s breach predicated only on its failure to consult the information from Contango‘s permit application when it prepared the specifications. The Corps represented to Weeks that there were no other pipelines in the area, and it knew that Weeks would rely entirely on the specifications. If the Corps could not be sure the specifications were accurate, it should have warned Weeks of that limitation or required Weeks to inspect the site,23 but it did neither.24
Further, the district court found that the Corps was negligent not only in preparing the specifications but also “in failing to warn or notify Weeks Marine of the existence of the Contango Pipeline before Weeks Marine‘s barge struck the pipeline.” The Corps awarded the contract in August 2009, and Weeks struck the pipeline in February 2010. Updated NOAA charts and a local notice to mariners became available in the intervening months, but the Corps neither consulted them nor required Weeks to do so. As a result, the government‘s liability was independent of the permit and its issuance, so the exculpatory clause does not apply.
VI.
Although Weeks claims that it is liable for only 10% of the damages, we accept the district court‘s finding that
It was appropriate for the district court to find that Weeks bore a substantial portion of the responsibility because Weeks was operating the G.D. MORGAN at the time of the accident and the risk of causing substantial damage far outweighed the burden of downloading updated NOAA charts and using local notices to mariners to check for new pipelines. The fact that Weeks followed the custom of the dredging industry is not dispositive, because a common practice can still be negligent.25 Moreover, the Eastern District of Louisiana previously found a dredger liable for 50% of a pipeline owner‘s damages under similar circumstances. See S. Natural Gas, 711 F.2d at 1252 n. 2. Considering Weeks‘s negligence and that caselaw, the district court did not clearly err in finding Weeks 40% liable.
AFFIRMED.
PRISCILLA R. OWEN, Circuit Judge, concurring in part and dissenting in part:
I agree that Weeks Marine, Inc. (Weeks) was properly found liable by the district court for damages that Contango Operators, Inc. (Contango) suffered. However, I do not join in the disposition of the Government‘s appeal. I disagree with the panel majority‘s interpretation of the exculpatory clause in the permit that the United States issued to Contango under
Section 10 of the Act prohibits the creation of any obstruction in the navigable waters of the United States unless the proposed project has been recommended by the chief of the Army Corps of Engineers (the Corps) and authorized by the Secretary of the Army. Contango desired to build a natural gas pipeline in the Gulf of Mexico that would cross the Atchafalaya Pass Channel, a shipping channel that leads from the Gulf of Mexico into the port of Morgan City, Louisiana. Contango applied for and the Government issued a permit allowing the construction of the pipeline.
There is an exculpatory clause in the permit which provides:
3. Limits of Federal Liability. In issuing this permit, the Federal Government does not assume any liability for the following: b. Damages to the permitted project or uses thereof as a result of current or future activities undertaken by or on behalf of the United States in the public interest.
After the pipeline was constructed, the Corps undertook dredging operations in the Atchafalaya Pass Channel and awarded the dredging contract to Weeks. The plans and specifications prepared by the Corps and provided to Weeks specified the location of five pipelines in the Channel but did not include Contango‘s pipeline. Weeks’ dredge struck Contango‘s pipeline, resulting in an explosion and fire. The pipeline was inoperable for 35 days. Contango sued Weeks and the Government for damages, contending that the Government was negligent in failing to identify the existence and location of Contango‘s pipeline on the specifications provided to Weeks.
In holding that this incident did not come within the exculpatory clause in the permit issued by the Government to Contango, the district court placed great weight on the term “assume.” The version of the exculpatory language that had appeared in Section 10 permits prior to the version at issue in this suit had provided that “the United States shall in no case be liable for any damage or injury to the structure or work herein authorized.”1 The district court concluded that “assume” means that the Government does not “take on liability” while the older language indicated that the Government “is not liable for [any] damages” and that the two concepts were distinct.
The panel majority opinion also places considerable weight on the term “assume,” concluding that the phrase “assume any liability” “refers only to taking on new liability.”2 The majority opinion concludes that “the clause means that the permit or its issuance does not provide a basis for liability for the types of damages listed; it does not suggest the government is protected from existing sources of liability independent of the permit.”3
With great respect, I have difficulty following this explanation. The “types of damages listed” in the permit are quite broad. The damages identified are “[d]amages to the permitted project [Contango‘s pipeline] or uses [of Contango‘s pipeline] as a result of current or future activities undertaken by or on behalf of the United States in the public interest.” The reference to “current or future activities undertaken by or on behalf of the United States in the public interest” is also quite broad. That reference is not limited to activities that relate only to the permit.
Even giving the word “assume” a cramped meaning, the Government had no duty to Contango under admiralty law until the Government issued the permit to Contango allowing the pipeline to obstruct navigable waters. The exculpatory clause, fairly read in context, states that in exchange for allowing Contango to construct and operate a natural gas pipeline in navigable waters, the Government is not assuming, that is “taking on,” liability that it would not have had but for the issuance of the permit. In other words, since the only reason that the Government had any duty under admiralty law regarding the pipeline is because the pipeline is in navigable wa-
The majority opinion relies on a decision of the Court of Federal Claims regarding the Section 10 exculpatory clause.4 That was a takings case that is inapposite. In Banks v. United States, owners of property located on the shores of Lake Michigan contended that the Government‘s activities in St. Joseph Harbor had resulted in erosion and that their properties were receding at a rate of two feet per year.5 There were two components of the claims at issue. One was that the Government had installed steel sheet pilings at the St. Joseph Harbor, which the plaintiffs asserted “created a wall blocking the sand that otherwise would have traveled south and protected the shoreline [south of St. Joseph Harbor] from erosion.”6 The second component was that in an attempt to mitigate the erosion, the plaintiffs had placed shore protection, called “revetments,” on their properties.7 The Government contended that it was not liable for erosion that the revetments caused.8 In order to construct the revetments, the plaintiffs had obtained permits under Section 10 of the River and Harbor Act of 1899.9 A threshold issue in the case was whether the erosion caused by the revetments, as distinguished from erosion caused by the steel sheets installed in the harbor, constituted inverse condemnation and therefore constituted a taking rather than a tort.10 The court held that if the facts alleged by the plaintiffs were proven at trial, the erosion caused by the revetments would be a taking rather than a tort.11 In this context, the Government then argued that it was not liable for the erosion caused by the revetments because of the exculpatory clause in the Section 10 permits.12 Unsurprisingly, the Court of Federal Claims concluded that the exculpatory clause was not applicable to a constitutional takings claim. The court said, “it is not legally relevant here whether [the Government] ‘assume[s]’ liability or not.”13 This meant that the court did not even consider whether the Government assumed liability under the exculpatory clause, much less what liability the Government had assumed under that clause. Citing a takings case that held the Government is liable for the cost of protective measures taken by property owners to prevent erosion caused by the Government, the Court of Federal Claims said, “[u]nder Dickinson, [the Government] is liable for all that has been taken as a result of its activities; there is no liability for the government to ‘assume.‘”14 This
The present case is not a takings case. It is a tort case. The tort committed by the Government caused “[d]amages to the permitted project [Contango‘s pipeline] . . . as a result of current or future activities undertaken by or on behalf of the United States in the public interest.” The exculpatory clause applies.
For the foregoing reasons, I concur in part and dissent in part.
*
*
*
*
*
*
