272 F. 625 | 6th Cir. | 1921
On April 11, 1916, the Peninsular Portland Cement Company, of Jackson, Mich., contracted with the Consolidation Coal Company of Baltimore, Md., for the purchase of “55,000 to 60,000 tons of Consolidation Fairmont slack coal, less such amount as said Coal Company is unable to ship or Peninsular Portland Cement Company is unable to receive, on account of any strikes, accidents, contingencies of transportation or navigation, or causes beyond the control of either party affecting the shipment, delivery, or receipt of coal to be shipped under this contract,” shipments to be made to the Cement Company, at Cement City, Mich., “in as nearly equal monthly installments as possible during the period beginning at once, 1916, and ending April 15, 1917, subject to above-mentioned contingencies. Failure to- ship or receive coal on account of any of the above-named contingencies shall not require (or give option to) either party to ship or receive in subsequent months the amount of coal not shipped or received during the period of such contingency.” The price of the coal was 75 cents per ton f. o. b. cars at the mines, payment to be made in cash “on the 15th of each month for the preceding month’s shipments”; the terms of payment being made of the “essence of contract,” and noncompliance therewith giving the seller the privilege of cancellation. During the remainder of April, 1916, and throughout the months of May, June, July, and August, shipments were made only as ordered by plaintiff, which in fact received all the coal it desired during those months, unless, perhaps, to the extent of one car in August. The aggregate amount actually shipped, however, lacked about 4,446 tons of a 'full 5,000 tons per month. In September, 1916, and thereafter, a substantial car shortage existed and coal prices advanced.
A controversy arose as to the amount of future deliveries, plaintiff claiming it was entitled to the entire undelivered remainder of the 60,-000 tons, viz. about 42,000 tons, to be ratably distributed during the remaining 7}/¿ months of the contract period, viz. nearly 5,600 tons per month. Defendant, while admitting plaintiff’s right to 5,000 tons per month during the remaining period (subject to defendant’s asserted right to distribute available cars proportionately among all its customers), denied its obligation to make up1 the deficiencies accumulating during the first 4'l/¿ months, due solely to plaintiff’s failure to order. Shipments were continued throughout the contract period, but in no month to the full amount of even 5,000 tons; the total shortage (including that accruing during the first 4% months) being about 19,-492 tons. Plaintiff sued for its damages on account of this shortage. The ultimate issues upon the trial related to, first, plaintiff’s right to cumulate the shortages for the first 4% months; and, second, defendant’s asserted right to: prorate shipments according to car supply. The jury was instructed that it was defendant’s duty from October 21, 1916, to ship to plaintiff the entire theretofore undelivered remainder
While in the beginning month of April, 1916, it was understood that shipments would be made to meet plaintiff’s requirements, and the latter at first directed shipments on a basis of “4 cars per day, 24 cars per week” (a car was about 50 tons), four days later asking that shipments be reduced to 3 cars per'day, “18 cars per week,” because the “earlier order was more than necessary,” yet, in reply to defendant’s request to be advised of the approximate quantity of coal plaintiff would require, the latter wrote, on May 20th, that as near as it could estimate its requirements it would use the full amount of the contract, and that after approximately August 25th these requirements would be on a basis of 5 cars per day, which in fact would be about 6,000 tons per month, thus necessarily contemplating the making up of shortages. Two days later defendant replied that it was prepáring to carry out plaintiff’s ex
We think defendant could not reasonably have failed to understand from the entix-e correspondence that plaintiff was demanding, and that defendant was assenting to the demand, that plaintiff be given this undelivered remainder of the 60,000 tons, distributed ratably during the remaining mouths of the contract period. This conclusion is confirmed by the fact that on March 10, 1917, on plaintiff advising defendant that there was still a balance unshipped on the contract of 22,423 tons as of March 1st, and calling attention to a discrepancy in the figures furnished by defendant, the latter, under dale of March 15th, replied that, “In checking this over, I find we shipped you, up to March 1st, 38,036.55 tons, a shortage on what you have ordered shipped of 21,963.45. These shortages, as you understand, have been brought about by matters beyond our control, such as embargoes and coal car supply.” It will be noted that the shortage figures above given are on the basis of a full 60,000 tons per year, and would seem consistent only with an accumulation of the shortages during the earlier period. The parties have thus construed the contract as entire, and have treated it as in. full force. Except as the situation may be modified by car shortage, plaintiff was Lhus entitled to recover damages to the extent to which defendant failed to make deliveries. Consumers’ Co. v. Stafford, etc., Co. (C. C. A. 8) 239 Fed. 693, 695, 152 C. C. A. 527.
We think defendant not entitled to complain that recovery was al
There was express testimony of the existence in the coal producing and shipping trade of a general custom, applicable to contracts such-as we have here, to prorate shipments among the producer’s various customers in case of car shortage. The trial judge struck out this evidence of custom, because of opinion that even in its absence it was defendant’s duty to apportion cars available for the purpose among ex
The trial court properly instructed that plaintiff would be entitled to damages if defendant failed to ship coal, not because of a shortage of cars, but because of plaintiff’s refusal to pay an increased price. It was also proper to instruct generally that, unless defendant made an honest effort to put itself into position to deliver all the coal contracted for, the defense of car shortage should be disregarded, and plaintiff should be allowed damages sustained “because of such fault on the part of the defendant.” it was also proper to instruct that if defendant, tor the purpose of getting a higher price for coal, used available cars to deliver spot coal to parties with whom it had no contracts, when coal was due and not delivered to plaintiff, such action would be unfair to plaintiff. Testimony was presented and issues raised thereunder (including an asserted overcontracting by defendant), which made these instructions pertinent. Granted that defendant would normally be entitled to apportion its available cars on the basis of each day’s contract requirements (Luhrig Co. v. Jones & Adams Co., supra; McKeefrey v. Connellsville Co., supra), it does not, however, follow that plaintiff had no right to complain of the making of new contracts under existing circumstances, including the existence of an actual car shortage. Oakman v. Boyce, 100 Mass. 477, 486.
“Plaintiff would be entitled to all cars so used until the contract amount then due had been delivered to plaintiff. Bear in mind I say all of them, and not merely its proportionate share of them. Defendant cannot urge as a de*632 fense that parties with whom it had contracts were entitled to such cars unless they were so used tty the defendant."4
In our opinion the rule so stated savors too much of penalty. Under the rule so given, not merely plaintiff, hut every contract purchaser similarly situated, could visit like penalty upon defendant. We think it clearly an erroneous view that plaintiff was entitled to damages for failure to receive cars which others should have received. Upon this record this instruction may well have prejudiced defendant.
“If it [plaintiff] bad delivered to tbe defendant bis proportion of existing and available supplies, then it was excused by tbe strike from any further performance of tbe contract. If it bad not delivered to tbe defendant bis due proportion, then to tbe extent to wbicb tbe defendant bad been damaged by sucb failure it was liable and tbe defendant could recover.”
And see Jessup v. Piper, supra, 133 Fed. at page 111.
The charge contains some statements which suggest a contrary view. For example, the instruction that plaintiff should recover damages for breach of the contract unless there was finding in favor of defendant on all three points submitted, which included not only good faith and reasonable care in the taking of the contracts, honest effort, and reasonable diligence to secure sufficient cars to fill them, but (3) “the distribution of the cars which defendant actually got for its own use among its different customers so that this defendant [plaintiff?] received its fair share under the law as I have stated it to you.”
Upon this record we see no merit in defendant’s proposition that it was plaintiff’s duty to furnish the cars for its coal shipments. The dealings of the parties, including their pleadings herein, have foreclosed that question. Producers’ Coke Co. v. McKeefrey Iron Co. (C. C. A. 3) 267 Fed. 22, 28.
3. Plaintiff suggests that this case is one for the application of section 269 of the Judicial Code (as amended February 26, 1919, 40 Stat. c. 48, p. 1181 [Comp. St. Ann. Supp. 1919, § 1246]), which provides that on the hearing of “any * * * writ of error * * * in any case, civil or criminal, the court shall give judgment after an examination of the entire record before the court, without regard to technical errors, defects, or exceptions which do not affect the substantial rights of the parties,” which section in effect forbids any ef-
We have not attempted to discuss more than a small number of the errors assigned. Our views upon the questions not so discussed, should they arise upon a new trial, would seem sufficiently indicated by what is said generally in the opinion.
The judgment of the 'District Court is accordingly reversed, and the record remanded to that court, with instructions to award a new trial.
Plaintiff also claimed special damages for loss of profits, but this claim was rejected by tbe trial court and is not involved bere.
For example, shortages due to failure to order are not included in the express noncumulating provision respecting shortages due to contingencies of transportation, strikes, etc.
All italics in tbis. opinion onrs.
We tbink tbis point sufficiently saved. Altbougb tbe exception to tbe charge itself was not very definite, viz: “to tbe charge in reference to prorating subsequent to October 21,” yet there bad been exception to refusal of defendant’s requests wbicb raised tbis very point, and error is assigned thereon.