OPINION DENYING MOTION FOR REHEARING
Consolidated Petroleum Partners I, L.L.C. filed an amended motion for rehearing, which is denied. We withdraw our opinion dated April 29, 2005 and substitute the following opinion in its place.
Consolidated appeals the trial court’s partial summary judgment entered in favor of Tindle. 1 Consolidated raises four issues on appeal. We affirm.
*896 Background
On June 15, 2001, Tindle and Consolidated entered into a written agreement governing the acquisition and disposition of certain oil, gas, and mineral leases in the Weesatche Area (“WA”) of Goliad County. Paragraph 5 of the agreement set forth that Tindle would fund a portion of the estimated WA leasehold acquisition costs as follows:
5. Participant agrees to provide funding in the amount of $200,000 contemporaneously with execution and delivery of this Agreement. The amount funded and the considerations provided above are in contemplation of funding a portion of the $494,187.29 amount shown on Exhibit A. ($200,000 Divided by $494,187.29 equals Participant’s .404704% of 8/8ths ownership in WA)[.] Participant and CPP agree that the Amount shown on Exhibit A is an estimate based on negotiated terms and is subject to modifications, however[,] participant in no way is obligated to fund in excess of the $200,000 amount unless mutually agreed upon.
The parties further agreed that Tindle would be entitled to the following compensation:
[[Image here]]
lb. Reimbursement of lease acquisition costs (based on Participant’s factor of .404704% of 8/8ths) funded by Participant attributable to each lease;
[[Image here]]
Id. The overriding royalty interest ... will be delivered to Participant as soon as reasonably practical after lease acquisition. With respect to the cash consideration provided in [Paragraph lb above], such amounts (determined on a lease by lease basis) will be paid to Participant upon the earlier to occur of (i) disposition of such lease or (ii) inclusion of such lease within a drilling unit by CPP. For these purposes, disposition of a lease means a sale of a lease to a third party.
Consolidated entered into similar agreements with other participants, who contributed various percentages of the total leasehold acquisition cost. 2
Consolidated acquired multiple leases in the WA, but, following the drilling of a dry hole, sold all of the leases to a third party for $275,000.00. Subsequently, Consolidated distributed a portion of the sales proceeds to Tindle in the amount of $86,689.40.
Tindle filed the instant suit claiming Consolidated breached its contract with him by not repaying him the $200,000.00 he contributed toward the leasehold acquisition costs. Tindle subsequently moved for partial summary judgment on his breach of contract claim. Consolidated responded to Tindle’s motion, contending not only that Tindle’s interpretation of the contract was flawed, but also that the total leasehold acquisition costs were greater than the estimated $494,187.29 figure upon which Tindle’s participation factor was based and were, in fact, $613,544.27.
On March 19, 2003, the trial court conducted a hearing on Tindle’s motion for partial summary judgment. On March 21, 2003, the trial court granted Tindle’s motion, ordering that he be awarded the difference between his $200,000.00 funding contribution and the $86,689.40 already *897 paid to him by Consolidated. The court reserved issues pertaining to attorney’s fees and the value of the overriding royalty interest for trial. 3
Tindle later nonsuited his claims related to the respective values of the mineral acreage fee and the overriding royalty interest. On August 4, 2003, a trial was conducted on attorney’s fees. The trial court signed its final judgment on August 5, 2003, in which it awarded Tindle breach of contract damages of $113,311.00, attorney’s fees for both trial and appeal, and both prejudgment and post-judgment interest. Consolidated filed a motion for new trial, which the trial court denied. This appeal followed.
Standard of Review
In reviewing a traditional motion for summary judgment, this court must apply the standards established in
Nixon v. Mr. Property Management Co.,
1. The movant for summary judgment has the burden of showing that there is no genuine issue of material fact and that it is entitled to judgment as a matter of law;
2. In deciding whether there is a disputed material fact issue precluding summary judgment, evidence favorable to the non-movant will be taken as true;
3. Every reasonable inference must be indulged in favor of the non-movant and any doubts resolved in its favor.
See id.; May v. Nacogdoches Mem’l Hosp.,
Once the movant has established a right to summary judgment, the nonmovant has the burden to respond to the motion for summary judgment and present to the trial court any issues that would preclude summary judgment.
See, e.g., City of Houston v. Clear Creek Basin Authority,
*898 Contractual Interpretation
In its first and second issues, and in portions of its third and fourth issues, Consolidated argues that the trial court erred in granting Tindle’s motion for partial summary judgment because it improperly interpreted the contract between the parties and, as a result, improperly awarded damages to Tindle. Specifically, Consolidated argues that the agreement did not obligate it to repay Tindle the entirety of his funding contribution toward the lease acquisition costs if the leases were sold for a loss, but rather, Tindle was only entitled to be reimbursed the percentage of his participation factor based on sales proceeds from the leases as each was sold. Consolidated also argues that a material fact issue existed as to the leasehold acquisition costs and, therefore, as to the percentage comprising Tindle’s participation factor.
In construing a written contract, the primary concern of the court is to ascertain the true intentions of the parties as expressed in the instrument.
Coker v. Coker,
If the written instrument is so worded that it can be given a certain or definite legal meaning or interpretation, then it is not ambiguous, and the court will construe the contract as a matter of law.
Coker,
The interpretation of an unambiguous contract is a question of law, which we review de novo.
See MCI Telecommunications Corp. v. Texas Utilities Elec. Co.,
In interpreting a contract, we must presume that the parties thereto intended every clause to have some effect; therefore, we consider each part of the document with every other part of the document so that the effect and meaning
*899
of one part on any other part may be determined.
See Bimbaum v. Swept LP,
Tindle’s “participation factor” is explained in paragraph 5 of the agreement. The participation factor is a percentage determined by dividing Tindle’s funding contribution, $200,000, by the total leasehold acquisition costs, which were estimated in the agreement, but had yet to be finally determined at its signing.
The compensation at issue relates to the amount of “reimbursement” due Tindle of the leasehold acquisition costs. According to paragraph lb, this compensation is based on Tindle’s participation factor. The agreement further states that such compensation will be determined on a lease by lease basis and paid to Tindle upon the sale of the lease to a third party. It is undisputed that all leases at issue were sold to a third party.
Consolidated argues that the intent of the parties, as evidenced by the language of the agreement, was that, upon the sale of each lease, Tindle would be reimbursed a portion of the sales proceeds based on his participation factor. Tindle argues that the agreement’s language evidences the parties’ intent that Tindle be reimbursed the portion of the lease acquisition costs he funded attributable to each lease at the time that lease was sold to a third party. Having read the agreement, we agree with the parties that the agreement is not ambiguous. However, we are unable to conclude that Consolidated’s interpretation of the contract language is reasonable.
The agreement never references “sales proceeds.” While paragraph Id of the agreement states that the compensation due Tindle is to be paid upon the sale of the lease to a third party and determined on a lease by lease basis, such language does not serve to alter the manner of calculating the amount of reimbursement owed Tindle for his contribution to the total lease acquisition costs as outlined in paragraph lb. The language used in paragraph Id, given its plain meaning, does not contradict the language used in paragraph lb.
Paragraph lb plainly states that Tindle will receive reimbursement of the lease acquisition costs he funded, which, as paragraph 5 states, is determined by multiplying the total lease acquisition costs by Tindle’s participation factor. To “reimburse” means “to pay back or compensate (a person) for money spent, or losses or damages incurred.” The AmeRican HeRItage DictionaRY 1042 (2nd Col. Ed.1982). Thus, Consolidated was obligated to repay Tindle the portion of the lease acquisition costs he funded.
*900 Paragraph Id sets forth when the compensation in paragraph lb will become due and owing. It states that such compensation will be paid on a lease by lease basis when the leases are sold to a third party. Since multiple leases are contemplated earlier in the agreement, it is reasonable that the total compensation from paragraph lb would not be due upon the sale of the first lease if the remaining leases had yet to be sold. Rather, as the agreement states, such compensation would be paid on a “lease by lease basis.” As Consolidated notes in its brief, were the leases not sold to a third party, Tindle would not be entitled to payment.
We next consider whether the trial court properly awarded Tindle $113,311.00. Consolidated argues that a material fact issue existed as to the lease acquisition costs and, thus, as to the percentage comprising Tindle’s participation factor as well. However, the amount Tindle funded, $200,000.00, is a constant. Thus, no matter what the total lease acquisition costs were, when the amount of lease acquisition costs is multiplied by the percentage determined from dividing $200,000 by the lease acquisition costs, the product will always be $200,000.00. 5 Therefore, while there may exist a fact issue as to the amount of the total lease acquisition costs, that fact issue is not material as it has no bearing on the amount of money to which Tindle was entitled as reimbursement pursuant to the agreement.
The record in the case at hand reflects that upon the sale of all the subject leases, Consolidated paid Tindle $86,689.40. The contract indicates that upon the sale of the leases, Consolidated was to pay Tindle the portion of the lease acquisition costs he funded, $200,000.00. Thus, since there was a breach of the agreement by Consolidated, the trial court’s award of $113,311.00 allowed Tindle to receive the benefit of the bargain.
6
See,
e.g., Prudential Securities, Inc. v. Haugland,
Attorneys’ Fees
In parts of its third and fourth issues, Consolidated states that the trial court erred in awarding attorney’s fees to Tin-dle. From our reading of Consolidated’s brief, it appears that Consolidated’s claim that Tindle is not entitled to recover attorney’s fees is dependent on our disposition of issues one and two and the portions of issues three and four as set forth above. Inasmuch as we have overruled the aforementioned issues concerning the trial court’s grant of summary judgment in Tin-dle’s favor, it follows that we cannot sustain Consolidated’s issues concerning Tin- *901 die’s entitlement to recover attorney’s fees as part and parcel to its claim that Tindle is not entitled to summary judgment. In its brief, Consolidated has not argued that there is a lack of evidence to support Tindle’s entitlement to attorney’s fees apart from its contentions that the trial court’s grant of summary judgment on Tindle’s breach of contract claim was improper. See Tex.R.App. P. 38.1(h). The remainder of Consolidated’s third and fourth issues are overruled.
Disposition
Having overruled Consolidated’s issues one, two, three, and four, we affirm, the trial court’s judgment.
Notes
. Other fact issues reserved for trial were dismissed by Tindle prior to Consolidated’s appeal.
. The parties disagree as to the amount of the lease acquisition costs. Consolidated submitted summary judgment evidence that the lease acquisition costs were $613,544.27 with a participation factor of 32.59%. Tindle submitted summary judgment evidence that the lease acquisition costs were $494,187.29 with a participation factor of 40 .4704%.
. The trial court further awarded Tindle the value of a mineral acreage fee in the amount of $11,161.00. However, upon consideration of a revised order submitted by Tindle, the court reserved the issue concerning the value of the mineral acreage fee for trial in addition to other fact issues previously reserved. Thus, with regard to his reimbursement claim for lease acquisition costs, Tindle was awarded $113,311.00.
. For example, if a contract called for goods to be delivered to “the green house on Pecan Street,” and there were, in fact, two green houses on Pecan Street, a latent ambiguity would arise. See id. n. 4.
. For example, if X/Y = Z, then (Z)(Y) = X. The parties agree that X = $200,000.00. If, as Consolidated argues, Y = $613,544.27, then Z = 0.325975. If, as Tindle argues, Y = $494,187.29, then Z = 0.404704. Yet, in either scenario X = $200,000.00 Such is the case no matter what value is attributed to Y.
. We recognize that the sum of $86,689.40 and $113,311.00 exceeds the $200,000.00 to which Tindle was entitled by $0.40. Consolidated has not addressed this particular discrepancy in its brief and has therefore waived its consideration on appeal. See Tex.R.App. P. 38.1(h).