470 U.S. 1075 | SCOTUS | 1985
Dissenting Opinion
dissenting.
The Public Utility Regulatory Policies Act of 1978, Pub. L. 95-617, 92 Stat. 3117 (PURPA), is part of a broad congressional
Pursuant to § 210(a), FERC requires utilities to purchase electricity from qualifying facilities. See 18 CFR §292.303(a)(1984). In an apparent effort to encourage decentralized power production as much as possible, FERC adopted the maximum rate allowed by the statute — the incremental, or “full avoided cost,” standard — for such purchases. See § 292.304(b)(2); see also 45 Fed. Reg. 12214, 12222 (1980). We upheld its choice in American Paper Institute, Inc. v. American Electric Power Service Corp., 461 U. S. 402 (1983).
Though PURPA is a federal statute whose administration lies with FERC, “implementation” of the statute is left in large measure to the States. See § 210(f), 16 U. S. C. §824a-3(f); 18 CFR §292.401(1984). Thus, a State can, under certain circumstances, set rates that are lower than full avoided costs, 18 CFR §292.304(b)(3)(1984); a qualifying facility and a utility can negotiate for lower rates( § 292.301(b)(1); and the state regulatory authority or any nonregulated utility may apply to FERC for a waiver, § 292.403. The question in the present case is just how far a State can go in the other direction. In particular, the question is whether a State can require utilities to pay more than the full avoided cost rate for their mandatory purchases.
New York has set a minimum rate of six cents per kilowatt hour for utility purchases from qualifying facilities. N. Y. Pub. Serv. Law §66-c (McKinney Supp. 1984-1985). Appellant challenged the law, arguing that it could not be required to pay six cents per kilowatt hour for the times when its avoided costs fell below that amount. The Appellate Division of the New York Supreme
The New York Court of Appeals reversed, 63 N. Y. 2d 424, 472 N. E. 2d 981 (1984), viewing the state and federal laws as complementary rather than conflicting. The court read both the statute and the legislative history to intend a cap only on rates set by FERC, and noted that the New York statute was consistent with the federal Act’s overall purpose. It also pointed out that FERC, in explaining its regulations, had said that “the States are, free under their own authority, to enact laws or regulations providing for rates which would result in even greater encouragement of these technologies,” and that only state rates below the federal rate would have to “yield to federal law.” 45 Fed. Reg., at 12221.
In upholding the New York statute, the Court of Appeals reached a conclusion in conflict with the Kansas Supreme Court. See Kansas City Power & Light Co. v. Kansas Corporation Comm’n, 234 Kan. 1052, 676 P. 2d 764 (1984). Relying on the statement in American Paper Institute that the avoided cost rate “applies in the absence of a waiver or a specific contractual agreement,” 461 U. S., at 416, the Kansas court held that the state regulatory commission could not set rates for purchases from cogenerators that were higher than avoided cost.
There is no reconciling the decisions of these two state courts of last resort. Both rest on plausible arguments. The question over which they are divided, and which, in the posture of this case, falls
The federal question here is thus “substantial” in two senses — it is both open to debate and important. I dissent from the Court’s conclusion to the contrary.
Commentator8 have relied on these statements to conclude that the States can set higher rates. E. g., Cornell, A PURPA Primer, 3 Solar L. Rep. 31, 53 (1981); Lock, Statewide Purchase Rates Under Section 210 of PURPA, 3 Solar L. Rep. 419, 445-450 (1981).
Lead Opinion
Appeal from Ct. App. N. Y. Motion of Edison Electric Institute for leave to file a brief as amicus curiae granted. Request of counsel for appellant to delete Brooklyn Union Gas Co. as a party to this proceeding denied. Appeal dismissed for want of substantial federal question.