512 F.2d 1332 | D.C. Cir. | 1975
Petitioners in these cases are customers of natural gas pipelines subject to the jurisdiction of the FPC. The three pipelines involved, Transcontinental Gas Pipe Line Corporation (Transco),
The background of Order No. 467 is set out in our opinion in Pacific Gas and Electric Co. v. FPC.
Order No. 467 was issued January 8, 1973. At the time Panhandle was curtailing under an interim plan which it had negotiated among its customers, pending the outcome of hearings on a proposed permanent plan which the pipeline had filed with the FPC in 1971. The interim settlement plan expired by its own terms on October 31, 1973. On October 1, Panhandle filed an interim plan patterned after Order No. 467. It requested the Commission to allow this plan to go into effect on November 1, 1973, in time for the 1973-74 heating season, if the Commission refused to extend “the present curtailment procedures.”
Transco too was operating under an interim settlement plan during the winter of 1972-73. This arrangement expired by its own terms on November 15, 1973, and required Transco to file a permanent plan with the Commission no later than May 1, 1973. In May 1973 the FPC denied a motion by the pipeline to extend the interim plan for another year.
Southern found itself in a somewhat different posture when Order .No. 467 was handed down. It was then curtailing under a permanent plan which it had filed in 1971 and on which hearings before the FPC had already been held although no decision had been reached. The FPC’s staff moved to reopen the hearing record and to require Southern to file a 467 plan. The Commission ordered the record reopened but denied the second half of the staff’s request with the recitation that Order No. 467 was a guide rather than a rule.
After filing their appeals, petitioners in each case moved for a stay pendente lite. In two cases, those involving Transeo and Southern, stays were granted.
The central importance which relief pending decision has assumed in these cases is indicative of the nature of the underlying litigation. The petitioners do not contest the authority of the FPC to impose a 467-type plan on the pipelines after evidentiary hearings and decision on the record. But they do contest the Commission’s power to take the steps which it has taken in shaping the curtailment practices of pipelines during the interim. Hearings before the Commission have since been completed in each of these cases, with final decisions possible in time for the 1975-76 heating season.
Section 4 of the Natural Gas Act
In FPC v. Louisiana Power and Light Co.,
Moss involved a statutory scheme very similar to the one we have examined here. Under the Federal Aviation Act, fares can be set by the carrier or by the CAB.
In the Moss case, the Board had concluded, after repeated ex parte meetings with the carriers, that an increase in fares was warranted.
In clarifying the operation of 467, the FPC acknowledged that the pipelines were “still free to file tariff changes under Section 4 in whatever form they choose.”
The source of the agency’s leverage is less obvious in these cases than in Moss. The pipelines appear to have little direct stake in whether they curtail under a 467 plan or any other plan. As we noted in Pacific Gas and Electric Co.,
Clearly the pressure was on. But our task remains to assess, by what crude means we have at our disposal, the actual impact of that pressure on the pipelines’ ability to choose among alternatives.
It is also significant, in attempting to assess the practical scope of the discretion retained by the pipelines, that Order No. 467 did not cover all aspects of curtailment policy.
This evidence of a degree of independence and flexibility on the part of the pipelines leads us to view the problem in broader perspective. Regulation through “raised eyebrow” techniques seems inherent in the structure of most administrative agencies, combining as they do both policy-making and adjudicative functions. Short of sweeping condemnation of “the system,” judicial attempts to control it must be sensitive to the particular regulatory context in which it occurs, the interests affected by it,
And in these cases, we do not find abuses of the sort we faced in Moss. There the court observed that the agency’s dealing appeared to favor regulated concerns at the expense of consumers. Against this background, we stressed that the CAB’s rate formula was the product of behind-the-scenes bartering between the agency and the carriers, and that none of the tariffs filed consistent with the CAB’s formula were subject to investigation after they became effective. By contrast, the issues in these cases cannot be put comfortably in terms of “-whether the regulatory agency is unduly oriented toward the interests of the industry it is designed to regulate.”
We admit to a certain uneasiness at this juncture, however. As the Su
II.
As an alternative to an immediate implementation of a 467-type plan, both Panhandle and Transco moved the Commission for an extension of the negotiated interim plans then in effect, pending the selection of a permanent plan after hearings. Petitioners in those cases contend that the FPC’s denial of the motions to extend violated Michigan Consolidated Gas Company v. FPC.
There is little question that the plans which Panhandle and Transco sought to have extended were settlement proposals within the broad terms of Michigan Consolidated. Both had the support of most, if not all, of the parties, and both offered an interim solution which had been operationally tested. Whether these proposals received the kind of consideration to which they were entitled under the circumstances presents an interesting question.
III.
Petitioners in the Panhandle and Transco cases also attack the FPC’s determination to allow the pipelines’ 467 to go into effect in time for the 1973-74 heating season, as the interim regimen. That determination was arbitrary, petitioners contend, because the data available for implementation of those plans was inadequate and untested, and there was no preliminary finding that the 467 schedules were nondiscriminatory. We may take this as a more modest formulation of the arguments with which we dealt in Part I: even though the agency may not have been required to hold fullblown hearings in these cases under section 5, it was obligated to make a threshold investigation of possible weaknesses and inequities in the 467 filings prior to their being effectuated by the pipelines. As the Fifth Circuit noted recently in dealing with the same issue, section 4 of the Natural Gas Act does provide that a decision to suspend a company’s filing must be accompanied by “a statement in writing of its reasons for such suspension.”
IV.
Petitioner Battle Creek Gas Co. advances the contention that the FPC erred in treating Order No. 467 as a substantive rule. In Pacific Gas and Electric Co., we faced a challenge to the lawfulness of 467 based on the Commission’s failure to comply with the notice and comment requirements established by the Administrative Procedure Act. We found that 467 was exempt from these requirements because the Commission’s order, by its own terms, had “no final, inflexible impact upon the petitioners.”
since the statement will be applied prospectively, the courts are in a position to police the Commission’s application of the policy and to insure that the Commission gives no greater effect to Order No. 467 than the order is entitled to as a general statement of policy.74
We think petitioner’s claim, as it may relate to the FPC’s rejection of interim alternatives, is precluded by our discussion in Part II. As it may relate to the agency’s pressuring pipelines to file 467-type plans, it appears to be a restatement of the Moss argument dealt with in Part I, and we reject it for the same reasons. But this does not end the policing function of the courts contemplated by Pacific Gas and Electric Co. Final orders of the Commission implementing permanent curtailment plans will be subject to review, at which the agency “must be prepared to support the policy [of 467] just as if the policy statement had never been issued.”
V.
“End use,” as defined by the Commission, is the use made of gas by the ultimate consumer. The ultimate consumer may purchase directly from the pipeline or indirectly from a customer of the pipeline. Order No. 467 states that direct and indirect customers will be placed in the same priority-of-service position when their use of gas is comparable. Battle Creek Gas Co. makes the novel claim that this arrangement is impermissible because “the Commission has no jurisdiction to prevent discrimination between direct and indirect customers using natural gas supplied by Panhandle.”
VI.
Petitioners in the Transco and Panhandle cases raise a claim under section 102(2)(C) of NEPA, which requires that an environmental impact statement accompany agency proposals for “major Federal actions affecting the quality of the human environment.”
the Commission’s duty under the Natural Gas Act to prevent discriminatory practices in times of natural gas shortage called for prompt action. This created the type of ‘statutory conflict’ which alone can excuse compliance with section [102(2)(C)].81
Petitioners seek to distinguish American Smelting on the grounds that the pipeline in that case had no plan in operation prior to the one imposed by the Commission. In these cases, they argue, interim plans which had proved workable were in effect; thus, exigent circumstances did not exist to justify non-compliance with the statute. But all this ignores the fact that the plans in effect on the Transco and Panhandle systems expired by their own terms prior to the winter of 1973-74. The Commission was required to act, and to act promptly: there is no suggestion here, as there was in American Smelting;
We do not go so far as the Fifth Circuit appears to have gone in declaring recently that “it is well-settled that the FPC is not required to file impact statements for interim curtailment plans.”
VII.
We have examined the remaining contentions of the petitioners and have found them without merit.
. No. 73-1999, Consolidated Edison Co. v. FPC; No. 73-2017, North Carolina v. FPC.
. No. 74-1150, Alabama Gas Corp. v. FPC; No. 74-1200, Atlanta Gas Light Co. v. FPC.
. No. 74-1184, Battle Creek Gas Co. v. FPC; No. 74-1231, Michigan Consolidated Gas Co. v. FPC.
. Statement of Policy, Utilization and Conservation of Natural Resources — Natural Gas Act, Order No. 467, Docket No. R-469, 49 F.P.C. 85 (1973). Order No. 467 was subsequently clarified and amended in Order No. 467-A, 49 F.P.C. 217 (1973), and in Order No. 467-B, 49 F.P.C. 583 (1973). These orders will be referred to collectively as Order No. 467, or simply 467, unless otherwise necessary for clarity.
. 164 U.S.App.D.C. 371, 506 F.2d 33 (1974).
. 49 F.P.C. at 87.
. The priorities of service distinguished between users operating under “interruptible” contracts and those with “firm” requirements. The validity of this distinction, in the particular circumstances of the Transco case, was brought into question in our per curiam of November 26, 1974, in these cases. Consolidated Edison Co. v. FPC, No. 73-1999, 167 U.S.App.D.C. 134, 141-142, 511 F.2d 372 at 379-380. Further gradations among consumers were based on daily volumes of use.
. 49 F.P.C. at 585.
. Jt.App. 275 (Nos. 74-1184, 74-1231).
. Order Accepting and Making Effective Tendered Curtailment Plan, Denying Motion for Extension of Interim Curtailment Plan, and Granting Interventions, Docket No. RP 71-119, Jt.App. 371 (Nos. 74-1184, 74-1231).
. Order Denying Applications for Rehearing, Docket No. RP 71-119, Jt.App. 424 (Nos. 74-1184, 74-1231).
. Order Denying Motion for One-Year Extension of Interim Curtailment Plan and Providing for Filing of Curtailment Plan, Docket No. RP 72-99, Jt.App. 42 (Nos. 73-1999, 73-2017).
. Jt.App. 51 (Nos. 73-1999, 73-2017).
. Order Denying Motion for Reconsideration, Permitting Intervention, Fixing Date of Hearing, Specifying Procedures, and Suspending Proposed Revised Tariff Sheets, Jt.App. 55 (Nos. 73-1999, 73-2017).
. Order Reopening Record to Receive Additional Evidence and Denying Motion to Omit Intermediate Decision, Docket No. RP 72-74, Jt.App. 25 (Nos. 74-1150, 74-1200).
. Brief for Respondent FPC, Apps. C-D (Nos. 74-1150, 74-1200). Technically the Commission does not have authority under the Natural Gas Act to “reject” a proposed filing, although it may suspend a filing for a period of months, or after hearing, replace a filing with a tariff deemed just and reasonable by it. See text accompanying notes 24-26 infra. In this case, however, Southern had requested the Commission to “reject this filing” if not in compliance with Order No. 467 and to “advise Southern, how this filing should be modified so as to be in full compliance with such orders.”
. Order Accepting for Filing Tendered Tariff Sheets, Suspending Tariff Sheets, Granting Interventions, Denying Motion to Reject, Consolidating Dockets, Providing for Hearing and Establishing Procedures, Jt.App. 70 (Nos. 74-1150, 74-1200).
. Order Denying Petitions for Rehearing and Request for Stay and Granting Untimely Intervention, Jt.App. 108 (Nos. 74-1150, 74-1200).
. See Consolidated Edison v. FPC, supra note 7, 167 U.S.App.D.C. at 139 & n. 4, 511 F.2d at 377.
. Consolidated Edison v. FPC, supra note 7.
. Id. at 10.
. The terms of our stay were subject to modification by the Commission on certification to this court and after the court’s approval thereof. On January 10, 1975, the Commission reviewed the new interim settlement arrangement on rehearing, finding it unlawful due to a compensation scheme embodied in it, but did not purport to disturb the operation of that plan pursuant to our orders. Order Granting Rehearing in Part, Denying Rehearing in Part, and Requiring Environmental Impact Statement, Docket No. RP 72-99, reprinted in Motion of North Carolina Petitioners to Modify Stay and Request for Expedited Consideration, App. V (Nos. 73-1999, 73-2017) [hereinafter cited as Order of Jan. 10, 1975].
. Id. at 15. A recent submission by petitioners in a separate but related appeal, Motion for Expedited Briefing Schedule and Oral Argument, Transcontinental Gas Pipe Line Corp. v. FPC, No. 74-2036 (D.C.Cir.), stated that “[i]t is highly unlikely that the Commission will be able to prescribe a permanent plan in time for next winter.”
. 15 U.S.C. § 717c (1970).
. The Commission’s power to suspend may be exercised either on complaint of a local jurisdiction or a gas distributing company, or on its own motion.
. 15 U.S.C. § 717d (1970).
. 406 U.S. 621, 92 S.Ct. 1827, 32 L.Ed.2d 369 (1972).
. 45 F.P.C. 570 (1971).
. 15 U.S.C. § 717(b) (1970).
. Id. § 717o.
. 406 U.S. at 642, 92 S.Ct. at 1839.
. 139 U.S.App.D.C. 150, 430 F.2d 891 (1970).
. 49 U.S.C. §§ 1373, 1482 (1970).
. Id. at 897.
. Id.
. 49 F.P.C. at 585.
. Id.
. Jt.App. 43 (Nos. 73-1999, 73-2017).
. Jt.App. 27 (Nos. 74-1150, 74-1200).
. Id. 109.
. Supra note 5, 506 F.2d at 36.
. State of Louisiana v. FPC, 503 F.2d 844 at 872 (5th Cir. 1974); see International Paper Co. v. FPC, 476 F.2d 121 (5th Cir. 1973); Monsanto Co. v. FPC, 149 U.S.App.D.C. 396, 463 F.2d 799, 803 (1972). The Commission’s most recent position on this issue, which was questioned in State of Louisiana v. FPC, supra, came in Opinion and Order on Rehearing Clarifying and Modifying Opinion No. 647 and Order, Opinion No. 647-A, Docket Nos. RP71-92, RP71-120, 49 F.P.C. 1211, 1220:
With regard to the question of general damage liability for breach of contract based upon curtailment of gas deliveries, we agree with the reasoning of the concurring opinion in International Paper that two categories of litigation are presented: (1) litigation in
which a customer is unable to show that his service was reduced by anything other than a governmentally ordered curtailment plan which was necessary as a result of the gas shortage, and (2) litigation in which it can be shown that the pipeline’s need to curtail resulted from its own negligence, bad faith, or other wrongful conduct. With regard to the first situation, we think that pipeline must be completely exonerated as a matter of law.
. With regard to the second category of cases, we have neither the power nor de*101 sire to adjudicate United’s contract liability, for as recognized in International Paper, that is within the province of the appropriate court, (footnotes omitted).
. Both Transco and Panhandle proposed extensions of interim plans then in effect as alternatives to the immediate implementation of 467 filings, which did not have the assent of the pipelines’ customers. See Jt.App. 52-53 (Nos. 73-1999, 73-2017); Jt.App. 221 (Nos. 74-1184, 74-1231).
. It also explains why in at least two of these cases, Panhandle and Southern, in the course of filing their 467 plans, the pipelines continued to assert the justness and reasonableness of the plans under which they had been operating. See Jt.App. 274-75 (Nos. 74-1184, 74-1231); Jt.App. 30 (74-1150, 74-1200).
. See National Ass’n of Motor Bus Carriers v. FCC, 460 F.2d 561, 567 (2d Cir. 1972):
In Moss, therefore, the airlines’ “discretion” was so circumscribed as to have been almost nonexistent. The situation was not such that the airlines in fact had an option to choose between alternatives.
. These submissions were made to the court on November 26 and 29, 1974. They show the following pipelines, among others, curtailing on non-467 schedules: Cities Service Gas Co., Colorado Interstate Gas Co., Columbia Gas Transmission Co., Lone Star Gas Co., Northwest Pipeline Corp., United Gas Pipe Line Co. Some of these plans appear to be straight pro rata; others are modified end use plans.
. According to the Commission’s submissions, Trunkline submitted no plan subsequent to Order No. 467 and continues to curtail under the pro rata plan which it filed as its initial response to Order No. 431. See Brief for In- • tervenor National Distillers and Chemical Corp. at 20 (Nos. 74-1224, 74-1231).
. Jt.App. 56 (Nos. 73-1999, 73-2017).
. Id.
. See SCRAP v. United States, 412 U.S. 669, 693 n. 17, 93 S.Ct. 2405, 37 L.Ed.2d 254 (1972); National Ass’n of Motor Bus Owners v. FCC, supra note 46.
. Jt.App. 70 (Nos. 74-1150, 74-1200).
. Jt.App. 56 (Nos. 73-1999, 73^2017).
. Courts may be more likely, for example, to restrict regulation by informal means where first amendment values are at stake rather than purely economic interests. See Bantam
. 161 U.S.App.D.C. 6, 494 F.2d 925 at 933.
. Moss v. CAB, supra note 32, 430 F.2d at 893. It was with this phrase that Moss framed the issue before the court for decision.
. See text accompanying notes 42-45 supra.
. Order No. 467-B, supra note 4.
. 49 F.P.C. at 585.
. A helpful analogy is provided by cases dealing with whether administrative action is sufficiently final for judicial review. Like the instant case, these cases confront what is essentially a question of timing, balancing present injury to petitioners against the interests of both the agencies and the courts in having administrative processes run their full course prior to review. Compare Environmental Defense Fund, Inc. v. Ruckelshaus, 142 U.S.App.D.C. 74, 439 F.2d 584 (1971); Isbrandtsen v. United States, 93 U.S.App.D.C. 293, 211 F.2d 51 (1951), with United Gas Pipe Line Co. v. FPC, 86 U.S.App.D.C. 314, 181 F.2d 796 (1950).
. FPC v. Louisiana Power and Light Co., supra, note 27, 406 U.S. at 645, 92 S.Ct. at 1841.
. And some of these costs may be recoverable from the pipeline in a civil action. See cases cited note 43 supra.
. 49 F.P.C. at 219.
. Consolidated Edison Co. v. FPC, supra note 7, 167 U.S.App.D.C. at 143-144, 511 F.2d at 381-382; see FPC v. Louisiana Power and Light Co., supra note 27, 406 U.S. at 644 n. 18, 92 S.Ct. 1827, citing FPC v. Natural Gas Pipeline Co., 315 U.S. 575, 62 S.Ct. 736, 86 L.Ed. 1037 (1942).
. 108 U.S.App.D.C. 409, 283 F.2d 204, cert. denied sub nom., Panhandle Eastern Pipe Line Co. v. Michigan Consol. Gas Co., 364 U.S. 913, 81 S.Ct. 276, 5 L.Ed.2d 227 (1960).
. Id. 283 F.2d at 224.
. In addition to its attacks on the status of the interim plan as a “settlement” in the Panhandle case, the Commission based its rejection on the failure of the plan to “afford consideration of factors relating to end use . ” or to “permit allocation to be based on end use.” Battle Creek Gas Company asserts that the plan did take end use into account, and Panhandle itself, while opposing Battle Creek in the present appeal, has characterized the interim arrangement as an end-use plan, curtailing “among all customers — industrial and utility alike — on the basis of their industrial usage of gas.” Brief of Intervenor Panhandle Eastern Pipe Line Co. at 11 (Nos. 74-1184, 74-1231).
. Consolidated Edison Co. v. FPC, supra note 7, 167 U.S.App.D.C. at 140-141, 511 F.2d at 378-379.
. No. 74-2036, Transcontinental Gas Pipe Line Corp. v. FPC.
. 15 U.S.C. § 717c(e) (1970).
. Atlanta Gas Light Co. v. FPC, 476 F.2d 142, 148 (5th Cir. 1973).
Petitioners in the Panhandle case raise a related claim that the Commission’s action providing for the effectuation of the 467 plan did not afford due process in failing to provide opponents of the plan “an opportunity to test the data by cross-examination.” Brief of Michigan Consolidated Gas Co. at 25 (Nos. 74-1184, 74-1231). In light of the foregoing analysis, this amounts to an assertion that the section 4 procedure, as employed in these cases, is unconstitutional. We may grant that due process considerations are applicable to Commission actions under section 4, particularly where, as in these cases, the agency has involved itself to some degree in the shaping of the tariffs submitted, and where irrevocable effects may flow from their implementation on an interim basis. But the question remains what process is due. Morrissey v. Brewer, 408 U.S. 471, 481, 92 S.Ct. 2593, 33 L.Ed.2d 484 (1972). The existence of exigent circumstances, such as were involved here with the onslaught of the 1973-74 winter, is a recognized factor in making this determination. See, e. g., Cafeteria Workers v. McElroy, 367 U.S. 886, 81 S.Ct. 1743, 6 L.Ed.2d 1230 (1961); Bowles v. Willingham, 321 U.S. 503, 520-21, 64 S.Ct. 641, 650, 88 L.Ed. 892 (1944) (upholding Emergency Price Control Act’s failure to provide for hearing prior to issuance of rent reduction orders on grounds that “Congress was dealing here with the exigencies of wartime conditions and the insistent demands of inflation control.”). In each of these cases, the Commission received submissions from the in
. Text accompanying notes 61-64 supra.
. Id.
. Id. at 38.
. Brief of Battle Creek Gas Co. at 17 (Nos. 74-1184, 74-1231).
. 49 F.P.C. at 87.
. FPC v. Louisiana Power and Light Co., supra note 27, 406 U.S. at 642, 92 S.Ct. at 1839.
A holding in favor of petitioners on this point would also run afoul of court decisions to the effect that the Commission’s jurisdictional limitations did not stand in the way of policy-making sensitive to factors not subject to FPC regulation. See, e. g., Panhandle Eastern Pipe Line Co. v. FPC, 324 U.S. 635, 646-48, 65 S.Ct. 821, 89 L.Ed. 1241 (1945); Conway Corp. v. FPC, 167 U.S.App.D.C. 43, at 49, 51, 52, 510 F.2d 1264 at 1270, 1272, 1273 (April 4, 1975).
. 42 U.S.C. § 4332(2)(C) (1970).
. Id. at 937-38.
. State of Louisiana v. FPC, supra note 43, 503 F.2d at 873.
. Jt.App. 72 (Nos. 73-1999, 73-2017). The agency’s reasoning in the Transco case echoed its statements in the El Paso Natural Gas Co. proceedings, Docket No. RP72-6, and the United Gas Pipe Line Co. proceedings, Docket Nos. RP71-29, RP71-120. It was viewed critically by the Fifth Circuit in State of Louisiana v. FPC, supra note 43, which concluded that an impact statement required nothing jnore than “a good faith attempt fully to evaluate a curtailment plan’s environmental effects, reasonable alternatives, and other factors listed in NEPA . . and therefore that the many variables and uncertainties involved in evaluating the impacts of curtailment plans did not make compliance with NEPA impossible. Id. 503 F.2d at 876. We
. NLRB v. Wyman-Gordon Co., 394 U.S. 759, 766-67 n. 5, 89 S.Ct. 1426, 22 L.Ed.2d 709 (1969). See also Massachusetts Trustees v. United States, 377 U.S. 235, 246-48, 84 S.Ct. 1236, 12 L.Ed.2d 268 (1964); Communist Party v. Subversive Activities Control Board, 367 U.S. 1, 81 S.Ct. 1357, 6 L.Ed.2d 625 (1961).
. Order of Jan. 10, 1975, supra note 22, at 14.
. Among these are arguments that the Commission’s acceptance of the 467 plans by the pipelines was invalid because it overrode contractual provisions and the terms of certificates issued by the Commission without prior hearing. We think these claims are foreclosed by the Supreme Court’s decision in FPC v. Louisiana Power and Light Co., supra note 27, and our subsequent decision in Michigan Power Co. v. FPC, 161 U.S.App.D.C. 221, 494 F.2d 1140, 1144 (1974), in which we stated that
permitting a pipeline’s curtailment plan to take effect despite contrary terms in existing contracts is not inconsistent with the decision in United Gas Pipe Line Co. v. Mobile Gas Service Corp., 350 U.S. 332, 76 S.Ct. 373, 100 L.Ed. 373, . . . (1956); and . a curtailment plan does not of itself constitute an abandonment of service within the meaning of section 7(b).
. See text accompanying notes 63-64 infra.
. See Consolidated Edison Co. v. FPC, supra note 17, 167 U.S.App.D.C. at 141-143, 511 F.2d at 379-381; State of Louisiana v. FPC, supra note 43, 503 F.2d at 871-872 (examining aspects of a Commission-imposed plan similar in many respects, but not identical to the 467 paradigm).