72 Mo. App. 673 | Mo. Ct. App. | 1898
This is an action to recover the reasonable value of work and materials furnished by the plaintiff in repairing a 'business house which is owned ahd controlled by the defendant as trustee. The answer is a general denial. It also sets up a counterclaim. The case was referred to George E. Smith, Esq., who took the testimony and reported the same, together with his conclusions to the circuit court. He recommended a judgment for plaintiff for $1,340, and a judgment cn the counterclaim for $1. The report was confirmed and judgment entered accordingly. The defendant has appealed. We are indebted to the referee for the following statement of the issues:
“By the amended petition in this case, the plaintiff sues for the reasonable value of work and materials furnished at request of defendant, and expended in altering and reconstructing a building at the southwest corner of Thirteenth and Olive streets, in the city of St. Louis, belonging to the trust estate, alleged to have been completed on July 1, 1893.
The various items are set out with their values amounting to the sum of $6,935; credits are given for cash and orders paid amounting to the sum of $5,595, leaving a balance of $1,340 due plaintiff, for which judgment is prayed.
The amended answer pleads that the work and material sued for was furnished by plaintiff under a special contract with defendant, dated October 15,1892, by which plaintiff undertook to alter said building, under the direction of Geo. H. Eied, architect, and to finish the same on or before February 15, 1893, and in default thereof to pay defendant $10 for every day thereafter said building should remain unfinished, as and for liquidated damages; that plaintiff did not finish the same until May 27, 1893, a delay of one hun
The answer also alleges that plaintiff left out a window and certain wainscot required by the plans and specifications, and which defendant was compelled to supply at an expense of $131; that the contract price (of the building) was $6,935.
The answer further alleges that defendant complied with said special contract, and asks judgment for the two items specified in the sum of $1,141.
The reply admits that the work was done under the special contract pleaded by defendant; that it was not completed until May 27,1893, but excuses delayby pleading that the work was interrupted and hindered by the city of St. Louis in building a sewer on Thirteenth street along the east side of the lot and covering up the old material which had been piled in said street, under permit from architect Ried, who was also building commissioner of the city; that the street and lot were thus blockaded so that the old material could not be used, nor could new material be conveyed to said building from January 1 to March 1, 1893, while Thirteenth street was closed to the public.
The reply admits that defendant left out a window and certain wainscot from the building, but pleads that such omission was made with the approval of the architect, etc.”