Connecticut Fund for Environment v. Job Plating Co.Connecticut Fund for Environment v. Job Plating Co.
RULING ON PLAINTIFFS’ MOTION FOR PARTIAL SUMMARY JUDGMENT AND ON DEFENDANT’S MOTION FOR SUMMARY JUDGMENT
This is a citizen suit under the federal Clean Water Act against the operator of an electroplating plant that concededly discharges pollutants into the Quinnipiac River. The suit was brought against the Job Plating Company of Plainville, Connecticut, by the Connecticut Fund for the Environment and the Natural Resources Defense Council.
The environmental organizations contend that Job Plating violated the Clean Water Act on 174 occasions by discharging ef *209 fluents in excess of the amount permitted by its National Pollutant Discharge Elimination System permit. The plaintiffs seek a declaratory judgment that Job Plating has violated the Clean Water Act, an injunction to prevent further violations, and civil penalties of up to $10,000 per violation payable to the United States Treasury. They also seek costs and attorneys’ fees.
Job Plating does not deny that it has exceeded the discharge levels authorized by its NPDES permit. However, the company asserts that this action should nonetheless be dismissed for any of five reasons. The court finds none of these arguments to be persuasive.
First, Job Plating contends that the suit was not brought within the applicable statute of limitations. The court finds, however, that the action is governed by the five-year statute of limitations applicable to government suits under the Clean Water Act rather than by the shorter statute of limitations that would be provided by state law. Accordingly, the action is timely.
Second, Job Plating asserts that penalties for past violations cannot be recovered in citizen suits under the Clean Water Act. The court finds that, while private damages may not be recoverable under the Act, civil penalties (including fines) may be obtained on behalf of the United States.
Third, Job Plating argues that the court, in an exercise of its discretion, should defer in this matter to the Connecticut Department of Environmental Protection. However, the court finds that no such deference is called for where, as here, the suit does not raise complex issues of fact that are peculiarly within the agency’s expertise.
Fourth, Job Plating contends that the action should be dismissed because, under the Clean Water Act, a citizen suit is precluded by a state’s “diligent prosecution” of the same matter. The court finds that there was no “diligent prosecution” in this case, however, because the state’s suit against Job Plating was initiated only after the citizen suit.
Finally, Job Plating argues that its NPDES permit is unenforceable because it was not properly promulgated. The court, noting that Job Plating failed to take advantage of earlier opportunities to challenge its permit, holds that the validity of the permit cannot be raised in this action.
Accordingly, the court finds that Job Plating is liable to the plaintiffs for violation of the Clean Water Act. The court defers a decision with respect to the relief that ought to be granted as a result of this ruling.
I.
This action, a citizen suit brought pursuant to Section 505 of the Clean Water Act (“Act”),
The plaintiffs allege that the defendant violated its National Pollutant Discharge Elimination System (“NPDES”) permit,
see
On March 2, 1984, the plaintiffs filed a motion for partial summary judgment accompanied by a statement of undisputed facts, exhibits, an affidavit and a memorandum of law. On May 11, 1984, the defendant filed a memorandum in opposition to plaintiffs’ motion. The defendant filed a motion to dismiss accompanied by exhibits, an affidavit and a memorandum of law. Each of the parties thereafter filed several additional papers concerning the outstanding motions. On November 19, 1984 (after the transfer of this case to me), oral argument was held on the pending motions. The motion for partial summary judgment and motion to dismiss became ripe for decision as of March 28, 1985, the date on which the plaintiffs’ standing was upheld.
II.
The following material facts are undisputed:
1. On February 23, 1976, the Connecticut Department of Environmental Protection (DEP) issued NPDES permit number CT0022284 to the defendant. The permit was reissued on March 23, 1978. See Plaintiffs’ Statement, ¶ 3 and Exhibit A (NPDES permits).
2. The defendant is required by its NDPES permit to file monthly DMRs. These reports indicate whether the defendant, on the basis of the results of specific tests, is in compliance with its permit. See Plaintiffs’ Statement, ¶ 4; Exhibit D attached to Plaintiffs’ Statement (copies of DMRs).
3. The defendant reported in its DMRs that, between May 1978 and November 17, 1983, it had on 174 occasions discharged substances in excess of the amounts allowed by its permit. See Plaintiffs’ Statement, ¶ 5.
4. On September 9, 1983, the plaintiffs sent a Notice of Intent to Sue to the Administrator of EPA, DEP and the defendant pursuant to
5. Neither the EPA nor the DEP had filed any action against the defendant as of November 17, 1983, the date this action was filed. See Mastriani Aff., ¶¶ 8-10.
6. On December 9, 1983, the Commissioner of DEP issued an Order to Abate Pollution, No. 3639 to the defendant. Mastriani Aff. ¶ 9, Ex. C.
7. On February 9, 1984, Mike Harder, Senior Sanitary Engineer for the Water Compliance Unit, DEP, sent a letter to the defendant that stated that the defendant was in violation of DEP’s Abatement Order *211 and that the matter had been referred to the Attorney General’s Office for further action. See Mastriani Aff. If 10, Ex. D.
8. The plaintiffs have never contacted the defendant and requested that they be permitted to join in negotiations with the DEP and the defendant, nor have they been denied the opportunity to so join in. See Mastriani Aff., ¶ 11.
9. On March 19, 1984 the State of Connecticut, through DEP, instituted a civil action in the Connecticut Superior Court against the defendant to enforce Abatement Order No. 3639. See Mastriani Aff., Ex. E (copy of complaint). The defendant was served with the Summons and Complaint on March 23, 1984, and counsel filed an appearance on April 3, 1984 on behalf of the defendant. On April 6, 1984, the plaintiffs’ counsel was informed by the defendant’s attorney of the suit by DEP. See Mastriani Aff., ¶ 13.
10. The state’s suit in the Connecticut Superior Court seeks enforcement of Order No. 3639, issued on December 9, 1983, requiring submission of an engineering report and subsequent placement of approved waste water treatment facilities in operation by May 31, 1984; the instant citizen suit seeks penalties for violation of effluent limitations set forth in NPDES Permit No. CT0022284, and an injunction against future violations of the permit limits. See Affidavit of Richard F. Webb (executed June 19, 1985) (“Webb Aff.”), ¶ 2(c).
11. The state’s suit has been resolved, with no penalties assessed against the defendant and the filing of a Stipulated Judgment in the Superior Court on June 6,1984. See Webb Aff., 112(c), Attachment (Stipulated Judgment).
III.
The defendant raises five arguments in favor of its motion to dismiss and in opposition to the plaintiffs’ motion for summary judgment: (1) that this action is barred by the applicable statute of limitations; (2) that
A. Statute of Limitations
The Act provides no statute of limitations for actions brought under it. The defendant argues that state law should supply the applicable statute of limitations for state-promulgated NPDES permits.
See
Memorandum of Law in Support of Motion to Dismiss (filed May 11, 1984) (“Defendant’s Memorandum I”) at 21-23; Defendant[] Job Plating Company, Inc. Supplemental Memorandum of Law in Support of Motion to Dismiss (filed Sept. 19, 1984) (“Defendant’s Memorandum III”) at 1-3. In this case, the defendant contends that the applicable statute of limitations is one year pursuant to
The plaintiffs, citing cases on point, claim either that the five-year limitations period of
Our Court of Appeals recently has held that
[w]hen Congress creates a federal cause of action but does not expressly provide an applicable statute of limitations, [it is to be] assume[d] that Congress intended the courts to adopt the limitation period of an analogous cause of action ... and “resort to state law remains the norm for borrowing of limitations periods.” ... But where the application of a state statute of limitations would “frustrate or interfere with the implementation of national policies” or “be inconsistent with the underlying policies of the federal statute, ” courts should borrow a timeliness rule from federal law.
Monarch Long Beach Corp. v. Soft Drink Workers, Local 812, International Brotherhood of Teamsters,
The defendant has not drawn to the court’s attention any case in which a court has applied a state statute of limitations to a citizen suit under the Act. In contrast, several courts specifically have refused to apply state limitations periods because to do so would frustrate the federal policy of uniform enforcement of the Act.
See Chesapeake Bay Foundation v. Bethlehem Steel Corporation,
The court concludes that application of the state statute of limitations to citizen suits under the Act is inappropriate, precisely for the reason noted by the Court of Appeals in
Soft Drink Workers. See Chesapeake Bay I, supra,
Three of the cases that have dealt with the appropriate statute of limitations for citizen suits under the Act, including one in this Circuit, have applied the five-year limitations period of
This court assumes without deciding that
B. Penalties for Past Violations
The defendant contends that
Every court but two that has considered this issue has ruled in favor of the plaintiffs’ position for the reason that
The cases relied upon by the defendant only state the undisputed proposition that private damages are not recoverable by plaintiffs in citizen suits brought under
Two cases contrary to the plaintiffs’ position,
Hamker v. Diamond Shamrock Chemical Co.,
Accordingly, the court finds that the plaintiffs in this action may obtain relief for the defendant’s past violations of its NPDES permit.
C. Primary Jurisdiction
The defendant contends that the doctrine of primary jurisdiction should cause the court, in an exercise of its discretion, to defer to DEP’s abatement proceeding.
See
Defendant’s Memorandum I at 17-19. The plaintiffs, on the other hand, argue that the doctrine of primary jurisdiction has no application to this case because of the absence of complex issues of fact with which the court is unfamiliar and with respect to which the agency arguably is expert.
See Far East Conference v. United States,
Assuming
arguendo
that the doctrine of primary jurisdiction may be applied to require a deference of some kind to state administrative agencies in matters treated by federal law, the factors that would lead the court to invoke that doctrine are not present in this case. The court is not faced with complex issues of fact, but rather with a straightforward enforcement action in which legal issues are presented. In fact, the drafters of
A case relied upon by the defendant,
Montgomery Environmental Coalition Citizens Coordinating Committee on Friendship Heights v. Washington Suburban Sanitary Commission,
The court concludes that the doctrine of primary jurisdiction does not prevent it from exercising jurisdiction over this action to enforce an NPDES permit.
D. Diligent Prosecution
The defendant contends that the state, by bringing an abatement action against it in state court, was “diligently prosecuting” an action within the meaning of
On its face, the diligent prosecution provision of
Apart from
Sierra Club v. Simkins Industries, Inc., supra,
in which the state agency acted after the citizen suit had been filed in federal court, all the cases that have considered
The court concludes that, in accordance with the unambiguous language of
E. Validity of NPDES Permits Issued by DEP
The defendant’s final argument goes to the very validity and enforceability of the NPDES permits issued by DEP. Specifically, the defendant contends that because certain “guidelines” that DEP used to set the effluent standards in the NPDES permit allegedly were not properly promulgated under the Uniform Administrative Procedure Act,
The defendant has failed to avail itself of two different fora in which it might have challenged its NPDES permit. First, the defendant did not commence an administrative challenge to the NPDES permit within 30 days of its issuance by DEP, as permitted by statute.
See
By failing to challenge its NPDES permit under state law at a time when its purported legal deficiency should have been as apparent to the defendant as it is now, the defendant is precluded from doing so in this action. 8
Second, the defendant could have filed an application for review (in the United States Court of Appeals), challenging EPA’s ap
*217
proval of the state’s allegedly invalid NPDES permit program.
See
This case is clearly distinguishable from
Sierra Club v. Indiana-Kentucky Electric Corporation,
For the reasons stated above, the defendant may not raise the issue of the validity of its NPDES permit in this enforcement proceeding.
11
Cf. Adamo Wrecking Co. v. United States,
IV. Summary Judgment for Plaintiffs
Courts have granted summary judgment for plaintiffs in numerous citizen suits brought pursuant to
Conclusion
For the reasons stated above, the plaintiffs’ Motion for Partial Summary Judgment is granted and the defendant’s Motion to Dismiss is denied.
If the parties are unable to reach agreement by October 15, 1985 on the relief that ought to be granted as a result of this ruling, the parties shall file by that date proposed orders and memoranda with respect to the relief that would be appropriate in these circumstances. In preparing their papers on the issue of relief, the parties shall acquaint themselves with decisions by other district courts on the subject. See, e.g., Chesapeake Bay II, supra, at 1552-65.
It is so ordered.
Notes
. This case originally was assigned to the docket of Judge M. Joseph Blumenfeld, Senior United States District Judge. With the consent of Judge Blumenfeld and other transferor judges, and pursuant to an Order of Transfer and Reassignment (entered Aug. 2, 1984 by Chief Judge T.F. Gilroy Daly) this case and other similar pending cases brought by the plaintiffs in this District were transferred to my docket. Nineteen such cases are now pending, not including several in which consent decrees have been entered. This case is one of three in which summary judgment motions have been fully briefed and argued.
. The EPA Administrator has issued the necessary approval to the DEP to issue NPDES permits. See Plaintiffs’ Statement Pursuant to [Local] Rule 9[c] in Support of Their Motion for Summary Judgment ¶ 3, attached to Notice of Motion (filed Mar. 2, 1984).
.
Bertha Building Corp. v. National Theatres Corp.,
. The defendant goes on to claim that injunctive relief is inappropriate because the plaintiffs have failed to allege current violations by the defendant of its NPDES permit, and therefore that the plaintiffs are entitled to no relief.
See
Defendant’s Memorandum I at 21. Assuming
arguendo
that the defendant’s view of relief obtainable pursuant to
.
No action may be commenced—
(1) under subsection (a)(1) of this section—
******
(B) if the Administrator [of EPA] or State has commenced and is diligently prosecuting a civil or criminal action in a court of the United States, or a State to require compliance with the standard, limitation, or order, but in any such action in a court of the United States any citizen may intervene as a matter of right, [emphasis supplied]
.
. Assuming
arguendo
that, contrary to the clear wording of
. The defendant claims that the state statutory provisions do not comport with due process in a case such as this, where the defendant allegedly did not encounter problems with its NPDES permit until more than 30 days after DEP issued the permit. Assuming
arguendo
that the defendant did not have constructive notice that, given its levels of effluent discharge, the NPDES permit might be questionable, there is no indication in the record that it ever attempted to initiate any formal action concerning the validity of the permit with DEP or in the state courts.
See Sun Enterprises, Ltd. v. Train,
. Presumably, the defendant also could have instituted an action in state court to compel DEP to promulgate the regulations that it thought were necessary.
. The Commissioner of DEP has rejected administrative challenges to the legality of the state’s NPDES permit process. See Proposed Decision and Final Decision, In re United Technologies Corporation, Pratt & Whitney Aircraft Group, NPDES permit #CT 000 1376, Exhibits 1 and 2, attached to Affidavit of Katherine H. Robinson (executed Jan. 14, 1985) ("Robinson Aff. I’’); Proposed Decision and Final Decision, In re United Technologies Corporation, Pratt & Whitney Aircraft Group, NPDES permit It 000 1384, attached to Affidavit of Katherine H. Robinson (executed Aug. 13, 1985) ("Robinson Aff. II"). The appeals of the final decision in those cases, see Robinson Aff. I, Ex. 3; Robinson Aff. II, Ex. 3, have been withdrawn. See Robinson Aff. I, ¶ 5; Robinson Aff. II, ¶ 6.
.
Cf. Appalachian Power Co. v. Environmental Protection Agency,
Assuming
arguendo
that the defendant properly could attack the validity of its NPDES permit in this proceeding and that regulations underlying the permit were not properly promulgated, it is still unlikely that the defendant could prevail on this issue. First, there is authority to support the proposition that NPDES permits are enforceable prior to the adoption of supporting regulations.
See Natural Resources Defense Council v. Train,
Second, the defendant would not necessarily prevail, even if it is correct in arguing that the NPDES permit’s discharge limits are invalid. In this respect, the defendant’s argument proves too much. If the NPDES permit is indeed invalid, every discharge by the defendant might be illegal because no discharge is permitted in the absence of an NPDES permit.
See
. The defendant’s bald assertion that ‘DMR's cannot be used as the basis for strict liability under the [Act] since these reports do not accurately reflect the amount of effluents being discharged due to laboratory error[,]”
see
Defendant’s Memorandum III at 17, does not present a disputed issue of material fact required to avoid summary judgment pursuant to