Opinion
The principal issue in this appeal is whether the plaintiffs
The operations of the facility require department approval in the form of a water discharge permit,
In February, 2001, the defendant Dominion Nuclear Connecticut, Inc. (Dominion), in conjunction with its efforts to acquire the Millstone facility,
The plaintiffs’ requests for relief were based in part on allegations that the permit renewal application was invalid because the three nuclear- reactors were shut down at the time the application was filed. Consequently, the Millstone facility was not engaged in operations of a continuing nature as required for application approval under § 4-182 (b). The plaintiffs also alleged that the emergency authorization had been issued in violation of the letter and spirit of the law because its issuance presumed the validity of the underlying permit and it was one in a series of authorizations routinely issued to Northeast over a period of years without notice to the public and without public participation.
On March 29, 2001, following the hearing in Hartford, the court, Schuman, J., issued a written opinion denying the plaintiffs’ application for a temporary injunction. That same day, the department approved the transfer of all environmental permits and emergency authorizations from Northeast to Dominion. On March 30, 2001, the plaintiffs petitioned this court, pursuant to General Statutes § 52-265a, for certification to take a direct appeal from the trial court’s denial of the application for a temporary injunction. The petition was denied on April 3, 2001. Meanwhile, by order dated March 27, 2001, the case was transferred to the complex litigation docket in Norwich.
The court determined that the plaintiffs had “no standing to bring a § 22a-16 action to challenge either the transfer of the permit, the validity of the emergency authorization or the validity of the extension of the underlying 1992 permit with the expiration date of 1997,” under the principles espoused in Fish Unlimited v. Northeast Utilities Service Co.,
The plaintiffs claim on appeal that the court improperly (1) granted the defendants’ motions to dismiss their complaint for (A) lack of standing under § 22a-16 and (B) failure to exhaust their administrative remedies, and (2) denied their application for a temporary injunction. The plaintiffs also claim that alleged procedural irregularities in the hearing proceedings on the motions to dismiss were “prejudicial to the administration of justice.” Because we agree with the trial court’s ruling on the issue of standing, we do not reach the remaining issues raised in the appeal.
I
We first address the defendants’ claim that the request of the plaintiffs for injunctive relief to enjoin the transfer of the permit and emergency authorization should be dismissed on the ground of mootness. The defendants point out that the commissioner long ago
“Mootness implicates [this] court’s subject matter jurisdiction and is thus a threshold matter for us to resolve. ... It is a well-settled general rule that the existence of an actual controversy is an essential requisite to appellate jurisdiction; it is not the province of appellate courts to decide moot questions, disconnected from the granting of actual relief or from the determination of which no practical relief can follow. ... An actual controversy must exist not only at the
Connecticut courts have rejected injunctive remedies on the ground of mootness where the issue before the court has been resolved or has lost its significance because of intervening circumstances. See Waterbury Hospital v. Connecticut Health Care Associates,
In the present case, following the court’s denial of the application for a temporary injunction on March 29, 2001, the department approved the transfer of all environmental permits and authorizations from Northeast to Dominion. Two days later, Northeast conveyed the Millstone facility to Dominion. In light of the fact that the facility has been sold and that the permit and emergency authorization have long since been transferred, we conclude that the plaintiffs’ request for injunctive relief to prevent the transfers from taking place is rendered moot. The plaintiffs’ request for a judgment declaring that the permit and authorization may not be transferred also is rendered moot. Intervening circumstances have changed the legal landscape, a controversy no longer exists between the parties and
Connecticut courts also have dismissed cases on the ground of mootness where the court can offer no practical relief because the position of one of the parties has changed. Shays v. Local Grievance Committee,
II
We next address the issue of the plaintiffs’ standing. The plaintiffs claim that the trial court improperly granted the defendants’ motions to dismiss their complaint because § 22a-16 affords them standing to bring an action alleging unreasonable pollution for lack of a valid permit directly in the Superior Court. The defendants respond that past Supreme Court decisions have held that standing is not available under § 22a-16 to commence such claims directly in the Superior Court. We agree with the defendants.
We begin our analysis by setting forth the appropriate standard of review. “If a party is found to lack standing, the court is without subject matter jurisdiction to determine the cause. ... A determination regarding a trial
“Subject matter jurisdiction involves the authority of the court to adjudicate the type of controversy presented by the action before it. . . . [A] court lacks discretion to consider the merits of a case over which it is without jurisdiction .... The objection of want of jurisdiction may be made at any time . . . [a]nd the court or tribunal may act on its own motion, and should do so when the lack of jurisdiction is called to its attention. . . . The requirement of subject matter jurisdiction cannot be waived by any party and can be raised at any stage in the proceedings. . . .
“Standing is not a technical rule intended to keep aggrieved parties out of court; nor is it a test of substantive rights. Rather it is a practical concept designed to ensure that courts and parties are not vexed by suits brought to vindicate nonjusticiable interests and that judicial decisions which may affect the rights of others are forged in hot controversy, with each view fairly and vigorously represented. . . . These two objectives are ordinarily held to have been met when a complainant makes a colorable claim of direct injury he has suffered or is likely to suffer, in an individual or representative capacity. Such a personal stake in the outcome of the controversy . . . provides the requisite assurance of concrete adverseness and diligent advocacy. . . . The requirement of directness between the injuries claimed by the plaintiff and the conduct of the defendant also is expressed, in our standing jurisprudence, by the focus on whether the plaintiff is the proper party to assert the claim at issue. . . .
“Two broad yet distinct categories of aggrievement exist, classical and statutory. . . . Classical
“Statutoiy aggrievement exists by legislative fiat, not by judicial analysis of the particular facts of the case. In other words, in cases of statutory aggrievement, particular legislation grants standing to those who claim injury to an interest protected by that legislation.” (Citations omitted; internal quotation marks omitted.) Fort Trumbull Conservancy, LLC v. Alves,
“Traditionally, citizens seeking to protect the environment were required to show specific, personal aggrievement to attain standing to bring a legal action. . . . The Connecticut Environmental Protection Act; General Statutes § 22a-l et seq.; however, waives the aggrievement requirement in two circumstances. First, any private party, including a municipality, without first having to establish aggrievement, may seek injunctive relief in court for the protection of the public trust in the air, water and other natural resources of the state from unreasonable pollution, impairment or destruction .... General Statutes § 22a-16. Second, any person or other entity, without first having to establish aggrievement, may intervene in any administrative proceeding challenging conduct which has, or which is reasonably likely to have, the effect of unreasonably polluting, impairing or destroying the public trust in the air, water or other natural resources of the state. General Statutes § 22a-19 (a).” (Citation omitted; inter
In concluding that the plaintiffs lacked standing to bring their complaint directly in the Superior Court pursuant to § 22a-16, the trial court relied on our reasoning in Fish II, a case very similar to the present case. All of the plaintiffs
Our analysis of the standing issue in Fish II was guided by our decisions in two earlier cases, Connecticut Fund for the Environment, Inc. v. Stamford,
In affirming the trial court’s judgment, we concluded that “[s]ection 22a-19, which authorizes any person to intervene in any administrative proceeding and to raise therein environmental issues must be read in connection with the legislation which defines the authority of the particular administrative agency. Section 22a-19 is not intended to expand the jurisdictional authority of an administrative body whenever an intervenor raises environmental issues. Thus, an inland wetland agency is limited to considering only environmental matters which impact on inland wetlands. Other environmental impacts must be raised before other appropriate administrative bodies, if any, or in their absence by the institution of an independent action pursuant to § 22a-16. . . . [Gjeneral environmental matters [involving air and noise pollution and environmental problems created by increased traffic] were not relevant to the proceedings before [the environmental protection board] and therefore its refusal to entertain comment or evidence of a noninland wetland nature was appropriate.”
The plaintiffs in Middletown claimed that they had standing under § 22a-16 to seek an injunction to preclude the proposed burning of oils containing PCBs on the basis of the defendants’ “failure to obtain a variety of approvals and permits” including a water discharge permit under General Statutes § 22a-430. Id., 595. We rejected the plaintiffs’ claim in reliance on our decision in Connecticut Fund for the Environment, Inc. Id., 597.
We first noted that § 22a-16 “permits any private party, including a municipality, to seek injunctive relief ‘for the protection of the public trust in the air, water and other natural resources of the state from unreasonable pollution, impairment or destruction.’ We have recently concluded, however . . . that invocation of [CEPA] is not an open sesame for standing to raise environmental claims with regard to any and all environmental legislation. In Connecticut Fund for the Environment, Inc. v. Stamford, [supra,
We had no further occasion to address the issue of whether § 22a-16 confers standing to bring claims of unreasonable pollution under the licensing statutes until Fish II, where we affirmed our holding in Middle-town. Fish II, supra,
In the present case, we also conclude that the plaintiffs lack standing to bring their complaint pursuant to § 22a-16. We have stated that “one of the basic purposes of [CEPA] is to give persons standing to bring actions to protect the environment and standing is conferred
The plaintiffs claim that we should reevaluate our present interpretation of § 22a-16 with respect to actions brought pursuant to the licensing statutes, because the dissent in Nizzardo v. State Traffic Commission,
The dissent in Nizzardo raised the question of whether standing under § 22a-16 had been construed too narrowly in Middletown, stating that “it was self-contradictory to hold, as we did in Middletown, that one has standing under § 22a-16 to raise environmental concerns only under [CEPA] itself, and that, when one attempts to bring such an independent action, one has no standing to do so. In other words, it is difficult to see why the action that was held to be without standing in Middletown was not an action under [CEPA] itself. The majority [in Nizzardo], in relying on and reaffirming the holding of Middletown, does not explain this self-contradiction.” Nizzardo v. State Traffic Commission, supra,
The majority in Nizzardo concluded, and we continue to maintain, that the claim in Middletown was
Moreover, construing the plaintiffs’ claim of an invalid permit and emergency authorization as an independent claim of unreasonable pollution under § 22a-16 would effectively remove from the department and give to the court the department’s authority under § 22a-430 to make decisions regarding permit applications. It is not our function to take such a step; that determination rests with the legislature.
The plaintiffs next contend that the commissioner has instituted numerous actions pursuant to § 22a-16 in which this court has held that unlawful activities that occur in the absence of permits or in violation of statutes, regulations and abatement orders create unreasonable pollution under CEPA. See Keeney v. Old Saybrook,
We stated in Keeney v. Old Saybrook, supra,
The plaintiffs also attempt to draw a distinction between the claim of unreasonable pollution in Fish II and their present claim of unreasonable pollution. They assert that the claim in Fish II related to the validity of the permit, whereas the claim in this case alleges serious “ongoing pollution” that is unlawful because it is “unpermitted.” We do not agree that the present claim of “ongoing pollution” differs in any significant respect
The plaintiffs next contend that they have standing to bring their claim under § 22a-16 because the legislature contemplated that issues of pollution in violation of the public trust might implicate regulatory or administrative proceedings. They argue that, pursuant to General Statutes § 22a-18, the court may, but need not, remand the parties to administrative, licensing or other proceedings to determine the legality of the defendants’ conduct. The Superior Court thus is empowered to determine the legality of that conduct, separate and apart from the agency’s own proceedings. We do not agree that the plaintiffs’ have standing to raise their claim of an invalid permit pursuant to §§ 22a-16 and 22a-18.
On appeal, the city argued that the defendants’ complaint was premised on the lack of flow in the Shepaug River and that, because the rate of flow is governed by the minimum flow statute, which is enforced by the department, the defendants were precluded under our holdings in Middletown, Fish Unlimited v. Northeast Utilities Service Co.,
The present case is distinguishable from Waterbury. In that case, the defendants’ claim of excessive diversion of water was an allegation of direct harm to the environment. The court specifically observed: “To resolve the question of whether Waterbury’s diversion of water from the Shepaug River violated CEPA, the trial court [would be] required to determine whether Waterbury’s diversion was of such magnitude that it constituted, not merely an impairment, but an unreasonable impairment of the public trust in the river as a natural resource in violation of § 22a-16.” Id., 522-23. Here, by contrast, the plaintiffs did not make an allegation of direct harm to the environment, but alleged
In reaching this conclusion, we note that, in Waterbury, we agreed with the plaintiffs characterization of our decisions in Middletown, Fish I and Fish II as being based on a theory of exhaustion of administrative remedies.
We now clarify our decision in Waterbury to recognize that Middletown and Fish II involved claims that the plaintiffs lacked standing because the court did not have jurisdiction “to litigate environmental issues that are governed by § 22a-430, and which clearly have been placed within the exclusive domain of the department.”
Although this clarification does not affect our holding in Waterbury that the exhaustion doctrine does not apply where the legislature determines that a court may exercise jurisdiction pursuant to § 22a-16, despite the availability of administrative procedures, there must be no possible confusion as to our reasoning in Middle-town and Fish II, because we rely on those two cases as precedent in the current matter.
With each new case, we have continued to refine the law on standing under § 22a-16. We have determined that a plaintiff has standing to bring an independent action under § 22a-16 where an administrative body does not have jurisdiction to consider the environmental issues raised by the parties. See Connecticut Fund for the Environment, Inc. v. Stamford, supra,
Our conclusion that the plaintiffs lack standing to bring their claim under § 22a-16 is dispositive, and precludes our consideration of their remaining claims that the trial court improperly relied on the exhaustion doctrine and improperly conducted proceedings “prejudicial to the administration of justice.” We do not reach the plaintiffs’ claim that the trial court improperly denied their application for a temporary injunction for the same reason.
The appeal from the judgment dismissing the action against Northeast Nuclear Energy Company is dismissed; the judgment dismissing the action against the named defendant and the defendant Dominion Nuclear Connecticut, Inc., is affirmed.
In this opinion the other justices concurred.
Notes
The plaintiffs in this case are Connecticut Coalition Against Millstone, an organization based in Mystic, advocating the use of safe and renewable
General Statutes § 22a-16 provides: “The Attorney General, any political subdivision of the state, any instrumentality or agency of the state or of a political subdivision thereof, any person, partnership, corporation, association, organization or other legal entity may maintain an action in the superior court for the judicial district wherein the defendant is located, resides or conducts business ... for declaratory and equitable relief against the state, any political subdivision thereof, any instrumentality or agency of the state or of a political subdivision thereof, any person, partnership, corporation, association, organization or other legal entity, acting alone, or in combination with others, for the protection of the public trust in the air, water and other natural resources of the state from unreasonable pollution, impairment or destruction provided no such action shall be maintained against the state for pollution of real property acquired by the state under subsection (e) of section 22a-133m, where the spill or discharge which caused the pollution occurred prior to the acquisition of the property by the state.”
The defendants are Arthur J. Roque, Jr., commissioner of environmental protection; Northeast Nuclear Energy Company; and Dominion Nuclear Connecticut, Inc.
These actions include Fish Unlimited v. Northeast Utilities Service Co.,
Any person or municipality must obtain a national pollution discharge elimination permit prior to discharging any substance into the waters of the United States or Connecticut under the federal Clean Water Act, 33 U.S.C. § 1342 and General Statutes § 22a-430. In Connecticut, the department is responsible for issuing the federal and state discharge permits.
General Statutes § 22a-430 (c) provides in relevant part: “An application for a renewal of a permit which expires after January 1, 1985, shall be filed with the commissioner at least one hundred eighty days before the expiration of such permit. . . .”
The additional toxic substances that are not covered by the 1992 permit include hydrazine and ethanolomine.
General Statutes § 22a-6k provides in relevant part: “(a) The Commissioner of Environmental Protection may issue an emergency authorization for any activity regulated by the commissioner under section . . . 22a-430 . . . provided he finds that (1) such authorization is necessary to prevent, abate or mitigate an imminent threat to human health or the environment; and (2) such authorization is not inconsistent with the federal Water Pollution Control Act .... Such emergency authorization shall be limited by any conditions the commissioner deems necessary to adequately protect human health and the environment. . . .”
Prior to submission of the application, Connecticut Coalition Against Millstone (CCAM) had sent a letter and notice of intervention to the commissioner requesting that the department commence an administrative proceeding to consider the anticipated application. The commissioner denied CCAM’s request for an administrative proceeding and intervention, however, on the ground that a permit transfer does not require an administrative proceeding and hearing, but that, in the event that the permit was transferred, CCAM could request intervention in any subsequent administrative proceeding conducted with respect to renewal of the permit. The plaintiffs subsequently intervened in the permit renewal proceedings.
Paragraphs eight, nine and ten of the plaintiffs’ complaint allege that Millstone’s operations generate pollution. Paragraphs eleven through seventeen and paragraph twenty allege that the operations of the facility require a permit, that the permit expired in December, 1997, that the permit has not been renewed and that Northeast filed an application for renewal of the permit 180 days prior to its expiration. Paragraph twenty-one alleges that the renewal application was invalid under § 4-182a (b) because Millstone was shut down and was not engaged in activities of a continuing nature at the time the application was filed. Paragraphs twenty-two through thirty allege that an emergency authorization improperly was issued to Northeast. Paragraphs thirty-five and thirty-six allege that the commissioner has no legal authority to approve the continued operation of Millstone following expiration of the 1992 permit and to issue the emergency authorizations.
The transfer order stated that objections to the order should be filed with the complex litigation docket in Norwich within twenty days. The plaintiffs filed an objection with the Hartford Superior Court on April 14, 2001. On April 17,2001, the presiding judge for the complex litigation docket in the judicial district of Norwich, apparently unaware that the plaintiffs
The commissioner and Northeast filed motions to dismiss the case on March 19, 2001. Dominion filed a motion to dismiss the case on March 21, 2001.
See footnote 2 of this opinion.
The defendants raised similar claims earlier in the proceedings. On May 3, 2002, prior to the transfer of the appeal to this court, Northeast and Dominion filed a motion with the Appellate Court seeking dismissal of the appeal on the ground of mootness. They argued that, even if the trial court should have granted the plaintiffs’ motion for a temporary injunction, the commissioner’s subsequent approval of the permit transfer, followed by the sale of the Millstone facility to Dominion, rendered it impossible for the court to grant the plaintiffs any practical relief. The Appellate Court denied the motion on July 17, 2002. Northeast filed a motion for reconsideration on July 26, 2002, arguing that it no longer owned or operated the facility and no longer held the related pennits or authorizations, and, accordingly, a controversy no longer existed between the plaintiffs and Northeast. The Appellate Court denied the motion for reconsideration on September 11, 2002. In raising their present claims, the defendants do not seek to dismiss the appeal in its entirety, but only as to (1) the injunctive relief requested with respect to the permit transfer, and (2) Northeast in its capacity as a defendant. We note that the plaintiffs made no direct response in their briefs to Ihe defendants’ claims of mootness.
There also were four additional plaintiffs in Fish II: Fish Unlimited, a national clean water fisheries conservation organization based in Shelter Island, New York; Don’t Waste Connecticut, an environmental group based in New Haven; the town of East Hampton, New York; and the Green Party of Connecticut. See Fish II, supra,
The two defendants in Fish II were Northeast and its parent company, Northeast Utilities Service Company. Northeast was involved in the management and operation of the three nuclear reactors. See Fish II,
The plaintiffs in Fish II did not seek a declaratory judgment and injunctive relief to prevent the transfer of the permit and emergency authorization from Northeast to Dominion, as the plaintiffs do here.
The principle that § 22a-19 does not expand the authority of an administrative body to consider environmental issues outside its jurisdiction and that, in such cases, an independent action may be brought pursuant to § 22a-16, has been affirmed in subsequent decisions of this court. Connecticut Water Co. v. Beausoleil, 204 Corm. 38, 46,
General Statutes § 22a-430 provides in relevant part: “Permit for new discharge. Regulations. Renewal. Special category permits or approvals. Limited delegation. General permits, (a) No person or municipality shall initiate, create, originate or maintain any discharge of water, substance or material into the waters of the state without a permit for such discharge issued by the commissioner. Any person who initiated, created or originated a discharge prior to May 1, 1967, and any municipality which initiated, created or originated a discharge prior to April 10, 1973, for which a permit has not been issued pursuant to this section, shall submit an application for a permit for such discharge on or before July 1, 1987. Application for a permit shall be on a form prescribed by the commissioner, shall include such information as the commissioner may require and shall be accompanied by a fee of twenty-five per cent more than the amount established in regulations in effect on July 1, 1990. On and after July 1, 1991, such fees shall be as prescribed by regulations adopted by the commissioner in accordance with chapter 54. The commissioner shall not issue or renew a permit unless such, issuance or renewal is consistent with the provisions of the federal Clean Water Act (33 USC 1251 et seq.).
“(b) The commissioner, at least thirty days before approving or denying a permit application for a discharge, shall publish once in a newspaper having a substantial circulation in the affected area notice of (1) the name
“(c) The permits issued pursuant to this section shaE be for a period not to exceed five years, except that any such permit shaE be subject to the provisions of section 22a-431. Such permits: (1) ShaE specify the manner, nature and volume of discharge; (2) shaE require proper operation and maintenance of any poEution abatement facihfy required by such permit;
(3) may be renewable for periods not to exceed five yeans each in accordance with procedures and requirements estabEshed by the commissioner; and
(4) shaE be subject to such other requirements and restrictions as the commissioner deems necessary to comply fuEy with the purposes of this chapter, the federal Water PoEution Control Act and the federal Safe Drinking Water Act. An appEcation for a renewal of a permit which expires after January 1, 1985, shaE be filed with the commissioner at least one hundred eighty days before the expiration of such permit. The commissioner, at least thirty days before approving or denying an appEcation for renewal of a permit, shaE pubhsh once in a newspaper having substantial circulation in the area affected, notice of (A) the name of the appEeant; (B) the location, volume, frequency and nature of the discharge; (C) the tentative decision on the appEcation, and (D) such additional information the commissioner deems necessary to comply with the federal Clean Water Act (33 USC 1251 et seq.). There shaE be a comment period foEowing the pubEc notice during which period interested persons and municipaEties may submit written comments. After the comment period, the commissioner shaE make a final determination that (i) continuance of the existing discharge would not cause poEution of the waters of the state, in which case he shaE renew the permit for such discharge, or (u) continuance of the existing system to treat the discharge would protect the waters of the state from poEution, in which case he shaE renew a permit for such discharge, (in) the continuance of the existing system to treat the discharge, even with modifications, would not protect the waters of the state from poEution, in which case he shaE
“(d) If the commissioner finds that any person or municipality has initiated, created or originated or is maintaining any discharge into the waters of the state without a permit as required in subsection (a) hereof, or in violation of such a permit, he may issue an order to abate pollution which shall include a time schedule for the accomplishment of the necessary steps leading to the abatement of such pollution, or notwithstanding any request for a hearing pursuant to section 22a-436 or the pendency of an appeal therefrom, he may request the Attorney General to bring an action in the superior court for the judicial district of Hartford to enjoin such discharge by such person or municipality until the person or municipality has received a permit from the commissioner or has complied with a permit which the commissioner has issued pursuant to this section. Any such action brought by the Attorney General shall have precedence in the order of trial as provided in section 52-191.
An even more compelling example of the difference between a permitting claim and a claim of unreasonable pollution under § 22a-16 can be found in Fish Unlimited v. Northeast Utilities Service Co.,
The plaintiffs in Fish I sought to enjoin the defendants from restarting unit 2, one of the three nuclear generating units in the Millstone facility, because the once-through condenser cooler water system in place at unit 2 allegedly had caused “ ‘unreasonable pollution, impairment and destruction of the public trust in the air, water and other natural resources of the state within the meaning of . . . General Statutes § 22a-16.’ ” Fish I, supra,
The plaintiffs argue that Waterbury v. Washington,
The plaintiffs state in their brief that their claim of “unreasonable and lawless pollution” is alleged in paragraphs eight, nine, ten, sixteen, seventeen, twenty-four, twenty-six, twenty-eight, twenty-nine, thirty and thirty-nine of the complaint. Those paragraphs include allegations of the polluting activity (eight, nine, and ten), allegations that the 1992 permit has expired (sixteen and seventeen), allegations that the emergency authorization is invalid (twenty-four, twenty-six and twenty-eight through thirty) and allegations that Millstone operations involve conduct that has, or is reasonably likely to have, the effect of unreasonably polluting the natural resources of the state (thirty-nine).
General Statutes § 22a-18 provides: “(a) The court may grant temporary and permanent equitable relief, or may impose such conditions on the defendant as are required to protect the public trust in the air, water and other natural resources of the state from unreasonable pollution, impairment or destruction.
“(b) If administrative, licensing or other such proceedings are required or available to determine the legality of the defendant’s conduct, the court in its discretion may remand the parlies to such proceedings. In so remanding the parties the court may grant temporary equitable relief where necessary for the protection of the public trust in the air, water and other natural resources of the state from unreasonable pollution, impairment or destruction and the court shall retain jurisdiction of the action pending completion of administrative action for the purpose of determining whether adequate consideration by the agency has been given to the protection of the public trust in the air, water or other natural resources of the state from unreasonable pollution, impairment or destruction and whether the agency’s decision is supported by competent material and substantial evidence on the whole record.
“(c) If the agency’s consideration has not been adequate, and notwithstanding that the agency’s decision is supported by competent material and substantial evidence on the whole record, the court shall adjudicate the impact of the defendant’s conduct on the public trust in the air, water or other natural resources of the state in accordance with sections 22a-14 to 22a-20, inclusive.
“(d) Where, as to any administrative, licensing or other proceeding, judicial review thereof is available, the court originally taking jurisdiction shall maintain jurisdiction for purposes of judicial review.
“(e) The court may award any person, partnership, corporation, association, organization or other legal entity which maintains an action under section 22a-16 or intervenes as a party in an action for judicial review under section 22a-19, and obtains declaratory or equitable relief against the defendant, its costs, including reasonable costs for witnesses, and a reasonable attorney’s fee.”
We also discussed the matter of primary jurisdiction in Fish I, where the defendants had argued, in the alternative, that the plaintiffs’ claims should be dismissed under that doctrine. See Fish I, supra,
We expressly stated that in Middletown and Fish II “we concluded that, pursuant to the doctrine of exhaustion of administrative remedies, the defendants were required to bring their claims to the administrative bodies entrusted with enforcement of the environmental statutes on which their claims were based.” Waterbury v. Washington, supra,
In Fish II, we stated: “In light of the conclusion that the plaintiffs lacked standing to bring their claim directly in the Superior Court, we do not reach the issue of exhaustion of administrative remedies.” Fish II, supra,
We take no issue with the characterization in Waterbury of our ruling on standing in Fish I as based on the exhaustion doctrine.