Conduit & Foundation Corp. v. Metropolitan Transportation AuthorityConduit & Foundation Corp. v. Metropolitan Transportation Authority
OPINION OF THE COURT
The narrow issue presented on this appeal is whether the evidence on the record supports a holding that the Metropolitan Transportation Authority and the New York City Transit Authority acted unlawfully in rejecting all bids submitted in an initial round of bidding on a public works project.
The relevant facts are not in dispute.
1
Respondents, the Metropolitan Transportation Authority and the New York City Transit Authority (Transit Authority), solicited bids for a public works contract for the massive rehabilitation of part of New York City’s
Subsequent to the meetings, the second lowest bidder advised the Transit Authority by letter that significant cost reductions were possible and suggested another meeting to discuss the possibility of preparing revised contract documents. Several days thereafter, it was petitioner that met again with the Transit Authority. Petitioner was informed that its bid, though the lowest, was far in excess of the revised estimated cost and that, therefore, all the bids might be rejected. Nevertheless, petitioner was told that it was deemed technically and financially qualified to undertake the project and, indeed, was afforded the opportunity to reduce its bid for consideration. Within the next two weeks, petitioner once again met with the Transit Authority and offered to reduce its bid price by two million dollars, a proportionately small amount. The reduction was deemed insufficient by the Transit Authority’s Chief Engineer who, on the following day, recommended that all the bids be rejected and that the contract, with modifications, be readvertised for a second round of bidding. The recommendation was adopted by the President of the Transit Authority and the three bidders were notified. Thereafter, the Transit Authority circulated a notice soliciting new bids for the project and indicating an estimated cost range between $100 and $120 million, $20 million lower than that originally advertised.
Petitioner commenced this article 78 proceeding seeking an injunction against a second round of bidding and a judgment directing respondents to award the contract to petitioner as the lowest responsible bidder. Special Term granted the petition concluding that the Transit Authority’s postbid communications with the three bidders, its revision of the advertised cost estimate and its purpose of obtaining bid prices lower than that originally received rendered the decision to reject all first round bids arbitrary and capricious. The Appellate Division agreed with Special Term, two justices dissenting, that the contract should be awarded to petitioner, but modified the judgment to reduce the contract price by two million dollars on the basis of petitioner’s prior offer to the
As this court has stated on prior occasion, the purpose of the laws in this State requiring competitive bidding in the letting of public contracts is "to guard against favoritism, improvidence, extravagance, fraud and corruption.”
(Jered, Contr. Corp. v New York City Tr. Auth.,
Indeed, this policy is reflected explicitly in the statutory provisions which mandate that public work contracts be awarded "to the lowest responsible bidder”. (Public Authorities Law § 1209 [1]; General Municipal Law § 103 [1];
see also,
General Municipal Law § 100-a.) Dishonesty, favoritism and material or substantial irregularity in the bidding process, which undermines the fairness of the competition, impermissibly contravene this public interest in the prudent and economical use of public moneys.
(See, e.g., Gerzof v Sweeney,
Nevertheless, where good reason exists, the low bid may be disapproved or, indeed, all the bids rejected. Neither the low bidder
Moreover, it cannot be gainsaid that a realistic expectation of obtaining lower contract prices upon a second round of bidding constitutes a reasonable, bona fide ground for rejecting all first round bids and serves the public’s interest in the economical use of public moneys.
(See, Orelli v Ambro,
Here, where the court below found only that the postbid activity of the Transit Authority created an "appearance of impropriety” and "cast a doubt” upon its fair dealing with the bidders, the respondents’ decision to seek a rebid ought not to have been disturbed. It may be true, as the majority at the Appellate Division found, that it would have been wiser for the Transit Authority to meet with all the bidders at the same time, instead of separately, in order to avoid the possible appearance of unfair dealing. Likewise, other bid interactions between the Transit Authority and certain bidders may have been more discreet. Nevertheless, as noted in the dissenting opinion of Justice Niehoff, absent some finding that the respondents had, in fact, engaged in some unfair or unlawful practice tainting the impartiality of the competitive bidding process, it was error to grant the petition.
The Transit Authority clearly was empowered to reject all the first round bids, and its expectation of obtaining lower bid prices upon readvertisement was a rational basis for deciding to do so. Petitioner failed to demonstrate that the respondents acted unlawfully with regard thereto or with regard to other postbid conduct. Consequently, the petitioner having neither requested to add to the record nor having sought a hearing on the facts 2 (see, Siegel, NY Prac §§ 554, 556), but, instead, having chosen to rely solely on its documentary submissions which were insufficient to meet its burden, the petition should have been dismissed.
Accordingly, the order of the Appellate Division should be reversed, with costs, and the petition dismissed.
Chief Judge Wachtler and Judges Meyer, Simons, Kaye, Alexander and Titone concur.
On respondents’ appeal, order reversed, with costs, and petition dismissed. Petitioner’s cross appeal dismissed as academic.
Notes
. Respondents substantially admitted the factual allegations contained in the article 78 petition, denying, however, the legal conclusions drawn therein. At Special Term, the parties relied solely upon their pleadings, documentary submissions and oral argument. No contention was made that the record before the court was insufficient and no request was made for an evidentiary hearing. (See, CPLR 409; Siegel, NY Prac § 556.)
. Indeed, petitioner argues in its brief (Brief of "Respondent-Cross Appellant”, at 72) to this court that permitting respondents to do so at this point would be improper as there is no basis "now [to] complain that [Special Term] lacked sufficient pertinent evidence to make a decision.”