98 N.Y.S. 253 | N.Y. App. Div. | 1906
This action was brought to foreclose a mechanic’s lien on real property belonging to the defendant The Church of St. Augustine, a religious corporation. On the 30th of June, 1894, the plaintiff' entered into a contract in writing, which upon its face purported to be made between himself and the trustees of St. Augustine’s Roman Catholic Church of the city of New York. It was signed by T. F. Gregg, rector of the church, and does not appear to have been executed or, when it was made, authorized by the board of trustees of thé church at a regular meeting. By that contract the plaintiff agreed to complete and finish mason work to be done in the erection of a new church and rectory building on land belonging to the church corporation, and to supply materials therefor; the owner agreed to pay the contractor for doing the work and furnishing the materials the sum of $27,900 in partial payments' at certain stages of the work.. The contractor stipulated to provide whatever was necessary for the proper completion of the mason work within a limited time, and that if he failed to do so the owner might notify him in writing to proceed and complete the work, and if he failed so to do for the space of three days after service of a notice the cor
Many matters were, discussed on the argument which we do not find it necessary to consider in the determination of this controversy as it is now presented. -We are' concerned only with the rights ..of Miller &' Eobinson and of the plaintiff, so far as they are connected with or related to each other, and as those of .the former depend upon those of the latter. It is as well to say, perhaps, that we are not satisfied of. the correctness of the ruling of the referee that the notice of lien filed by the. plaintiff was insufficient, but .we are satisfied that the notice, of lien filed by Miller & Eobinson was sufficient; and that is all that is required under the Mechanics’ Lien Law of (1885 (Laws of 1885, chap. 342, as amd.): That the referee was technically correct in- ruling that the churph corporatioft was not bound as an original contracting party to the agreement of June - 30, 1894,-need not be questioned and that there was no technical ratification of that, agreement may also be .conceded, but it is very plain that there was a consent on-the part of the corporation to- the plaintiff. performing work and supplying materials under, the June contract above referred to. The property upon which the improvements were, made and to which the contract related was always that of the church. The réctor, on the whole evidence, is clearly shown to have been in fact the agent of the church corporation. All' through the. record it appears that everything connected with the progress of this work from its initiation until the end was left in the hands of .Mr. Gregg as the representative of the corporation. Money raised upon the mortgage was applied to the payment of work done in part by the plaintiff in the construction of the church and the. rectory Connected therewith; that money was put into and drawn from the bank account of the church kept in the name' of “ Thomas F. Gregg,.. Hector St. Augustine’s, Hew Fork,” and the' chiu-ch corporation had no other bank account than the one kept in. that way, and the Rev. Mr. Gregg paid out the money to- the plaintiff' on áccoünt of
It is claimed, however, that the plaintiff was justified in refusing to complete the work in consequence of the refusal of the church corporation to pay him. for the extra work. What is said in Flaherty v. Miner (123 N. Y. 389), to the effect that where a contract required defendants to make to a plaintiff payments as the work progressed, and the defendants refused to pay as required, there was a breach of the .contract by the defendants which justified a refusal on the part ef the plaintiff to continue the work, does not apply under the facts as ‘they appear in the record before us. On the 1st of December, 1894, the plaintiff received a sum of moiiey from the church and delivered to it a writing in the following words: “ I hereby agree to ask for no more money for work on St. Augustine’s Church and Rectory, of which I am the contractor, until all plastering is completed in both buildings, if I am paid the sum of Two thousand dollars to-day.” That sum was paid, and it would appear that nothing was due the plaintiff when it was paid. .The plastering never was completed. When the plaintiff left the work the first truss had been put up. It fell, “ and they were re-erecting it about December 17th, 1894.” On December 14, 1894, the three days’ -notice was served. Before the expiration of that period the- first truss was in position, and much work could have been done by the plaintiff under his contract. The remarks of the referee in his opinion on this subject are satisfactory, and in our judgment dispose of it.
We are of the opinion that the referee did not err in his finding that the plaintiff and the defendants Miller & Robinson had no right to enforce a lien against the property at the time their respective notices of lien' were filed, but we are unable to'see how, upon any just, reasonable or -equitable ground all the costs and disbursements of this action should he charged upon the defendants Miller & Robinson. T-hey did not foment a litigation nor did they protract it; they were made parties to the action and they merely endeavored to enforce their rights in subordination to those of the plaintiff, if peradventure his lien were established and the church property made subject to it. The proceedings before the referee set forth in the
The judgment should be modifed by striking out the provision respecting the recovery of costs against Miller & Robinson, and as modified affirmed, with costs of this appeal to Miller & Robinson.
O’Brien, P. J., Ingraham, Laughlin and Clarke, JJ., concurred.
Judgment modified as directed in opinion, and as modified affirmed, with costs of appeal to Miller & Robinson. Settle order on notice.