Dеfendant Standard Oil Company of California (Standard) appeals from a judgment entered upon a jury verdict in favor of plaintiff Conderback, Incorporated (Conderback) in the sum of $154,374.45 with interest and costs.
The action was brought to recover the balance allegedly due on a contract for the construction, designing, maintenance and dismantling of Standard’s exhibit at the Seattle World’s Fair in 1962. There were two jury trials. On defendant’s motion, the cause first proceeded to trial on the issues raised by the separate defenses of account stated, accord and satisfaction and compromise and release set forth
At all times here material, Conderback was a California corporation engaged in the business of building advertising exhibits. 2 It had been organized in 1957 and had its principal place of business in San Francisco. All of its capital stock was owned by Marinus van der Woert and Edward Rails-back, its president and vice-president respectively. Prior to the formation of Conderback, Railsbaek had been continuously employed in the exhibit business since 1935 and had personally done work for Standard since 1939. Van der Woert had worked in the exhibit display business since 1946 and during that time on exhibits for Standard. Both men had been employees together in the same exhibit building firm and were able to acquire some of the accounts, including that of Standard, when the firm ceased doing business.
From the time they organized Conderback, Railsbaek and van der Woert had continuous business dealings with the advertising department of Standard, approximately 90 percent of the time with either M. A. Mattes, the advertising manager, or Jeff Kersh, an employee in the department. From 1960 until it suspended its operations, Conderback did over 300 jobs for Standard’s advertising department. Among these were Standard’s exhibits at the California State Fair, which Conderback built each year. Railsbaek considered Standard to be one of Conderback’s better accounts. However, prior to the Seattle World’s Fair job, the largest job
In their years of working together on more than 300 jobs, there had never been any litigation between Conderback and Standard over the former’s billings. According to their customary way of working together, Conderback would “be notified that there was a job coming up and we had a certain budget to adhere to. We would then come back to the shop and design within this budget and endeavor to hold the budget price that they had given us.” An estimate would be given through the use of a basic formula but at the end of the job an adjustment would usually be made based on the same formula to take care of changes and additions. 3 This applied to so-called “time and material” business as distinguished from “bid” business which was billed at the bid price. There was testimony thаt Conderback’s methods of estimating and billing were discussed with Standard and that the latter was well aware of them. The increase of the markup on subcontracted work (see fn. 3, ante) had also been discussed with Standard who had assured Conderback that this so-called agency markup should and could be used.
The Seattle World’s Pair was scheduled to open on April 21, 1962. In the spring of 1961, Railsbaek and van der Woert met with Mattes, advertising manager of Standard, to discuss the possibility of having Conderback handle Standard’s exhibit at the Pair. Mattes inquired as to whether the project was beyond the “scope” of Conderback and was assured by the latter’s representatives that they could handle the job since much of the work would be subcontracted. Mattes was told that because Conderback was a small company and the project was a large one, Conderback would have to bill Standard in advance of any expenditures. Mattes selected Conderback to do the job. There were no other competitive bidders.
Conderback started work almost immediately. To design Standard’s building at the Pair, it retained one Tepper who was to work directly with Railsbaek and van der Woert, but who soon “bypassed” them at Mattes’ request and worked with the latter who approved the building and all exhibits before Conderback saw them. Conderback also retained an architect and an engineer and entered into a number of subcontracts for the performance of the construction work. The subcontractors billed Conderback for the work done and the latter in turn eventually billed Standard for the same
The concept of the Century 21 Exhibit as designed within the limits of the initial budget of $230,000 soon started changing and continued to change up to and even after the Fair opened in April 1962. These changes were made principally by Mattes. At first Conderbaek did not challenge his decisions but finally at the beginning of 1962 the matter “was so far out of hand that . . . [Conderbaek] could never catch up,” since it had no control of the budget or the design or the coordination between them. When Railsback raised some question about completing on time the work as modified, Mattes replied “Let’s get the job done, we will worry about that later. ’ ’
At about this time—February 1962—the parties realized that the job had already cost more than the initial budget figure of $230,000. Standard thereupon requested from Conderback a written estimate of the total cost of the job. According to Standard’s Whitmore, this was required for budgetary reasons. In compliance with the request, Conderbaek wrote to Standard on February 12, 1962, giving an itemized breakdown of costs and noting that to date there were total authorized expenditures of $307,518.12. 7 Standard then requested a firm bid on the amount required to finish the job. In reply Conderbaek on February 26, 1962, sent Standard “our firm bid” for the Century 21 Exhibit in the sum of $351,587.20 based on the detailed breakdown furnished in its letter of February 12, 1962. 8 Standard accepted and confirmed this “firm bid” by its letter of March 23, 1962. 9
There ensued a number of meetings between the representatives of the parties. In the meantime Conderback was reeiving invoices after June 1—the cutоff date of their June 15 billing. Standard indicated that it was not willing to discuss these latter invoices at the time. On June 30, 1962, Conderback’s van der Woert wrote to Mattes attaching “schedules covering costs ... to June 1, 1962, maintenance costs for the exhibit to October 26, 1962, and costs incurred during the month of June” but holding in abeyance design fees and sales tax. Total actual costs to June 1, 1962, were therein scheduled at $525,134.17, of which the same amount was noted paid as in the June 15 schedule and $109,762.23 was the “additional requested.” The parties agreed upon a number of the items for which Conderback thereupon invoiced Standard on July 11, 1962, in the sum of $66,794.01 and was paid. On July 26, 1962, Conderback again invoiced Standard for specified items totalling $39,848.87.
11
The invoice was not designated a final billing. Eventually Standard agreed to pay the invoice. Standard’s Whitmore testified at the first trial that he wanted a reassurance from Conderback that it was the final payment on the building and exhibits. Eailsback on the other hand testified that he attended all the meetings, that he never heard of such a statement and that it was not a condition of the payment of either the July 11 or the July 26 invoice. Defendant’s claim is that it specifically conditioned its agreement to pay the July 26 invoice on the receipt of an
Nevertheless, after these events upon which Standard based its claim of final settlement, said defendant paid $1,871.80 to Conderbaek, most of which represented charges for work done prior to May 28, 1962. Additionally, on September 14, 1962, van der Woert wrote to Mattes ‘‘ listing the developments to date regarding the following unpaid accounts.” 13 Eventually in the fall of 1962, Conderbaek settled its obligations with the designer and its sales tax liability to the State of Washington. Although the parties differ as to the basic contract under which the work was being done, they appear to agree that under either of their respective theories, the total amount to be paid by Standard to Conderbaek could not be arrived at until the above two liabilities had been determined.
In December 1962, van der Woert telephoned Whitmore, advising that there were some additional bills.
14
On January
By this time, Conderbaek’s Leong, who had run an audit on the Fair job, had left the company. Railsbaek had been hospitalized with a serious illness until January 3, 1963, and the two Conderbaek officers had decided to defer discussion with Standard of the application “of our formula to the costs that we had incurred. . . . ”
17
Railsbaek and van der Woert, with the help of an outside auditor, then started “to re-audit this job on a complete and thorough basis” in the latter part of January and the first part of February. In early March 1963, they contacted Mattes and asked for an opportunity to present their final bill. A meeting was held at which Conderbaek submitted and left with Standard for its examination all of the work sheets of the reaudit together with their supporting data. Other discussions followed with Standard’s representatives. There was testimony that the manager of Standard’s purchase and stores department indicated that after the $230,000 limit of the original purchase order had been passed, the job should have been handled on a cost-plus-jia;ed-/ee basis. Conderbaek indicated it merely wanted its existing formula applied. At one point, Standard’s representatives offered a 17.625 percent markup on
Standard’s first attack is aimed at the very heart of the judgment. It contends that Conderback could not bring or maintain the present action since it was acting in the capacity of a contractor in California without being duly licensed. 19 In substance defendant argues that all negotiаtions and correspondence leading up to the contract between the parties, the contractual arrangements themselves and certain contracts between Conderback and the designer, architect and engineer of the project all took place in San Francisco, where the principals herein and the other persons mentioned all had their respective offices. At the same time Standard admits, as it must, that the building which was the subject of the project was intended to be, and in fact was, constructed outside of the State of California and in the State of Washington" and has conceded both in its briefs and at oral argument that its contention is confined to and is predicated solely upon those acts of Conderbaek which occurred in the State of California.
Section 7028 of the Business and Professions Code
20
makes it
“unlawful
for any person to engage in the business or
act
Section 7031 provides: “No person engaged in the business or acting in the capacity of a contractor, may bring or maintain any action in any court of this State for the collection of compensation for the performance of any act or contract for which a license is required by this chapter without alleging and proving that he was a duly licensed contractor at all times during the performance of such act or contract.” (Italics added.)
Gonderback concedes, and the record shows, that it was not a licensed contractor in California at any time. Its basic position is that the California Contractors’ License Law (Bus. & Prof. Code, §§ 7000-7145) does not extend to construction outside of California although it has not squarely met defendant’s argument that Gonderback’s acts within the state were done in the capacity of a contractor so as to make the law operative against it. Neither of the parties has cited, nor have we found, any case involving a similar question.
It is clear at the outset, as indeed defendant seems to concede, that where a state in the proper exercise of its police power enacts statutes, such as those now before us, regulating a business and requiring a license to be obtained by anyone engaged therein
(Riley
v.
Chambers
(1919)
In the much cited case of
Howard
v.
State of California
(1948)
Examined in the context of these cases, the concern for the public inherent in the statute centers upon building done in California and practices of the building trades in this state
(Howard
v.
State of California, supra, 85
Cal.App.2d 361, 366); it focuses upon all those who may be involved in such building—subcontractors, materialmen, employees and owners (F
raenkel
v.
Bank of America, supra,
In our view, it was not the purpose of the Legislature in enacting the Contractors’ License Law to bring within its ambit a person who, not otherwise engaged in the contracting business in California, merely enters into negotiations or contracts in this state for a construction work or project in another state or foreign country. The purpose of the law is to
We hold that where, as in the instant case, a person offers, undertakes or contracts in this state to construct or demolish a building, project or other improvement located outside of California, such person does not thereby become one engaged in the business or acting in the capacity of a contractor within this state so as to be subject to the Contractors' License Law. Nor does the mere fact that, as here, such person’s principal place of business is in California necessarily compel a different conclusion.
Defendant refers us to
Lewis & Queen
v.
N. M. Ball Sons
Standard next contends that according to the undisputed evidence the parties after the completion of the job reached an agreement as to the amounts due Conderback which Standard promptly paid and that Conderback is bound by “the account stated by it and by the accord and satisfaction reached.” It will be recalled that these and other special defenses were the subject of the first trial at which a jury returned a verdict rejecting them. It is now urged that there is no evidence suрportive of such verdict and that this case is controlled by
Potter
v.
Pacific Coast Lumber Co.
(1951)
This defense is defined by Civil Code sections 1521 and 1523: “An accord is an agreement to accept, in extinction of an obligation, something different from or less than that to which the person agreeing to accept is entitled.” “Acceptance, by the creditor, of the consideration of an accord extinguishes the obligation, and is called satisfaction. ”
The question whether an agreement amounts to an accord and satisfaction is one of the intention of the parties and is therefore a question of fact.
(Lapp-Gifford Co.
v.
Muscoy Water Co.
(1913)
In the instant ease, the evidence pertinent to the events and transactions allegedly constituting the accord and satisfaction was in conflict. In the first place, as we have seen, Standard’s witnesses maintained that it agreed to рay the invoice of July 26, 1962, only on condition it receive “reassurance” that it was the final payment on the building and exhibits and that such reassurance was given by Conderback in its letter of August 2, 1962 (see fn. 12, ante). On the other hand, Conderback’s witness Railsback testified that he attended all of the meetings out of which the accord is supposed to have arisen and that there was no condition affixed to the payment of the invoice. Conderback also introduced testimony explaining how the letter of August 2 happened to be sent (see fn. 12, ante). According to Conderback’s witnesses, Standard’s Whitmore dictated the crucial opening sentence of the letter to Conderback’s office manager giving no explanation that this understanding had been reached between the parties and thereafter van der Woert signed the letter on the assumption that it referred to the finality of the particular billing. 22 Standard’s check did not indicate it was tendered in full and final payment.
A second and more significant consideration however is the fundamental issue raised by the parties as to the exact nature of their contractual arrangements. As we have set forth above, Standard’s evidence was directed to establishing its central thesis that the work was being done on the basis of Conderback’s firm bid of February 12, 1962, plus the costs of
Events transpiring after the alleged accord and satisfaction of July and August 1962 fall into the same pattern of plaintiff’s evidence. As to these, there was evidence that in September 1962 Standard made a further payment to Conderbaek; that in the same month the latter sent Standard a list of developments relating to unpaid accounts; that in December 1962 the parties had discussions in connection with additional bills, quite apart from the tax liability; and that Standard made a payment in February 1963.
From all of the foregoing evidence introduced by Conderback, the jury could reasonably conclude that the parties did not agree that the July 26 invoice was to be a final billing and that its payment by Standard was to constitute full payment for the building and exhibits, but could conclude that the various items of expense were to be billed from time to time until Conderback, in accordance with the parties’ customary practices in the past, had been paid for all costs of the project.
The
Potter
and
Creighton
cases relied upon by defendant do not declare rules of law different from those set forth by us herein. They are distinguishable on their own facts from the case before us and hold that upon evidence which is neither in conflict nor reasonably susceptible of conflicting inferences the respective creditors therein knew or of neces
We turn to consider defendant’s three claims of error in the admission of evidence.
1. At the first trial on the separate defenses Railsbaek testified on direct examination concerning discussions had with Mattes in the spring of 1963 about Conderback’s most recent billing and the formula applicable to it. Railsbaek was then asked if Mattes approached him with a new formula of his own to which defendant’s counsel interposed that “possibly we are getting into objectionable area” and “whether or not Standard offered to help these people out to a certain extent in April would be a matter which would be excluded from evidence” and “I don’t think that they should get into any offers made by Standard.” Plaintiff’s counsel stated that “this isn’t a settlement negotiation” and “We are not asking for offers.” The court observed that in considering whether or not there was a settlement in July or August 1962, the jury could consider what transpired thereafter and overruled the objection. The witness thereupon testified as set forth in the footnote. 23 At the second trial the same evidence was admitted over defendant’s objection that it was “an offer of settlement.” Plaintiff’s counsel stated “This isn’t an offer of settlement. This is introduction now of a different formula after years of dealing.” Standard now claims it was prejudiced before both juries.
The rule is well established that offers in compromise are not admissible in evidence as such.
(People
ex rel.
Dept. of Public Works
v.
Forster
(1962)
As we think the trial judge properly held at the first trial, evidence of discussions between the parties in 1963 was relevant on the issue then before the jury (see fn. 1,
ante)
of whether there had been an accord and satisfaction between them in July or August 1962. (See
Owens
v.
Noble, supra,
77
The problem at the second trial is a more difficult one since, as we have said, plaintiff’s theory of case was that it was to be compensated according to a pricing formula and in line with customary practices in the past. In our view, this theory did not justify the admission of what were apparently offers to compromise the then pending dispute and the admission of such evidence was error.
However, even assuming that the admission of the evidence at the first trial was error, neither such error nor the error at the second trial appears to us to be prejudicial in the light of the entire record.
(People
v.
Watson
(1956)
2. At the first trial evidence was admitted, over defendant’s objection, to the effect that prior to 1960 plaintiff had lost money on several jobs it had done for Standard and that in some cases Standard paid plaintiff more money on being apprised of the loss. This evidence of a course of dealing in the past was offered to show the contractual arrangements in the instant matter and to negate the existence of a firm bid contract. Evidence of other similar contracts between the same parties establishing a custom, habit or continuing course of business dealing is admissible as showing that on a particular occasion the thing was done as usual.
(Roberts Distributing Co.
v.
Kaye-Halbert Corp.
(1954)
3. At the first trial defendant’s counsel read into evidence portions of the testimony of Railsbaek given at a deposition taken by defendant in which the witness was asked to explain alleged discrepancies in costs in various documents already before the jury. Railsbaek testified that he could not explain in detail without records but could explain “in generalities.” In the course of this explanation he stated in the deposition that because of Conderback’s need for funds, “we would take and let go, things we were negotiating at that moment ... to get some money that would keep us going until next time. Having had past experience, long years of past experience with Standard I felt sure this would be adjusted fairly and squarely in the ultimate negotiations that followed jobs of this nature.”
The deposition testimony then continued: “ Q. [By defendant’s counsel] And you say you prepared this thing and let go of certain sums, is that right ? A. Yes, that is right.’’
Upon the request of plaintiff’s counsel and the order of the court, defendant’s counsel was then required, over his objection, to read the rest of the last answer as set forth in the footnote. 24
Defendant contends that the admission of the rest of the
It was also within the sound discretion of the trial judge to require defendant’s counsel to read all of the answer in order to obviate immediately any false or distorted impression the jury might receive from a fragmentary introduction. McCormick states the applicable rule in this situation as follows: “ [T]he prevailing practice seems to permit the proponent to prove any relevant part that he desires. It seems, however, that to guard against the danger where it exists of an ineradicable false first impression, the adversary should be permitted to invoke the court’s discretion tо require the proponent to prove so much as relates to the fact sought to be proved, that is, all that is relevant to explain or is needed in interpreting the part proved.” (McCormick, op. cit., pp. 131-132.) The trial court did not abuse its discretion in the instant case. Furthermore, we cannot see how defendant could have possibly been prejudiced anyway since its counsel, just prior to the answer in dispute, had read into evidence similar testimony (quoted by us above) as to what Railsback “felt” would be done by Standard.
Standard further complains that the court’s instructions to the first jury on accord and satisfaction compounded the claimed error since, while stating that accord and satisfaction depended on the mutual intention of the parties, it failed to state that such intention must be determined by the words and actions of the parties and that subjective motives must be disregarded. The point is without
Standard next contends that there is no evidence to support the verdict of $154,374.45 or any part thereof. The gist of the argument in support of this point seems to be this: that the so-called “firm” bid of February 26, 1962, constituted the contract between the parties and the jury by its verdict in effect disregarded the firm bid and re-evaluated the job on a time and materials basis. Standard seems content to confine its argument to these assertions and within this narrow range. Its responsibility in urging a total insufficiency of evidence extends much further. “The appellate court starts with the presumption that the evidence sustains each finding of fact [citations], and the burden rests upon appellant ‘to demonstrate that there is no substantial evidence to support the challenged findings.’ [Citations.] To this end appellant must set forth in his brief all material evidence upon the point, not merely his own proofs [citations] ; . . .”
(Davis
v.
Lucas
(1960)
We have already alluded to the central issue raised by the parties as to the contractual arrangements entered into between them. This was spelled out in detail by the second pretrial conference order. It is apparent that at the second trial the jury found in favor of plaintiff’s theory of ease and rejected defendant’s theory of ease. It follows therefore that in urging the insufficiency of the evidence defendant must do more than merely reassert its position at the trial.
We have carefully examined the record and the
In its fifth contention on appeal Standard asserts that the inclusion in the judgment of amounts for maintenance 27 and a markup on the design fee is contrary to the undisputed evidence.
As to the first item, the record shows without contradiction that, as defendant claims, the maintenance of the project was under a
separate
contract and that Conderback had been paid in full for all such services. Standard points out to us that notwithstanding this clear testimony, an amount for maintenance of $40,412.91 as calculated according to the formula advanced by plaintiff was erroneously submitted to the jury. After deduction of the sum of
As to the design fee, Standard contends that the parties did not intend that Conderback should have a markup and that as a сonsequence an excessive amount of $6,609.37 is included in the judgment. We cannot agree. Although Standard points to initial correspondence in which no mention is made of a markup on the design fee, there was. testimony that the markup was to be applied at the end of the job. This was a part of plaintiff’s general theory of ease, involving the prior course of dealing between the parties which the jury passed upon favorably to plaintiff.
Finally Standard contends that the court erred in awarding interest on the judgment from the date of filing the original complaint. 28
Civil Code section 3287 provides in relevant part: “Every person who is entitled to recover damages certain, or capable-of being made certain by calculation, and the right to recover which is vested in him upon a particular day, is entitled also to recover interest thereon from that day,.. . .” Under this section interest cannot be awarded prior to judgment when the amount of damages cannot be ascertained except on conflicting evidence.
(Lineman
v.
Schmid
(1948)
In the instant matter, at least according to plaintiff’s theory of case which the jury accepted, there is no single contractual document in which the sum due or the means of calculating it are clearly provided for. Indeed, according to plaintiff’s theory, compensation is predicated on an “open ended” purchase order involving application of a pricing formula and negotiations between the parties, all in accordance with a prior course of dealing. We detect an inherent complexity in the process. The applicable test then is whether the exact sum found to be due plaintiff was known to defendant in that it was certain or capable of being made certain by calculation. (See
Gray
v.
Bekins
(1921)
The judgment is modified by deducting therefrom the sum of $8,641.31 and by eliminating therefrom interest on the judgment from the date of the commencement of the action to the date of entry of judgment on the verdict and as thus modified the judgment is affirmed. Plaintiff is to recover its costs on appeal.
Molinari, J., and Sims, J., concurred.
Appellant’s petition for a hearing by the Supreme Court was denied March 22, 1966.
Notes
The special interrogatories were: “1. Did the parties agree between themselves in July or August of 1962 as to the total amount due Conderback, Inc. for the erection of the building and the construction and installation of displays in the building at the Seattle World’s Pair; 2. Did the parties agree between themselves in January, 1963, as to all sums due Conderback for all work done by Conderback, Inc. for Standard Oil at the Seattle World’s Pair.”
Conderbaek suspended business activities in July 1963, approximately two months after the commencement of this action on May 13, 1963. It was not a going business at the time of trial.
In general outline, Conderback’s standard formula which it had used over the years consisted of the following principal factors: (a) the cost of labor plus a 100 percent markup plus an additional markup for fringe benefits; (b) the cost of materials plus a 50 percent markup; (e) the cost of subcontracted work plus a 10 percent markup “as a rule,” subsequently changed to 17.625 percent as an “agency markup” customarily paid agencies by Standard when they supervised subcontractors.
This followed a letter of June 15, 1961, from Conderback to Mattes offering an “estimated quotation for budgeting purposes only” of $275,194.
The letter further stated that “any major changes from building modеl or additional mechanical displays, we are sure you will understand, will be confirmed in writing and subject to negotiation” and presented a plan for payment consisting of “a blanket advance progress billing substantiated within 30 days” to be made on the first of each month, payment thereon on the 10th of the month, and “detailed billing for the payment ... by the end of the month.” There is testimony that these arrangements were made because Conderback did not have “the cash load to finance this job.”
This purchase order is attached to and incorporated by reference in plaintiff's amended complaint which alleges the delivery thereof on July 7, 1961, defendant’s promise to pay for labor, material and expenses, plus amounts for overhead and profit, and the delivery on August 10, 1961, of a modification (request for adjustment) of such order. Plaintiff’s amended complaint is based solely upon such purchase order and modification.
The letter stated in part: “At the inception of this project, we offered our original estimate to you for $275,000.00. This was subsequently formalized in writing for $253,000.00 and we undertook the project. Since starting the project there has been a series of changes and additions to the project. To date we have written and verbal approval for the following changes and additions’ ’ in the amount of $307,518.12 including “Formal estimate” of $253,000 (apparently $230,000 plus the 10 percent override). It concluded: “The changes and additions listed on the above and preceding pages have materially increased our original estimate to you for the entire exhibit. It is hoped that these changes and additions can he negotiated and approved as soon as possible so that our delivery date will not be impaired.” (Italics added.)
The letter concluded: “The price is based on designs and details as planned as of February 12, 1962. Any major changes or additions requested to the project will he negotiated and confirmed to you in writing before expense is incurred.” (Italics added.)
This is made the basis of Standard’s first affirmative defense and of all four counts of its cross-complaint.
This was attributed to: (1) Conderback’s inability to coordinate design with estimated budget; (2) numerous changes to exhibits, art and copy; (3) necessity of quoting in “our February 12, 1962 budget quotation ’ ’ on many exhibits not then in final design concept.
Attached schedules showed §418,759.32 as of July 16, 1962, plus the CAdditional Requested” and invoiced of $39,848.87 producing a grand total of $458,608.19, of which §411,259.32 had been paid.
This letter to Mattes from van der Woert was embraced within the first special interrogatory at the first trial (see fn. 1, ante). It read: “Rеgarding our invoice 21000-11, dated July 26, 1962, the amount will cover final hilling for the erection of the building and construction and installation of the displays within the exhibit building. The amount does not include maintenance, dismantling, sales tax, additional design fees, nor additional changes to the exhibit since June 1, 1962.” (Italics added.)
Andrew Leong, office manager and accountant for Conderbaek, gave the following explanation at the first trial as to how the letter came to be written: On August 2, 1962, Standard’s Whitmore telephoned him and requested such a letter, even dictating the first sentence. Whitmore gave no indication that this was the agreement of the principals and at the time both Railsbaek and van der Woert were out of the office. Leong had the letter typed and placed on van der Woert’s desk for signature. "Van der Woert then signed the letter assuming that it referred to the finality of that particular billing.
This letter referred to three subcontractors and Tepper, the designer. It concluded by stating that Conderbaek had never included the amounts from the first three to Standard “in our final billing. We feel that if the explanations are satisfactory, we will negotiate with them.”
According to Whitmore, whose testimony is relied upon by bоth parties on this point, van der Woert said there were a number of items previously understood not to be Standard’s responsibility which van der Woert had not been able to negotiate with subcontractors in Seattle. He inquired whether Whitmore “would meet with him and discuss whether or not Standard would be willing to pick up some of these costs because he was going to be stuck with them, and I said yes, I would meet with him, ...” After the meeting, Whitmore requested van der Woert to send a list of the items.
The list not in the form of an invoice was captioned: “Standard Oil Company Final Billing Century 21 World’s Fair. ’ ’
In the sum of $3,110.19 (later adjusted) and captioned “Be: Standard Oil Company of California final billing, Century 21, World’s Fair.’’
According to plaintiff’s contentions made at the pretrial conference and plaintiff’s evidence at trial, the sum to be paid plaintiff for the completion of the entire job was to be computed by the following formula: (1) the amount paid by plaintiff to its subcontractors plus a 17.625 percent markup for supervision; (2) plaintiff’s own labor costs plus 100 percent markup, plus 19.8 percent of said labor costs to cover fringe benefits, plus an additional 10 percent on the total sum; (3) plaintiff’s own cost of materials plus a markup of 50 percent; (4) miscellaneous direct expenditures, e.g., freight and telephone, plus a 10 percent markup; and (5) expenses of plaintiff’s officers while in Seattle at $200 a day each (compare customary formula of plaintiff as outlined in fn. 3, ante). Railsbaek testified that by agreement between the parties, the above formula was to be applied to the contract entered into.
On May 31, 1963, "the amended complaint prayed for judgment in the sum of $171,026.80 ($665,400.85 less $494,374.05 paid).
This issue was not raised by the pleadings or designated as an issue in dispute in the interlocutory pretrial conference order made before the first trial. At the start of the first trial it was asserted in a trial memorandum filed by defendant. It was thereafter raised in defendant’s motion for a judgment notwithstanding the verdict (necessarily made after the second trial) upon denial of which the court stated: “It is my opinion and the Court finds that plaintiff did not have to possess a California Contractor’s license for the performance of the work in the State of Washington; . . .” Although the issue was timely raised below, “It is immaterial that the parties, whether by inadvertence or consent, even at the trial dо not raise the issue. The court may do so of its own motion when the testimony produces evidence of illegality. [Citation.] It is not too late to raise the issue on motion for new trial [citation], in a proceeding to enforce an arbitration award [citation], or even on appeal. [Citation.]”
(Lewis Queen
v.
N. M. Ball Sons
(1957)
Hereafter unless "otherwise indicated all section references are to the Business and Professions Code.
Seetion 7030 was repealed in 1963 and in substance incorporated within section 7028, which was amended at the same time.
Conderback’s invoice of July 26, 1962, set forth a column of 16 items, with amounts of billing for only six items, the columnar spaces opposite the others being left blank. The six items billed totalled $39,848.87. Attached to the invoice are detailed schedules covering the same 16 items with a series of columns headed “Amount as of 7/16/62,” “Additional Requested,” “Total,” “Amount Paid,” “Amount Requested,” “Amount to be Billed.” The invoiced amount of $39,838.87 appears as a footing in the columns “Additional Requested” and “Amount Requested. ’ ’
Railsback testified: ‘' In the meeting the day before they had offered us—this group of nine people, as I recall, had offered us a 17.625 markup on the ovеr-all cost of the job. This amounted to, well, none on the overall costs on some balance of it. It amounted to $7,000, which we refused. Mr. Mattes called the ensuing morning, called me personally and offered a different formula that amounted to $28,000, which I also refused, ’ ’
Mr. Brown, defendant’s counsel, then read the following complete answer: “Tes, that is right. Putting them off, may I say, putting off certain sums or certain portions of certain sums, hoping that and trusting that they would do as we had previously been on jobs of this nature. I said that this fell into four general areas. ’ ’
Code Civ. Proc., § 1854, provides: "When part of an act, declaration, conversation, or writing is given in evidence by one party, the whole on the same subject may be inquired into by the other; when a letter is read, the answer may be given; and when a detached act, declaration, conversation, or writing is given in evidence, any other act, declaration, conversation, or writing, which is necessary to make it understood, may also be given in evidence. ’ ’
The instructions in question are; "Ton are instructed that question of the existence of an accord and satisfaction depends upon the intention of the parties, whiсh must be determined from all the surrounding circumstances, both oral and written. There must be a meeting of the minds between the parties to an accord, whether there was an accord in this case, is a question for you as jurors to decide. ’ ’
"E’er there to be a valid accord and satisfaction you must find that both parties knew and intended that a final settlement was taking place and that each knew and understood the terms of the settlement,”
Maintenance was a ‘‘24-hour round-the-clock service” at the Fair building by three of Conderback’s employees throughout the course of the Fair. They would keep the building up, clean it, “work on things, be called at any time to repair, etcetera.”
The judgment on the verdict provides for “interest thereon at the rate of seven percent (7%) per annum from the date the obligation became due, being the date of the filing of the Complaint in this action, being May 13, 1963, ...”
Wken asked at the trial to explain these divergent results, Railsback testified: "We were at the time, I believe, auditing or in the course of auditing the job as a whole, and these figures would change, I woxild dare say if they were audited today, they would change again.” (Italics added.)
