110 P. 973 | Cal. Ct. App. | 1910
This is an action to restrain the defendant from levying a writ of attachment. In their complaint the plaintiffs alleged ownership and possession of certain quartz mining claims, known as the Dreisam mines, "together with all the fixtures and all other machinery and tools used in working and developing said mines"; that on June 15, 1908, plaintiffs entered into a written agreement with the Parlin Gold Mining Company, whereby plaintiffs agreed to sell said mines to said company for a certain sum, which was to be paid on or before May 1, 1909; that for a consideration the time of payment was extended to September 1, 1909; that, *22 about June 15, 1908, said company entered "in and upon said mines and proceeded to work and develop the same, and in the working and developing of said mines placed and used thereon certain electrical machinery," being certain motors, lighting transformer and pump, fully described; "that by the terms of said agreement all machinery and tools used by the Parlin Gold Mining Company in the working and development of said mines became, have been and now are fixtures attached to said mines, and ever since said motors and electrical machinery have been placed upon and used in the working and development of said mines have been and now are the property of said plaintiffs until said mines shall have been fully paid for by said Parlin Gold Mining Company in accordance with the terms of said agreement"; that, on August 29, 1909, defendant, as sheriff, by virtue of a writ of attachment issued out of the superior court of Tuolumne county, in an action wherein one Claytor is plaintiff and the Parlin Mining Company, a corporation, is defendant, levied upon said property and "did commence the moving of said electric motors, lighting transformer and electric pump from said Dreisam Mines," and said defendant, as such sheriff, threatens to continue the removal of said machinery "from off said property, all of which will cause these plaintiffs great and irreparable injury. That it is necessary that defendant be restrained from moving from said mines said electric motors and electrical machinery to prevent a multiplicity of judicial proceedings." Plaintiffs pray that defendant be restrained from levying upon said property and machinery, "and from interfering with or taking or removing any of said machinery from said Dreisam Mines to which they are now affixed," and for further relief.
The complaint was filed on August 30, 1909, and on the same day the court made its restraining order and fixed the hearing for September 3, 1909, at which time, by consent of the parties, the order to show cause and time in which defendant was to plead was continued to September 24, 1909, at which time defendant filed a general demurrer, a motion to dissolve the restraining order on the ground that the complaint does not show sufficient facts to justify the restraining order, and also filed an answer to the complaint. On September 25, 1909, and before the hearing, plaintiffs served and filed a supplemental *23 complaint alleging that they are now, and during all the times mentioned therein they have been, the owners of said mining property and said electrical machinery, and, that since September 1, 1909, and after the filing of the original complaint, the agreement set forth in plaintiffs' complaint expired and terminated, and the deed placed in escrow . . . has been withdrawn by plaintiffs, and the said company now has no right, title or interest in said described mines; that defendant threatens to remove from said mines said machinery described in said original complaint, and such removal will work great and irreparable injury to plaintiffs. On October 4, 1909, defendant served and filed his answer to said supplemental complaint, and on October 8, 1909, the court made its minute order denying defendant's motion to dissolve the restraining order, and granted the injunction, upon plaintiffs giving bond for $500. The formal order was made October 9, 1909, and recites that the hearing came on regularly September 24, 1909, "and after the introduction of oral and documentary evidence the hearing was continued for argument until Monday, the twenty-seventh day of September, 1909, and on said date said matter was duly argued by the respective counsel and submitted to the court for its decision."
In his answer to the original complaint defendant denies, on information and belief, most of its averments. Likewise he denies the averments of the supplemental complaint, on information and belief; admits that he threatens to remove from said mines said fixtures as set forth in plaintiffs' original complaint, but denies that it will work great or irreparable injury; avers that he is acting in obedience to a writ of attachment in an action wherein one Claytor is plaintiff and Parlin Mining Company is defendant, as alleged in the original complaint.
Defendant appeals from the order "granting plaintiff an injunction pendente lite, as prayed for in the complaint"; claiming that neither the order denying the motion to dissolve the restraining order nor the order granting the injunction should have been made, for the reason that there was no sufficient showing made in the complaint.
The complaint alleged that the property which defendant threatened to remove had become fixtures to the realty and *24 part thereof, and that, by the terms of the agreement, it was to belong to plaintiffs, as did the other realty, "until said mines shall have been fully paid for by the said Parlin Gold Mining Company in accordance with the terms of the said agreement." Presumably, the agreement, when introduced at the hearing (it was not set forth in the complaint or answer) supported plaintiffs' averments. It would have been more satisfactory had the complaint set forth the agreement in terms so as to have shown from its face that the averments of the complaint were thereby supported, but we think there were sufficient facts alleged to justify the restraining order pending the hearing.
It is argued by appellant that the Parlin Gold Mining Company had the right of possession and the right of property until September 1, 1909, subject to payment of the full purchase price of the property on that day, and, hence, plaintiffs had no rights therein until after that date. But the right of the company was a right to prospect and develop the mines; it had no right to commit waste or remove from its situs that which constituted a part of the realty, other than ore bodies or minerals, or to make such use of timber and the like as might be necessary in the working of said mines. Obviously, no creditor had any greater right. Appellant cites Miller v.Waddington,
Respondents state in their brief that since this motion was heard and determined, "the case has been tried on its merits, findings of fact and conclusions of law were duly made, and judgment entered in favor of plaintiffs." This is not denied. We cannot act upon this statement alone, but if it be true, it would avail appellant nothing should he prevail on this appeal. Regardless, however, of this fact, we think the order should be affirmed, and it is so ordered.
Hart, J., and Burnett, J., concurred.