Concerned Citizens v. CrossgatesConcerned Citizens v. Crossgates
Lead Opinion
Proceeding pursuant to CPLR article 78 (transferred to this court by order of the Supreme Court at Special Term, entered in Albany County) to review a determination of the Commissioner of the State Department of Environmental Conservation which granted certain permits to intervenorrespondent. In June, 1979, Pyramid Crossgates Company (Pyramid) applied to the Department of Environmental Conservation for permits pertaining to stream protection, impоundment structures, freshwater wetlands, indirect sources of air pollution and discharges to the waters of the State, which were needed by Pyramid for the construction of a proposed regional shopping mall in Albany County. Follоwing preliminary proceedings and 81 days of hearings, in which petitioners participated, the Administrative Law Judge issued his hearing report which contained numerous findings of fact and a recommendation that the permits be denied. Respondent commissioner substantially adopted the report, but rather than deny the permits the commissioner concluded that there were certain points which had not been sufficiently addressed by the parties to enable completion of a final environmental impact statement and a final determination on the permit applications. The commissioner provided a detailed list of the “shortcomings” and directed Pyramid to submit relevаnt information within six months. He further directed that copies of all submitted material be made available to all parties who actively participated in the hearing, and he afforded all parties the opportunity to еstablish the need for further hearings. After reviewing all submittals, comments, and replies filed by Pyramid and other parties pursuant to his prior decision, the commissioner determined that an adjudicatory forum was not necessary for resolutiоn of the remaining issues. Thereafter, the commissioner issued a determination denying the permits “upon technical grounds consisting of an interaction between traffic analyses and air quality modeling”. He concluded that since Pyramid had met all other criteria for the issuance of the permits, and since the record suggested that Pyramid might be able to demonstrate specific mitigation measures to reduce projected carbon monoxide сoncentrations to satisfactory levels, Pyramid should have a reasonable time
Mikoll, J., dissents and votes to annul in the following memorandum.
Dissenting Opinion
I respectfully dissent. The commissioner’s failure to prоvide a public hearing on submissions made after the November 28, 1980