CONCERNED CITIZENS OF COSTA MESA, INC., et al., Plaintiffs and Appellants, v. 32ND DISTRICT AGRICULTURAL ASSOCIATION et al., Defendants and Respondents.
L.A. No. 32144
Supreme Court of California
Dec. 1, 1986
January 22, 1987
42 Cal. 3d 929
Richard L. Spix for Plaintiffs and Appellants.
John K. Van de Kamp, Attorney General, R. H. Connett, Assistant Attorney General, Dennis W. Dawson, Deputy Attorney General, Neil Papiano, Deborah M. Nesset and Iverson, Yoakum, Papiano & Hatch for Defendants and Respondents.
OPINION
REYNOSO, J.—What may a citizens’ group do when a stadium is constructed in their neighborhood substantially different than planned? The citizens charge that the changes were made without notice and that they did not know of the changes, and could not through the exercise of reasonable diligence have discovered them, until the first and overly noisy concert took place. On those facts, does the California Environmental Quality Act protect the citizens? We hold that it does.
The California Environmental Quality Act (
The precise issue in this case is whether the 180-day limitation period bars a suit if an EIR relating to the project has been filed, but two important
I.
In 1977, the 32nd District Agricultural Association (district), which constructs, maintains, and operates facilities at the Orange County Fairgrounds, proposed to improve and upgrade the fairgrounds, including the Pacific Amphitheater within the grounds. The district prepared an EIR in connection with the project after a public hearing. Construction of the theater commenced in February 1983, and the first concert at the newly completed theater was held on July 27 of that year.
On January 20, 1984, plaintiffs, a nonprofit corporation whose membership is comprised of some of the approximately 24,000 residents who live near the fairgrounds, and two individuals who also reside nearby, filed suit against the district and Ned West, Inc. (West), the builder and operator of the theater under a contract with the district. Their first cause of action, which is the focus of our inquiry here, alleged that the district violated CEQA by making substantial changes in the theater after the EIR was filed without notification to the public or the filing of a subsequent EIR.
According to the complaint, the EIR described the theater as containing 5,000 fixed seats with additional seating on the grass. It was to be located on six acres of land, and its stage would be directed away from the sensitive residential areas to the north of the fairgrounds. Performing Arts Associates, a group formed specifically for the venture, would manage the theater and market its entertainment to the “affluent people available and willing to attend quality shows such as those presented at the Greek Theatre.” The EIR stated that: (1) there was no problem with on-site parking, (2) noise was a major concern of area residents, and (3) mitigation studies would be undertaken early in the planning process to address the concerns of nearby residents. In 1978, the district determined to carry out the theater project, after finding that the EIR was complete and adequately addressed environmental issues.
The complaint alleges that the district then entered into a contract with West in March 1980 that authorized West to make substantial changes in
The complaint asserts that the district had a duty to prepare a subsequent or supplemental EIR, as required by
Plaintiffs sought both declaratory and injunctive relief.2 Defendants demurred to the complaint, claiming that the cause of action was barred by the limitation period in subdivision (a) of
II.
We begin with a summary of some of the relevant statutory provisions. CEQA describes an EIR as “an informational document which . . . shall be considered by every public agency prior to its approval or disapproval of a project.” (
We have indicated that CEQA‘s fundamental objective is “to ensure ‘that environmental considerations play a significant role in governmental decision-making.‘” (Fullerton Joint Union High School Dist. v. State Bd. of Education (1982) 32 Cal.3d 779, 797 [187 Cal. Rptr. 398, 654 P.2d 168].) To facilitate CEQA‘s informational role, the EIR must contain facts and analysis, not just the agency‘s bare conclusions or opinions. This requirement enables the decision-makers and the public to make an “independent, reasoned judgment” about a proposed project. (Santiago County Water Dist. v. County of Orange (1981) 118 Cal.App.3d 818, 831 [173 Cal.Rptr. 602]; People v. County of Kern (1974) 39 Cal.App.3d 830, 841 [115 Cal.Rptr. 67] (requirement of detail in EIR “‘helps insure the integrity of the process of decision by precluding stubborn problems or serious criticism from being swept under the rug.‘“); see also
“Public participation is an essential part of the CEQA process” (
As one commentator has noted, “the ‘privileged position’ that members of the public hold in the CEQA process . . . is based on a belief that citizens can make important contributions to environmental protection and on notions of democratic decision-making. . . .” (Selmi, The Judicial Development of the California Environmental Quality Act (1984) 18 U.C. Davis L.Rev. 197, 215-216.) “CEQA compels an interactive process of assessment of environmental impacts and responsive project modification which must be genuine. It must be open to the public, premised upon a full and meaningful disclosure of the scope, purposes, and effect of a consistently described project, with flexibility to respond to unforeseen insights that emerge from the process.” (County of Inyo v. City of Los Angeles (1984) 160 Cal.App.3d 1178, 1185 [207 Cal.Rptr. 425].) In short, a project must be open for public discussion and subject to agency modification during the CEQA process. (Ibid.) This process helps demonstrate to the public that the agency has in fact analyzed and considered the environmental implications of its action. (No Oil, Inc. v. City of Los Angeles (1974) 13 Cal.3d 68, 86 [118 Cal.Rptr. 34, 529 P.2d 66].)
Turning now to plaintiffs’ complaint, we apply the established principle that “a general demurrer admits the truth of all material factual allegations in the complaint [citation]; . . . the question of plaintiff‘s ability to prove these allegations, or the possible difficulty in making such proof does not concern the reviewing court.” (Alcorn v. Anbro Engineering, Inc. (1970) 2 Cal.3d 493, 496 [86 Cal.Rptr. 88, 468 P.2d 216]; accord Perdue v. Crocker National Bank (1985) 38 Cal.3d 913, 922 [216 Cal.Rptr. 345, 702 P.2d 503].) “[I]f there is a reasonable possibility that a defect in the complaint can be cured by amendment or that the pleading liberally construed can state a cause of action, a demurrer should not be sustained without leave to amend.” (Minsky v. City of Los Angeles (1974) 11 Cal.3d 113, 118 [113 Cal.Rptr. 102, 520 P.2d 726].)
The gravamen of plaintiffs’ first cause of action is that the district violated
Two matters are clear at the outset of our analysis. First, the complaint alleges a cause of action for violation of CEQA, and second, if the provisions of
It cannot be doubted that some of the changes allegedly made in the project by the contract between the district and West could be characterized as substantial enough to require the district to file a subsequent EIR to assess their environmental effects, as required by
It is equally clear that the complaint was filed more than 180 days following the commencement of construction of the theater. Although construction began in February 1983, the complaint was not filed until January 20, 1984. At first blush, therefore, the action seems barred.
But plaintiffs make an argument which persuades us that the statute must be interpreted to the contrary—only then will its purpose be fulfilled. They alleged that they did not know of the changes made in the project by the contract with West, and could not with reasonable diligence have discovered them, within 180 days from the time construction of the theater commenced because the district did not make the changes public and did not give notice that it had determined that these changes did not require a subsequent EIR, if such a determination was in fact made. Thus, when construction began, plaintiffs expected the project approved by the district to be the same one analyzed in the EIR, and they had neither actual nor constructive notice to the contrary.
We agree that the action should not be barred simply because of plaintiffs’ failure to file their action alleging a violation of CEQA within 180 days of
Here, plaintiffs allege that the theater project was the subject of an EIR but that the actual project built differed substantially from the facility described in the EIR. The lack of public notice that the agency had authorized these substantial changes compromised the goal of public participation in the environmental review process. In fact, the agency‘s failure to prepare a supplemental or subsequent EIR effectively deprived the public of any meaningful assessment of the actual project chosen by the agency. (Mira Monte Homeowners Assn. v. County of Ventura, supra, 165 Cal.App.3d at p. 365.) Indeed, the commencement of a project in these circumstances is more misleading than if the agency had prepared no EIR, since the public might justifiably but erroneously assume that the project being built is the one discussed in the EIR. (Cf. Coalition For Canyon Preservation v. Bowers (9th Cir. 1980) 632 F.2d 774, 779 [63 A.L.R.Fed 1] [citizens have right to assume that public officials will comply with applicable environmental law].) As a result, the public would fail to challenge the agency‘s noncompliance with CEQA within time limitations measured from commencement of construction.
It does not follow, however, that an agency‘s failure to comply with CEQA may be challenged at any time without limitation. Plaintiffs suggest that their action was timely because it was filed a few days before the expiration of 180 days after the first concert was held at the theater on July 27, 1983. They alleged that they lacked actual or constructive notice of the changes before that time.
We reject plaintiffs’ position as contrary to the Legislature‘s intent. By providing in
We can give effect to the statute, while simultaneously vindicating the Legislature‘s goal of promoting public comment on projects that may have environmental significance, by holding that the phrase “commencement of the project” in subdivision (a) of
Because we review an order sustaining a demurrer without leave to amend in this case, we have to accept the complaint‘s material factual allegations as true. Plaintiffs alleged that they neither knew nor could with reasonable diligence have discovered that a cause of action had accrued to them until 180 days before the date they filed their complaint. While a trier of fact
Accordingly, we reverse the judgment of the Court of Appeal insofar as it affirms the trial court‘s order dismissing the plaintiffs’ first cause of action.
Bird, C. J., Broussard, J., and Grodin, J., concurred.
MOSK, J.—I dissent.
The majority interpret the relevant statutory provisions properly, but they err in analyzing the complaint.
The law is clear that if a public agency makes substantial changes in a project after filing an environmental impact report (EIR) and fails to file the supplemental EIR those changes require, an action challenging the agency‘s noncompliance with the California Environmental Quality Act (CEQA) “must be filed within 180 days of the time the plaintiff knew or should have known that the project under way differs substantially from the one described in the EIR.” Assuming arguendo these plaintiffs did not actually know of the variations—which is difficult to believe—the question is when they should have known that the amphitheatre under construction differed substantially from the project described in the EIR.
In ruling on a general demurrer we must accept as true “all the material factual allegations in the complaint.” We are not, however, compelled to accept as sound the various legal conclusions set forth in the complaint. Nor are we prohibited from rationally reading the factual allegations.
The majority obviously harbor some reservations about the validity of the complaint, for their opinion observes that “‘if there is a reasonable possibility that a defect in the complaint can be cured by amendment or that the pleading liberally construed can state a cause of action, a demurrer should not be sustained without leave to amend,‘” citing Minsky v. City of Los Angeles (1974) 11 Cal.3d 113, 118 [113 Cal.Rptr. 102, 520 P.2d 726]. In this case, however, plaintiffs were given leave to amend and elected instead to stand on their complaint. In such situations we construe a complaint strictly, and we presume the plaintiffs have stated “as strong a case as [they] can.” (Gonzales v. State of California (1977) 68 Cal.App.3d 621, 635 [137 Cal.Rptr. 681]; see also Sarro v. Retail Store Employees Union (1984) 155 Cal.App.3d 206, 211 [202 Cal.Rptr. 102].) Thus the majority
Plaintiffs filed their complaint on January 20, 1984. That complaint was untimely under the rule now adopted if it was filed more than 180 days after plaintiffs knew or should have known of the substantial changes in the amphitheater plans. January 20, 1984, is 180 days after July 24, 1983. Therefore, if plaintiffs should have known of the changes by July 23—or any earlier date—their complaint was untimely.
But, maintain plaintiffs, the defendants “concealed and misrepresented” facts material to their knowledge. We are not told how or in what manner the concealment was accomplished in connection with construction that took place in public view and, as alleged in the complaint, within sight of the plaintiffs who “have homes adjacent or proximate to the Orange County Fairgrounds.”
Plaintiffs concede that construction commenced in February 1983, and that the amphitheater was fully completed in time for a public concert on July 27. If the amphitheater was ready for use on July 27, it is impossible to rationally conceive a set of facts under which plaintiffs would not have been aware of the substantial changes more than three days earlier. Indeed, their complaint is deficient in alleging no such unusual facts.
Rome was not built in a day. Nor was this $11 million project built in three days. Plaintiffs concede that the amphitheater was constructed in a corner of the Orange County Fairgrounds, and that this was their home neighborhood. They allege that the amphitheater occupied 10 acres instead of the originally projected 6, and that the stage now faced a direction different from that originally proposed.
A court must be deemed naive if it is asked to believe these neighbors failed to observe construction on 10 acres rather than 6 until after the first public concert. Justice may wear a blindfold, but these plaintiffs do not allege they were similarly handicapped.
My concern with the majority result is three-fold. First, it puts these defendants to the time and expense of a trial and unnecessarily burdens the courts. Second, and more importantly, under Parkinson‘s Law the majority opinion will inevitably encourage numerous frivolous challenges to public or private projects after the statutory period has run. Under this new prevailing theory, complainants may await completion of a project that has been under construction for months before challenging its propriety. All
I would hold that the complaint was untimely and the demurrer was properly sustained.
Lucas, J., and Panelli, J., concurred.
Respondents’ petitions for a rehearing were denied January 22, 1987.
