Concannon and his wife made an oral agreement with Galanti by which Galanti, for $17,800, was to build a house for the Concannons in accordance with plans and specifications. In various respects Galanti intentionally deviated from the plans. His work and that of “his employees was, for the most part, not good.”
The Concannons took occupancy of the house in mid-July, 1958, ‘ ‘ and from that time, frequently brought to . . . [Galanti’s] attention” defective work. They gave to him written notice of defective work on two occasions (November 12, 1958, and March 26, 1959). By September 7, 1958, the Concannons had paid Galanti $16,435 on the contract price of $17,800 and on September 29,1958, Leo Concannon gave Galanti a promissory note for $1,078.95, the balance of the price less certain agreed adjustments ($286.05). The total of the payments, the note, and the adjustments was equal to the agreed price. Concannon, however, did not pay the note when it became due on December 29,1958.
*73 The Concannons brought an action to recover for breach of the contract, and Galanti declared in set-off, alleging among other things the nonpayment of the note. The case was referred to an auditor, whose findings of fact were to be final. The auditor, in addition to finding the subsidiary facts already stated, made the following findings: (1) The fair market value of the house, if completed in accordance with the plans and specifications, would have been $20,000, but, as in fact built by Galanti, was $10,000. (2) The ‘* 1 fair value of [the] labor and materials to complete the work under the . . . contract and to correct defective workmanship, which can be corrected, . . . [is] $5,000.” (3) The “diminution of . . . market value . . . because of defective work which cannot be economically . . . corrected . . . [is] $5,000.”
The auditor found generally for the Concannons in the sum of $10,000 for breach of the contract. On the counts of the declaration in set-off, he found for the Concannons, either because of failure of proof by Galanti or because Galanti had intentionally deviated from the contract. The Concannons’ motion for judgment on the auditor’s report was allowed. The case is here on Galanti’s appeal.
1. Galanti attempts, apparently for the first time on appeal (cf.
Donahue
v.
Dal, Inc.
2. The Concannons were entitled to damages sufficient to put them in as good a position as if there had been no breach and the contract had been completed. See
Walsh
v.
Cornwell,
*75
The auditor’s finding of total damages for G-alanti’s breach of contract in the sum of $10,000 thus was warranted. The Concannons, however, should not be paid more than the full equivalent of their bargain. They should have had a house worth $20,000 for a payment of $17,513.95. They should not receive the equivalent of $20,000 for a payment of only $16,435. Thus their recovery must be reduced by the portion of the adjusted price which has not been paid, the amount represented by the unpaid note for $1,078.95. See
Ficara
v.
Belleau,
3. The order for judgment for the Concannons is to be modified to allow a total recovery by them of $8,921.05 with interest from the date of the writ. See
Palmer
v.
Stockwell,
So ordered.
