Conart, Inc. v. Hellmuth, Obata + Kassabaum, Inc.Conart, Inc. v. Hellmuth, Obata + Kassabaum, Inc.
ConArt, Inc., is the company that did the concrete and stone work on the construction of the Shelby-Hall Interdisciplinary Sciences Building on the University of Alabama campus under a subcontract to the general contractor. Hellmuth, Obata + Kassabaum, Inc. was the architectural firm and supervised construction. As often happens with large construction projects, there were disputes and those disputes led to litigation.
ConArt sued Hellmuth in federal district court. Hellmuth had claims against Co-nArt that had been assigned to it by another party (the general contractor) in an earlier settlement of their differences. The contract between ConArt and that other party, which gave rise to the claims that Hellmuth had been assigned, contained an arbitration clause. After ConArt sued it, Hellmuth, relying on the arbitration clause, filed a demand for arbitration of the assigned claims. ConArt’s direct claims against Hellmuth, which were the basis of its lawsuit, were not subject to an arbitration agreement.
ConArt responded to Hellmuth’s arbitration demand by amending its complaint to include a count seeking a declaratory judgment that the claims Hellmuth was asserting against it were not arbitrable, and seeking an injunction to prevent the arbitration proceedings Hellmuth had demanded. ConArt contended that the claims against it that Hellmuth had been assigned were not covered by the arbitration clause, while Hellmuth contended that they were. The arbitration clause itself provided that the court would decide whether claims were arbitrable. The district court did so, concluding that the assigned claims Hellmuth had against Co-nArt were arbitrable. It declined to enter a declaratory judgment to the contrary
That ruling left the original claims that ConArt had asserted against Hell-muth pending before the district court. In spite of that, ConArt filed an appeal of the district court's order declining to declare the claims Hellmuth was asserting against it non-arbitrable and refusing to enjoin them. The first, and as it turns out last, issue before us is whether we have jurisdiction to decide this appeal. The order ConArt is seeking to have reviewed is not a final order within the meaning of
The appealability of interlocutory orders disposing of arbitration issues is governed by
ConArt argues that 28 U.S.C- § 1292(a)(1), which authorizes interlocutory appeals generally of orders “refusing ... injunctions” gives us jurisdiction over this appeal. That argument has too much throw weight. Accepting it would write out FAA
Instead, when presented with a potential overlap between the broadly sweeping terms of a statute of general application that appear to apply to an entire class, and the narrow but specific terms of a statute that apply to only a subgroup of that class, we avoid conflict between the two by reading the specific as an exception to the general.
See Edmond v. United States,
Subsection 1292(a) of Title 28 preceded the Judicial Improvements and Access to Justice Act, which amended the Federal Arbitration Act to include the provision governing appellate jurisdiction of arbitration orders that is now contained in
We are mindful of ConArt’s insistence that even if the order refusing to enjoin an arbitration cannot be reviewed interlocutorily because of
Besides, the “waste not” reasoning in favor of interlocutory review that ConArt urges on us is another argument that is too strong for its purpose. If we base jurisdiction on the desire to avoid the risk of arbitration proceedings that may later be held to be unnecessary, every order refusing to enjoin arbitration would be reviewable. Nothing would be left of
The appeal is DISMISSED for want of appellate jurisdiction.
Notes
. All decisions from the Fifth Circuit rendered before October 1, 1981 are binding precedent on the Eleventh Circuit.
See Bonner v. City of Prichard,