Opinion by
The Commonwealth of Pennsylvania through its Department of Mines and Minerals, now the Department of Environmental Resources, (Commonwealth) instituted this action against The Hartford Accident and Indemnity Company (Hartford) which is the surety on a performance bond for the construction of a water demineralization plant by the Pitt Construction Company (Pitt). Hartford has filed preliminary objections to the Commonwealth’s complaint in the
This matter arises out of a contract which was awarded by the Commonwealth in 1969 to Pitt to construct a water demineralization plant for the pricе of $669,680. The contract incorporates by reference the plans and specifications for the project and it provides that the Commonwealth will retain up to 10% of the contract price for one year after completion and acceptance of the plant. It also states that if the plant fails to meet the performance specifications and if Pitt does not remedy the failure within that time, Pitt forfeits the monies retained by the Commonwealth. Pitt subcontracted the design, construction and installation of two Continuous Countercurrent Ion Exchange (CC-IX) units to Chem-Seps. In 1972, Pitt went out of business. The plant allegedly did not comply with the performance standards because the plant as built does not produce the specified quantity of water.
The Commonwealth contends that the failure of the plant to produce the specified quantity of water is a breach of the contract and that Hartford, as the surety for performance of the contractor, is thеrefore either liable for the full obligation of the bond or should complete the contract at its own expense.
Hartford argues by way of its preliminary objections in the nature of a motion to strike off the complaint and for a more specific pleading, that the Commonwealth has no cause of action upon which relief may be granted because the contract includes a liqui
We first must consider the question of whether or not this preliminary objeсtion in the nature of a motion to strike off the complaint because of an alleged improper and impertinent claim of damages is appropriate. Our Supreme Court in Hudock v. Donegal Mutual Insurance Company,
In our opinion an allegation of damages or a prayer for damages which are not legally recoverable in the cause of action рleaded is impertinent matter in the sense that it is irrelevant to that cause of action. Thus, a preliminary objection in the nature of a motion to strike off impertinent matter, such as was done in the case at bar, would appeаr to be the approriate means through which to challenge an erroneous prayer for damages. (Emphasis added.)
Hudock v. Donegal Mutual Insurance Company, supra. In this case, the preliminary objection is in the nature of a motion to strikе off the complaint. We do not believe, however, that the possible pleading of improper damages justifies striking the entire complaint. See Spadel v. Zarlinski, 39 D. & C. 2d 452 (1966), noted in Hudock v. Donegal Mutual Insurance Company, supra,
Hartford’s other preliminary objections, in the nature of a motion for a more specific pleading and a
We also believe that the motion for a more specific pleading is without merit because the сomplaint does appear to us as sufficiently specific to advise the defendant as to what action is deemed improper and to permit the defendant to prepare a defense. Maddux v. Department of Agriculture, Bureau of Animal Industry,
The other preliminary objections before Us are in the nature of a demurrer by the additional defendant Chem-Seps to Hartford’s third-party complaint. Chem-Seps argues that Hartford has set forth no cause of action because it seeks total indemnification
Order,
And Now, this 24th day of January, 1979, the preliminary objections filed by The Hartford Accident and Indemnity Company and the Chemical Separations Corporation in the above-captioned matter are hereby dismissed and they are directed to file an answer within twenty (20) days.
Notes
This clause provides in pertinent part as follows :
(G-13, 5-12) The guarantee shall specifically stipulate that the Department shall be entitled to withhold up to ten percent (10%) of the total of Contract No. 13 until, in the opinion of the Engineers, the conditions outlined under paragraph G-13, 5-11, subparagraph (a) have been met. The Contractor further shall guarantee that he shall make all modifications necessary and perform all work required to modify or change the process in order to provide for the required results. If at the end of the year’s operational period it is determined by the Engineers that the conditions of this guarantee cannot be met, then the Contractor hereby agrees to forfeit the payment of monies retained or withheld.
“Liquidated damages” is the sum which a party to a contract agrees to pay if he breaks some promise and which, having been arrived at by good faith effort to estimate in advance actual damage that will probably ensue from breach, is recoverable as agreed damages if breach occurs, whereas a “рenalty” is not a pre-estimate of probable damages but is in the form of a punishment designed to prevent breach. In Re Plywood Company of Pennsylvania,
Paragraph 9(b) of part K of tbe contract provides in pertinent part:
Tbe Commonwealth shall not be precluded or estopped ■from demanding and recovering from the Contractor and/or his Surety such damages as may be sustained by reason of the Contractor’s failure to comply with the provisions of the Contract or on account of any over-payments made to the Contractor.
For example, in order to determine whether or not a stipulated sum nаmed in an agreement as a forfeiture for noncompliance is intended as a penalty or as liquidated damages, it is necessary to look at the language of the contract, its subject-mаtter, the intention of the parties as1 gathered from all its provisions, the ease or difficulty in measuring the breach in damages, and from the whole to gather the view which equity and good conscience require should be taken of the case. Bruno v. Pepperidge Farm, Inc.,
