23 Pa. Commw. 387 | Pa. Commw. Ct. | 1976
Opinion by
This case is before us on the preliminary objections of Bethlehem Steel Corporation (Bethlehem) to the petition of the Department of Environmental Resources (DER) seeking enforcement of Air Pollution Abatement Order No. 72-533 (order) which resulted from a consensual agreement executed on February 25, 1972 by Bethlehem and DER. The order provides, among other things, that Bethlehem submit an application for a permit to construct equipment -to control emissions of air contaminants resulting from the pushing operation at Coke Oven Battery No. 5 at its Bethlehem, Pennsylvania, plant by March 1, 1975 and that Franklin Coke Oven Battery No. 17 at Bethlehem’s Johnstown, Pennsylvania, plant cease operation by May 31, 1975. Paragraph 9
Bethlehem raises a question of the jurisdiction of this Court, issues of primary jurisdiction, exhaustion of administrative remedies, and ripeness for review and also
■Bethlehem fails to recognize in its arguments that the action to enforce the order to which it agreed and the application for modification before the EHB, though based to some extent on the same factual material, are proeedurally distinct.
'Section 10(a) of the Air Pollution Control Act
We next address Bethlehem’s contention that DER must elect to pursue its action either in the courts or through the administrative process. Bethlehem asserts that our decision in Department of Environmental Resources v. Leechburg Mining Co., 9 Pa. Commonwealth Ct. 297, 305 A. 2d 764 (1973), requiring DER to proceed
■Properly interpreted, Leechburg, in fact, supports the position of DER. In Leechburg, preliminary objections were sustained by applying the doctrine of election of remedies on all counts except one brought by DER to enforce a consent adjudication. We hold that by consenting to be bound by the order of February 25, 1972, Bethlehem agreed that it would take the required actions by the deadlines imposed unless the order were modified prior to that time. Bethlehem had, and still has, a right to appeal an adverse ruling on its petition for modification, first to the EHB and subsequently to this Court. During appeals from such ruling, however, the unmodified agreement remains in force. Since the deadlines for compliance have passed and Bethlehem has not taken the action which it agreed to take, the inception of an action for enforcement is timely and proper.
Now, this 18th day of February, 1976, the preliminary objections of the Bethlehem Steel Corporation in the above captioned matter are overruled, and Bethlehem Steel Corporation is allowed 29 days from this date within which to file an answer to the petition of the Department of Environmental Resources.
. Paragraph 9 of the order reads:
“9. Upon application of Bethlehem Steel Corporation the provisions of this order, and plans and schedules submitted and approved hereunder, may be modified by the Department, when
A. delivery or installation of equipment is delayed by events not in the control of Bethlehem Steel Cbrporation;
B. revision of the plans and schedules submitted or approved is necessary to incorporate changes in technology or corporate planning to achieve within the time specified in paragraph 5 hereof, significant improvement in air pollution control; or
C. air pollution control standards applicable to the byproduct, slot-type coke ovens are changed.
“Any order, decision or other action taken by the Department upon such application may be appealed to the Environmental Hearing Board and the courts of the Commonwealth as provided by law.”
. Act of January 8, 1960, P.L. (1959) 2119, as amended, 35 P.S. §4010 (a).
. See Commonwealth v. United States Steel Corp., 15 Pa. Commonwealth Ct. 184, 325 A.2d 324 (1974) ; Commonwealth v. Rozman, 10 Pa. Commonwealth Ct. 133, 309 A.2d 197 (1973).
. We recognize that the terms of the order, which allow Bethlehem to apply to DER for modification of the order with a right to appeal any action taken on such an application to the Environmental Hearing Board (EHB), create an unusual situation. A potential conflict could arise if the court directs enforcement in accord with the original terms of the order but prior to compliance by Bethlehem the EHB modifies those terms. If such a conflict would arise, we would consider the modification to be a proper defense to a contempt proceeding brought for non-compliance with the order entered relative to the petition for enforcement.