129 A. 635 | Pa. | 1925
Argued May 4, 1925. This was a petition for a writ of mandamus to compel the county controller to countersign a warrant for payment of work done on a county highway; a responsive answer was filed and at the trial the court directed a formal verdict for plaintiff, reserving certain questions of law on which judgment was entered for the defendant n. o. v., and the former has appealed.
The record discloses no error. In July, 1920, Cambria County duly awarded to the Met-Con Co., Inc., plaintiff, a contract for the erection of twenty thousand feet of guard rail along the public county highway known as Haws Pike, the consideration therefor being $23,090. The guard rail consisted of galvanized steel cable supported by reinforced concrete posts. The contract also contained a provision relating to retaining walls and stipulated that in case the contractor was compelled to excavate for footing it was to be done at three dollars per cubic yard. The work was placed under the supervision of the county engineer, and, some seven months after the contract was let, he concluded that certain dangerous curves along the lines of this highway should be eliminated by excavation, and prepared plans accordingly. This met with the approval of a majority of the county commissioners, who, in March, 1921, authorized the engineer to direct plaintiff "to do the excavating *585
called for on the plans and specifications prepared by the said county engineer for the elimination of dangerous curves and points on the Haws Pike in the township of Lower Yoder at the unit price of three ($3) dollars per cubic yard, as set forth in the proposal and contract between the said county of Cambria and the said Met-Con Company, Inc., which said contract is dated the 26th day of July, 1920." The engineer estimated the cost of this excavation at $17,394, but the amount here in controversy, for which defendant refused to countersign the warrant, is $14,191.86. That appellant did the excavating to which we have just referred is admitted and no question is raised as to the price, but the defendant as controller, challenged the liability of the county therefor, by reason of the statute which requires county work to be advertised and let to the lowest and best bidder. Section 10 of the Act of June 27, 1895, P. L. 403, 406, here applicable, provides that: "From and after the passage of this act all contracts made by the commissioners of said county involving an expenditure exceeding one hundred dollars shall be in writing, and shall, immediately after their execution, be filed with the controller; but no contract shall be made, nor the payment thereof certified by the controller, for over one hundred dollars, unless when made with the lowest and best bidder, after due notice to be published by the controller, when directed by the commissioners, if he approve the purpose of the proposals invited; all bids to be received by the controller, under seal, and to be in his presence opened by the commissioners, and the contracts awarded, of which awards the controller shall keep a record, and he shall certify no warrants for contracts not made agreeably thereto." Yet here the county commissioners, without advertising and without competitive bids, gave this work, amounting to more than $14,000, to plaintiff in entire disregard of the statute. The excavation for the elimination of curves, while a proper improvement, was entirely outside the original contract, for neither *586
therein, nor in the accompanying plans and specifications was there any reference to such excavation. The bidders at that time, of which plaintiff was the lowest, could have had no knowledge of it. This is manifest, for the plans covering the work here in question were not prepared until seven months after that contract was let. The only reference to excavation in the original contract is for "footing," an entirely different matter. No reason appears why the excavation in the elimination of curves should not have been advertised and let as a separate contract. It would be remarkable if this excavation work, costing approximately two-thirds as much as the original contract, could be treated as merely incidental to it. If so, then, to a contract of one hundred dollars for guard rails, the commissioners might, without securing bids, obligate the county for thousands of dollars for excavating or other like work, providing it was done by the party having the guard rail contract. True, municipal authorities may, without advertising for bids, provide for work incidental to that covered by the original contract (Clark Sons Co. v. Pittsburgh,
Furthermore, he who deals with a municipality must recognize that it can contract only upon such terms as the legislature has seen fit to prescribe. As stated by MR. JUSTICE FRAZER, in Harris v. City of Philadelphia et al.,
The judgment is affirmed at the cost of appellant. *588