Commonwealth Edison Co. v. United States Nuclear Regulatory CommissionCommonwealth Edison Co. v. United States Nuclear Regulatory Commission
In this case Commonwealth Edison (“Edison”) challenges as illegally retroactive a final order of the Nuclear Regulatory Commission (“NRC”) requiring Edison to pay fees at the price ceilings established in a 1984 regulation for the NRC’s license application review work regarding four nuclear reactors. Edison also challenges the interest and penalty charges applied to the review fee. The NRC argues that we have no jurisdiction because Edison failed to petition for review of the 1984 Rule within the statutory time limit. The NRC also argues that even if we have jurisdiction, the fees are not illegally retroactive. We have jurisdiction over this case, and hold that both the fees and the penalty and interest charges were proper.
I
In 1978 the NRC promulgated a final rule amending a regulation requiring,
inter alia,
applicants for operating licenses for nuclear facilities to pay a fee for the work involved in the NRC’s review of the license application. 43 Fed.Reg. 7210 (Feb. 21, 1978) (“1978 Rule"). The 1978 Rule was issued under the authority of the Independent Offices Appropriations Act (“IOAA”), which is presently codified at
The 1978 Rule set ceiling figures or caps, above which any party charged a fee under the 1978 Rule would not be assessed.
In 1982 the NRC issued a notice of proposed rulemaking (“1982 Proposed Rule”) to amend the 1978 Rule. 47 Fed.Reg. 52,-454 (Nov. 22, 1982). In its proposed rule, the NRC suggested removing all ceilings relevant to the applications at bar. Id. at 52,454, 52,456.
Several utilities, including Edison, commented on the proposed rule. Some of these comments specifically raised the challenge to the 1984 Rule that Edison raises in this petition. The final rule (“1984 Rule”) was promulgated on May 21, 1984.
In early 1985, the NRC issued bills to Edison under the 1984 Rule for license application review work for four nuclear reactors, two at Edison’s Braidwood facility and two at Edison’s Byron facility. These bills stated that they covered “the cost of the Operating License Review through June 23, 1984.” They were assessed using the 1978 hourly rates for professional services. All of the invoices exceeded the 1978 ceilings but were within the 1984 ceilings.
Edison contested the fees as illegally retroactive and eventually paid a lower amount. The NRC issued several notices demanding payment, culminating in a final order issued on September 13, 1985, that charged Edison for the unpaid remainder. The notice also charged interest and a penalty pursuant to
II
As the issue of initial forum jurisdiction over these fee decisions of the NRC has not been previously addressed explicitly, we treat the matter briefly in order to satisfy our duty to determine our own jurisdiction. The federal appeals courts have exclusive jurisdiction under a provision of the Administrative Orders Review Act (more commonly referred to as the Hobbs Act) over “all final orders of the Atomic Energy Commission [now the Nuclear Regulatory Commission] made reviewable by section 2239 of title 42.”
The general rule reiterated by the
Lorion
Court is that “[i]n the absence of specific evidence of contrary congressional intent, ... review of orders resolving issues preliminary or ancillary to the core issue in a proceeding should be reviewed in the same forum as the final order resolving the core issue.”
Lorion,
In
Lorion
the Court determined that the Hobbs Act granted the federal appellate courts exclusive initial review jurisdiction over a challenge to the NRC’s denial of a request to institute a proceeding to suspend a nuclear plant’s operating license.
Id.
at 1605, 1608;
see
In this case the core issue is whether to grant operating licenses in a
Of course, if Congress had expressed some other intent we would be bound to follow it.
Lorion,
Finally, we note that other courts of appeals have exercised initial review jurisdiction over challenges to the NRC’s license fee regulations.
New England Power Co. v. NRC,
Ill
The NRC argues that petitioner’s challenge to its bill for licensing application review has come too late because the Hobbs Act requires that a party aggrieved by a final order file a petition for its review within sixty days of the order’s entry,
The Hobbs Act provision at issue reads simply that “[A]ny party aggrieved by the final order may, within 60 days of its entry, file a petition to review the order in a court of appeals where venue lies.”
The Hobbs Act’s sixty-day restriction must mean at least that direct preenforcement challenges to rules brought after the expiration of the time limit are generally beyond the court’s jurisdiction. However, the cases interpreting the section establish that indirect challenges to the rule brought when the rule is applied to a particular individual are within the court’s jurisdiction.
Texas v. United States,
Some statutory review schemes explicitly provide for review of the underlying legislative rule in an enforcement proceeding.
E.g.,
The most venerable statement in this regard is that of the District of Columbia Circuit in the leading case of
Functional Music, Inc. v. FCC,
The rules here attacked were initially promulgated in 1955. It very well may be that they were then sufficiently final to support judicial review. [Footnote omitted.] No such review had been sought, however. And as to those rules, the statutory period specified for review of, or appeal from, Commission orders and decisions has long since passed.Nevertheless, we are persuaded that judicial examination is now permissible. As applied to rules and regulations, the statutory time limit restricting judicial review of Commission action is applicable only to cut off review directly from the order promulgating a rule. It does not foreclose subsequent examination of a rule where properly brought before this court for review of further Commission action applying it. For unlike ordinary adjudicative orders, administrative rules and regulations are capable of continuing application; limiting the right of review of the underlying rule would effectively deny many parties ultimately affected by a rule an opportunity to question its validity. And see Columbia Broadcasting System v. United States, 1941, 316 U.S. 407 , 421,62 S.Ct. 1194 [1202],86 L.Ed. 1563 , for example, where the Supreme Court clearly contemplated the continuing availability of review of Communications Commission rules and regulations.
Id.
at 546-47. While
Functional Music
was decided in the context of whether review existed over a denial to reconsider a legislative rule, its language created a clear exception for actions in which the agency applies a general rule to a particular party, such as the action at bar.
Functional Music
simply recognized that the growing understanding that regulations and rules were reviewable “orders” under the Hobbs Act,
see
4 Davis,
Administrative Law
§ 23.5 (2d ed. 1982);
cf. United Gas Pipe Une Co. v. FPC,
In addition, the courts have more readily found jurisdiction to review the substantive authority of legislative rules than they have challenges to the procedure by which the rule was established.
E.g., Texas v. United States,
Two cases of this court argued in the briefs do not suggest otherwise. The first,
Atchison, Topeka, and Santa Fe Railway Co. v. ICC,
Finally, this not a case in which the specific structure and purpose of a particular act require that judicial review be cut off.
E.g., Morris v. Gressette,
IV
The final order on review covers costs incurred by the NRC in reviewing the license applications for Edison’s four reactors up to June 23, 1984. The costs were incurred during the period that the 1978 Rule was in effect. The fees were assessed when the 1984 Rule was in effect and the final order applied the ceilings of the 1984 Rule. The hourly rates applied in calculating the fee were, however, the hourly rates appropriate under the 1978 Rule.
3
Edison asserts on the merits that the final order is retroactive. Edison also claims that it received insufficient notice under the IOAA of the 1984 Rule’s reach to cover pending applications.
See New England Power Co. v. NRC,
With regard to the applicable ceilings, the 1978 Rule established only that license application review fees that were assessed and charged under the 1978 Rule would be subject to the limitation of the maximum fee ceiling contained in that rule.
See
We do not think there is any great difficulty in reading the date on which the agency established that fees became due and payable to also establish the date on which the right to the ceilings established by the 1978 legislative rule become fixed. But we do not need to rely alone on these provisions to establish the date on which the right to the 1978 ceilings would vest. The NRC had in the past applied raises in fees to pending applications,
see
43 Fed. Reg. 7210, 7215 (1978) (comments to 1978 Rule noting that “in the case of ... operating licenses, where the permit review is completed on or after the effective date of this amendment to part 170 [the license fee schedule], the revised schedule will apply”), and the Statement of Considerations accompanying the 1982 Proposed Rule (which became, with amendments, the 1984 Final Rule), clearly notified the industry that the 1984 fee ceilings would apply to applications pending at the time the 1984 Rule became effective. It proposed in pertinent part that under the 1984 Rule all actual costs would be charged for review work
It is true, of course, that the 1978 Rule of the NRC provided little assurance to the regulated parties that their license application review costs would in fact be limited by the 1978 ceiling. License application reviews for nuclear plants are detailed and lengthy undertakings that may well take several years. There was no guarantee that the review process for any facility would be completed during the life of the 1978 Rule, and Edison took upon itself the risk that a new rule would be in place when its fees became due and payable.
It is important to remember that the NRC was under no obligation to limit in any way its recoupment of all the costs associated with the review of the license application. Its authority to recoup those costs derives from the IOAA, which empowers agencies to recover
all
of their costs that provide special benefits to the regulated parties.
The case law has made clear for some time that as a general rule of administrative law the filing of an application does not itself create a vested right in the applicant to the particular terms under which the license will be issued.
Nevada Power
It is true that Edison could not, in a practical sense at least, avoid the payment of review costs in the same way that applicants dismayed at the alteration of terms placed on a license could avoid those terms by withdrawing their applications. Edison would have had to pay the costs of review to date even had it withdrawn its applications, and it would be unrealistic to propose that a company in Edison’s position can freely choose to walk away from the construction or operation of a nuclear plant when it is informed of a potential review rate increase and fails to persuade the agency to desist. The massive past commitment of resources virtually prohibits such a course. Nevertheless, the simple fact of the matter is that Edison made a conscious decision to accept the NRC’s monopoly on regulation of the industry when it first chose to construct nuclear plants. It did so with full knowledge that the industry would be heavily regulated. That Edison hoped at an earlier time that the history of NRG regulation would take a different course is no argument that it must now have its way. Edison knew or should have known at the time of the 1978 Rule that the 1978 ceilings would only apply to those applications on which review was completed during the effective period of the 1978 Rule. The applications on review here were not so completed. Edison also had full notice of the change in the ceilings contemplated in the 1984 Rule and took full advantage of its right to participate in the rulemaking process. The use of the 1984 ceilings in calculating Edison’s fees was not retroactive and Edison was afforded adequate notice by regulation that the ceilings would apply.
V
Edison argues that even if it must pay the full principal of the fee issued to it, it still may not be held liable for interest or penalties under
A.
“Executive or Legislative" Agencies Under
“agency” means any department, office, commission, board, service, Government corporation, instrumentality or other establishment or body in either the executive or legislative branch of the federal government.
In early 1983 the relevant portion of Title 31 was recodified in an effort to increase its clarity without affecting its substance. Revision of Title 31, U.S.C., Pub.L. No. 97-452, 96 Stat. 2467 (1983);
see also
Detailed Explanation Prepared by the Office of Law Revision Counsel, 1982 U.S.Code Cong. & Admin.News 4301. The statute codified the interest and penalty provision as
At no place in
Edison claims that application of the plain meaning rule of construction excludes the NRC from the authority provided by
The NRC was explicitly established by Congress as an “independent” agency,
Moreover, the purpose of Congress in passing the 1982 Act and the predecessor 1966 Act firmly supports our conclusion that the NRC is an executive or legislative agency for the purpose of
Finally, the act explicitly authorized the Attorney General to interpret its provisions,
Therefore, we hold that under the circumstances of this case the NRC is an “executive or legislative agency” for the purposes of
B. Penalty and Interest Provisions
Edison argues that the NRC is precluded by its own regulations,
see
Edison’s only argument against the application of
An agency, of course, cannot by regulation free itself from a duty imposed by statute,
see National Muffler Dealers Association, Inc. v. United States,
VI
In accordance with the foregoing opinion, Edison’s petition for review is DENIED.
Notes
. The 1984 Rule changed the time at which bills were due and payable from "upon notification by the Commission when the review of the project is completed,”
. We note here that by "enforcement" review in this case we do not necessarily mean an action brought by an agency in court to enforce an order against a private party. In a case like this, it is the agency's application of a rule to a private party in administrative proceedings that is the enforcement action in question. Thus this petition for review represents judicial review of an agency’s enforcement proceeding even if the private party files the petition for review as a result of the agency enforcement.
. While there is some uncertainty in the record regarding whether license fees are due upon completion of the review work or upon the NRC’s notification to an applicant of a decision whether to license a nuclear reactor, we need not, and do not, resolve that issue today because neither point had been reached for any of the four reactors here at the time the 1984 Rule became effective.
. In its briefs and at oral argument Edison employed as a refrain references to a footnote in the 1978 Rule. The footnote provided that ”[w]hen review of the permit, license, approval, or amendment
is complete,
the expenditures for professional manpower [sic] and appropriate support services will be determined and the appropriate fee will be assessed, but in no event, will the fee exceed that shown in the schedule of facility fees." 43 Fed.Reg. 7210, 7220 (Feb. 21, 1978) (formerly codified at
. Edison also relies on the definition at the head of Title 31: "In this title, ‘agency1 means a department, agency, or instrumentality of the United States Government."
The act recodifying Title 31 specifically provided that it worked no substantive change on the preexisting law, and
The definition section of Chapter 37 is of no more help for it merely makes clear that
. Edison relies heavily on
Humphrey’s Executor v. United States,
. While some of the provisions of the NRC’s own debt-collection regulations appear potentially to conflict with the statute or the Federal Claims Collection Standards, we do not address any such issue because Edison did not raise it, and therefore waived it.
American Can v. Mansukhani,
Edison has also waived its argument that the NRC may not allow interest or penalties to accrue during the period from the filing of its petition for judicial review until the issuance of a final decree granting or denying review. Edison waited until its reply brief to raise this argument. That is too late. Such belated attempts to introduce new issues violate the need of the judicial system for order and efficiency, and they make veiy difficult, if not impossible, any effective plenary consideration by the court. Such attempts also seek to expand the issues on appeal without effective notice to the opposing party and come at a time when the opposing party has no opportunity to make a written response. We have regularly refused to consider arguments raised for the first time in a reply brief. This case is no exception.
See, e.g., Rudell v. Comprehensive Accounting Corp.,
. Edison has suggested in its brief that the NRC may have improperly calculated the starting date for the assessment of the late payment penalty. Edison argues that this reveals that the • NRC was itself unsure whether to apply
While Edison has noted that the time for instituting the late payment penalty may have been calculated incorrectly, it has done so exclusively in its attempt to show that the application of