Commerce Bank/Harrisburg, N.A. v. KesslerCommerce Bank/Harrisburg, N.A. v. Kessler
Lead Opinion
Appellant, Metro Bank, f.k.a. Commerce Bank of Harrisburg, N.A. (“Metro Bank”), appeals from the order determining that, pursuant to the Mechanics’ Lien Law,
The record reflects relevant factual and procedural background of this matter as follows:
On October 10, 2006, the Kesslers contracted with Ricker to build a luxury home in Harrisburg, Pennsylvania. On October 18, 2006, Ricker started excavation on the Kesslers’ lot. On January 12, 2007, the Kesslers contracted with Commerce Bank of Harrisburg, N.A. (“Commerce Bank”), now Metro Bank, for a construction loan of up to $435,000 with an open-ended mortgage, which was recorded on January 24, 2007. The home was substantially complete as of August 1, 2007.
Because the Kesslers were unable to make their mortgage payments, Metro Bank filed a mortgage foreclosure action on May 22, 2008, against the Kesslers. On July 24, 2008, Metro Bank obtained a default judgment against the Kesslers for $403,994.84. The Kesslers also failed to make their payments to Ricker. Consequently, on February 24, 2009, Ricker obtained a default judgment against the Kes-sler’s in the amount of $411,304.14. On February 26, 2009, the Kesslers filed for bankruptcy. On November 24, 2009, Metro Bank obtained relief from the automatic stay provision of the Bankruptcy Code
On July 13, 2010, Metro Bank and Rick-er filed a “Joint Emergency Motion To Stay Sheriffs Sale And Adjudicate Lien Priority Dispute.” The trial court ordered that the sheriffs sale be stayed pending briefing and argument. On February 25, 2011, the trial court entered an order holding that the judgment entered in favor of Ricker enjoys priority over the judgment entered in favor of Metro Bank. On March 7, 2011, Metro Bank filed a motion for post-trial relief, and on March 10, 2011, Metro Bank filed a notice of appeal to this Court attempting to initiate an appeal of the trial court’s February 25, 2011 order. The trial court did not issue an order disposing of Metro Bank’s motion for post-trial relief. Therefore, the motion was denied by operation of law. See
On March 23, 2011, the trial court issued an order requiring Metro Bank to file a concise statement of matters complained of on appeal pursuant to
Metro Bank presents three issues for appeal:
Under the Mechanics’ Lien Law,49 P.S. § 1508(c)(2) , as amended June 29, 2006, effective January 1, 2007, does an open-end mortgage dated January 12, 2007 have priority over a statutory mechanics’ lien based on construction begun on October 18, 2006?
Did the trial court err as a matter of law in assigning priority to a statutory mechanics’ lien, where the construction contract did not provide for a mechanics’ lien to be perfected at the time the contract was executed?
Did the trial court err as a matter of law in assigning priority to a statutory mechanics’ lien, where the lien claim failed to contain the statutorily mandated statement of the kind and nature of the labor and materials furnished?
Metro Bank’s Brief at 2.
Prior to considering the merits of Metro Bank’s appeal, we address whether the trial court’s February 25, 2011 order is interlocutory. Our Court may reach the merits of an appeal taken from “(1) a final order or an order certified as a final order (
Under Pennsylvania law, the priority of liens recorded against foreclosed property is usually established by filing exceptions to the sheriffs schedule of distribution after a sheriffs sale has occurred. See
Given that there has yet to be a sheriffs sale of the subject property in this action, at first glance the trial court’s February 25, 2011 order appears to be interlocutory. Metro Bank, however, argues that, “although the procedural posture of the case was somewhat unusual, the proceeding below was in the nature of a declaratory judgment on the lien priority issue, and the decision was therefore final and appealable.” Metro Bank’s Application for Reargument or Reconsideration at p. 2. We agree.
Specifically,
Courts of record, within their respective jurisdictions, shall have power to declare rights, status, and other legal relations whether or not further relief is or could be claimed. No action or proceeding shall be open to objection on the ground that a declaratory judgment or decree is prayed for. The declaration may be either affirmative or negative in form and effect, and such declarations shall have the force and effect of a final judgment or decree.
In this matter, a sheriffs sale was originally scheduled, however, given a recent change in the Mechanics’ Lien Law, a dispute arose regarding lien priority. Considering the uncertainty of the law, and the parties’ need to intelligently bid at the sheriffs sale, the parties agreed to stay the matter and obtain a decision on the lien priority statute. In so doing, the parties initiated a proceeding in the nature of a declaratory judgment action.
Our review of a trial court’s disposition of a declaratory judgment is governed by the following standard of review:
Our standard of review in a declaratory judgment action is limited to determining whether the trial court clearly abused its discretion or committed an error of law. We may not substitute our judgment for that of the trial court if the court’s determination is supported by the evidence.
State Automobile Mut. Ins. Co. v. Christie,
[w]e will review the decision of the lower court as we would a decree in equity and set aside the factual conclusions of that court only where they are not supported by adequate evidence. The application of the law, however, is always subject to our review.
O’Brien v. Nationwide Mut. Ins. Co.,
Specifically, Metro Bank’s first two issues on appeal challenge application of the amendments to the Mechanics’ Lien Law, effective January 1, 2007, to the liens at issue in this matter. In particular,
[t]he lien of a claim filed under this act shall take effect and have priority in the case of the erection of construction of an improvement as of the date of the visible commencement upon the ground of the work of erecting or constructing the improvement.
49 Pa.S.A.
Thereafter, on January 1, 2007, the amendments to the Mechanics’ Lien Law took effect. At that time,
The lien of a claim filed under this act shall take effect and have priority as follows:
(a) Except as set forth in subsection (c), in the case of the erection or construction of an improvement, as of the date of the visible commencement upon the ground of the work of erecting or constructing the improvement.
(b) Except as set forth in subsection (c), in the case of the alteration or repair of an improvement, as of the date of the filing of the claim.
(c) Any lien obtained under this act by a contractor or subcontractor shall be subordinate to the following:
(1) A purchase money mortgage as defined in42 Pa.C.S. § 8141(1) (relating to time from which liens have priority).
(2) An open-end mortgage as defined in42 Pa.C.S. § 8143(f) (relating to open-end mortgages), the proceeds of which are used to pay all or part of the cost of completing erection, construction, alteration or repair of the mortgaged premises secured by the open-end mortgage.
49 Pa.S.A.
In this matter, on October 10, 2006, the Kesslers contracted with Ricker. On October 18, 2006, Ricker started excavation on the Kessler’s lot, and as of October 26, 2006, the footers were in place. In other words, visible commencement of work upon the ground occurred in October 2006 — before the amendments to
Thereafter, on January 12, 2007, three months after construction began, and, significantly, after the effective date of the amendment set forth above, the Kesslers contracted with Commerce Bank (now Metro Bank) for a construction loan of up to $435,000, with an open-end mortgage. That open-end mortgage was recorded on January 24, 2007.
Ricker argues that his lien takes priority because the old Mechanics’ Lien Law was in effect at the time that he contracted with the Kesslers. Ricker’s Brief at 11-16. Applying contractual principles of law, Ricker argues that the laws that are in force at the time that the parties execute a contract merge into that contract. Id. at 11. To apply the amended version of the Mechanic’s Lien Law, Ricker argues, would allow the amended law to retroactively change the force and effect of his contract with the Kesslers. Id. at 12.
Furthermore, Ricker argues that to read the 2007 amendment as applying to his lien would violate fundamental principles of statutory construction, in particular
The trial court agreed with Ricker’s application of contractual principles. Trial Court Opinion, 5/13/2011, at 3.
Metro Bank argues on appeal that the trial court’s judgment, applying the prior version of
Rather, Metro Bank argues that the rights created by the Mechanics’ Lien Law are statutory remedies that “may be bestowed, altered, or repealed at the will of the legislature, even when they predate the legislature’s action.” Id. Given that, under Metro Bank’s analysis, any amendment to the Mechanics’ Lien Law simply alters a statutory remedy (and not a contractual right), therefore Metro Bank argues that the principles of statutory construction relied upon by Ricker and the trial court are inapplicable. Id. Likewise, because Metro Bank believes that there is a fundamental difference between contractual rights and statutory remedies, it asserts that Ricker’s and the trial court’s reliance upon precedent interpreting contractual rights, such as First National Bank of Pa., is also misplaced. Id. at 12-13.
Furthermore, even if contractual principles did apply to this matter, Metro Bank points out that if the Legislature had intended to preclude application of the amendments to
Finally, Metro Bank argues that the trial court’s reliance upon the “self-created” predicament can cut both ways. While Metro Bank could have insisted on proof that work on the property had not yet commenced, the amendments to the Mechanics’ Lien Law were passed on June 29, 2006, before Ricker entered into a contract with the Kesslers or began work on the property. While Metro Bank acknowledges that Ricker commenced work prior to the effective date of the amendment, Ricker, like Metro Bank, was on notice of the impending change. As a result, Metro Bank argues that it “was in no better position than Ricker to avoid the priority dispute.” Id. at 13.
Notwithstanding the well-developed arguments of both sides, our resolution of the retroactivity issue turns on the plain language of
Indeed, we agree with Metro Bank that the Legislature’s mention of certain sections of the Mechanics’ Lien Law within the statutory notes, clarifying that those sections apply prospectively, while not mentioning
Consequently, we hold that the trial court committed an error of law to the extent that it concluded that the previous version of
However, our analysis does not end there. To the contrary, Ricker argues that, even if the amended version of
Specifically, the amended version of
(2) An open-end mortgage as defined in42 Pa.C.S. § 8148(f) (relating to open-end mortgages), the proceeds of which are used to pay all or part of the cost of completing erection, construction, alteration or repair of the mortgaged premises secured by the open-end mortgage.
49 Pa.S.A.
Ricker argues that use of any portion of the proceeds to pay expenses other than those set forth in
Metro Bank disputes Ricker’s interpretation of
Metro Bank’s arguments, however, disregard the clear language of
Furthermore, we hold that Metro Bank’s argument in favor of application of other definitions set forth in
Consequently, Metro Bank’s arguments against limiting application of the exception set forth at
Metro Bank’s second issue on appeal attacks the validity of Ricker’s mechanics’ lien, arguing that the lien is invalid because the lien claim allegedly failed to contain the statutorily mandated statement of the kind and nature of the materials furnished. Metro Bank’s Moving Brief at 15-17. Therefore, Metro Bank argues that Ricker’s lien claim is defective as a matter of law, and should be invalidated. Id. at 17.
Pursuant to
Metro Bank argues that, given the absence of the referred to drawings and specifications, the statement of the kind and character of the labor and materials furnished was too vague, therefore invalidating the lien. Ricker, however, argues that substantial compliance is all that is necessary to satisfy
We agree with Ricker’s substantial compliance argument. Indeed, multiple Pennsylvania cases interpreting the “contents of the claim” section of the Mechanics’ Lien Law have long held that “[i]n considering a mechanics’ lien claim it must be kept in mind that substantial compliance with the Act is sufficient. This is shown to exist wherever enough appears in the statement to point the way to successful inquiry.” Marchak v. McClure,
Considering that the Kesslers hired Ricker to construct a new home, and considering that the lien claim referenced and attached the contract for that work, we hold that the lien claim provided the Kes-slers and Metro Bank with ample information to “point the way to successful inquiry.” The absence of the referred to drawings and specifications does not defeat Ricker’s lien. Consequently, Metro Bank’s argument attacking the validity of Ricker’s lien on that basis is without merit.
Therefore, in summary, we hold that the amended version of
Order affirmed.
Judge STRASSBURGER files a Dissenting Opinion.
Notes
.
. See also
. Under Pennsylvania law, we rely upon the substance of a pleading to determine the form of action. Stackhouse v. Commonwealth,
. Though uncommon, Pennsylvania precedent establishes the use of declaratory judgment proceedings for lien priority determinations. See Grambo et al. v. South Side Bank & Trust Co.,
.
. The pages within the trial court opinion are not numbered. We have added page numbers for ease of reference.
. Sections 201(14), 401, and 402 respectively relate to the definition of “residential property,” waiver of liens by a claimant, and waiver by a subcontractor; effect on a subcontractor.
. Indeed, for purposes of the underlying proceedings, the parties stipulated that portions of the proceeds of the open-end mortgage paid for costs such as tax claims, closing costs, satisfaction of an existing mortgage on the property, and payment of other judgments and liens. Of the $255,239.58 of loan proceeds that were disbursed at the loan closing, it appears that more than $95,000 was used to pay for things other than "completing erection, construction, alteration or repair of the mortgaged premises.”
. Based upon the record before us, it is unclear whether Metro Bank expressly preserved its opposition to Ricker’s argument that use of the mortgage proceeds for purposes other than those enumerated in
. In Denlinger, Inc. we quoted our own precedent explaining that:
[A]ll the cases agree that a substantial compliance is sufficient, and this is shown to exist wherever enough appears, on the face of the statement, to point the way to successful inquiry. Adherence to the terms of the statute is indispensable, but the rule must not be pushed into such niceties as to serve but to perplex and embarrass a remedy intended to be simple and summary, without, in fact, .adding anything to the security of the parties having an interest in the building sought to be encumbered. Certainty to a common intent has, therefore, always been held to suffice.
Denlinger, Inc.,
. While we make no judgment as to whether the statement in this matter would have been sufficient to comply with
Dissenting Opinion
DISSENTING OPINION BY
I respectfully disagree that a motion to determine lien priority should be considered in the nature of a declaratory judgment action and thus immediately appeal-able; accordingly, I dissent and offer the following analysis.
This case was initiated as a mortgage foreclosure action and both parties agreed to stop the sheriffs sale prior to its occurrence and ask the trial court to determine lien priority. The trial court held that Ricker’s mechanics’ lien had priority over Metro Bank’s mortgage. Bank has appealed.
The Majority holds that the joint request for a determination of lien priority is “in the nature of a declaratory judgment action, and since declaratory judgments are final orders, the court’s determination of lien priority is a final, appealable order.
You can call a cat a dog, but it is still a cat. This is not a declaratory judgment action; it is a mortgage foreclosure action.
Our Pennsylvania Rules of Civil Procedure govern the process when lien priority is disputed. Specifically, lien priority is established by filing exceptions to the sheriffs schedule of distribution after a sheriffs sale has occurred.
The method and procedure by which competing lien creditors may litigate their claims to sale proceeds is established by [Pa.R.C.P.] 3136. Rule 3136(g) implicitly recognizes the right of appeal by any person aggrieved by the court’s final disposition of exceptions to the sheriffs schedule of distribution. It authorizes the entry of an order that the sheriff invest the proceeds of sale pending final disposition of the exceptions or an appeal therefrom. It is clear that an appeal will lie from a final order sustaining or dismissing exceptions to a sheriffs schedule of distribution.
Metro. Fed. Sav. & Loan Ass’n of E. Pennsylvania v. Bailey,
There are myriads of subsidiary orders upon which parties desire rulings from a trial court. For example, in an ejectment action, has a party established ownership by adverse possession of a portion of the property? In an eminent domain case, where is the boundary line of the con-demnee’s property? In many civil actions, does the plaintiff have standing? Has the statute of limitations run? Is crucial testimony barred by the parol evidence rule? The list is endless.
If the Majority were correct, the eloquent words of Justice (later Chief Justice) O’Brien would ring true today: “The bifurcated appeal foisted upon the courts can only be termed a judicial Hydra. Would that a Hercules could appear ... to slay this monster.” Hession Condemnation Case,
Accordingly, I would quash the appeal as interlocutory.