24 How. Pr. 324 | N.Y. Sup. Ct. | 1862
This action was brought by the assignee of an insolvent firm, to recover moneys due upon contracts with the firm for work, &c. The case was referred, and the referee has reported for the plaintiff. The various exceptions taken by the defendants will be noticed in the order in which they were submitted in the defendants’ points.
2d. It is objected that there was an implied warranty that the article should be fit for the purpose contemplated; and that the defendants were entitled to recover a claim for extra charges caused by the non-performance of the assignors’ contract. There is no special finding of the referee as to this item. He allowed the defendants an offset of 0781.68. Of what this stim was composed it is not easy for us to discover; nor is it material. The evidence as to the performance of the contract by the plaintiff’s assignors, of the waiver of that performance and extension of time for performance, as well as the value and amount of the defendants’ set-off, raised questions of fact for. the decision of the referee. Even if we differed from him on such finding, the evidence is of that character to render his finding conclusive.
3d. It is objected that the damages for non-performance of the contract within the stipulated time were liquidated damages, and that the defendants were entitled to recover these damages at one hundred dollars per diem, Independent of the provision of the contract making this a forfeiture, I think the cases do hot warrant the conclusion that this amount was to be considered as liquidated damages. The case which throws most doubt upon this question is that of Cotheal v. Talmage, (5 Selden, 551;) but in that case the contract was of that particular character which could not be separated
I am free to say that I have never been able to see the propriety of denying to the parties in any case the right to fix the amount of damages to be recovered in case of non-performance of a contract, and have always thought where the parties have agreed on a sum which they say shall be liquidated damages, that they should be held to their contract as they make it. There will now and then be an apparently hard case, but the establishment of such a rule when clearly
4th. Whether or not there was an adjustment of the amount due between the parties, was a question of fact for the referee. His finding is consistent with the evidence.
5th. The same remarks apply to the alleged counter-claim for extra charges of work on “ The Virginia.”
6th. The ruling of the referee as to the conversations in regard to the Concha, prior to the written contract, was not erroneous. Those conversations were merged in the written contract. They were in no sense admissible, unless to explain some terms which could not be otherwise understood. Ho such object was avowed, and it is clear that no such reason existed to admit the testimony.
7th. The question put to Belknap was one put to an expert on a matter with which the court or jury could not be supposed to be conversant, and as such was admissible. Such evidence is admissible to explain technical terms in a contract, and also, as in this case, to explain the meaning of provisions used in a specification.
My conclusion is that the referee committed no error which calls for a reversal of this judgment.
Judgment affirmed, with costs.
Ingraham, Leonard and Peckham, Justices.]