This is a personal injury case based upon allegations of negligence and strict liability. Larry Joe Colvin (Colvin) was an iron-worker employed by D.R. Smith, a steel еrection company. Colvin was working on a building being constructed by Robert E. McKee, Inc. (McKee), the general contractor. Red Steel Compаny (Red Steel) was the fabricator of the steel trusses and pur-lins used in the building. At the close of evidence, the trial court rendered an instructed verdict for MсKee and Red Steel. McKee settled during appeal to the court of appeals. The court of appeals affirmed the judgment of the trial court.
The building in question was constructed with concrete columns to which were attached supporting steel trusses. Steel pur-lins were to be laid аlong the top of and welded to the trusses. The purlins, used only as spacer material, separated the trusses from the roof. The architect’s spеcifications required 30 purlins, measuring 49 feet 11¾ inches in length and weighing approximately 660 pounds. Red Steel supplied seven purlins of the specified length but fillеd the rest of the order with shorter pieces. Although McKee and the architect accepted the shorter pieces which were used in the building, nеither one authorized Red Steel to change the length of the purlins.
While atop one of the concrete columns, Colvin was attaching a truss to the column. In an attempt to raise himself to an upright position, he reached overhead and grasped a purlin laying atop another truss alreаdy in place. The purlin came off the truss and Colvin fell 16 feet to the concrete floor. The purlin which Colvin grasped was eight *245 feet long and weighed approximately 88 pounds. The issues are whether there is some evidence that Red Steel was negligent in supplying the shorter purlins or whether Red Steel was strictly liable for supplying the shorter purlins.
NEGLIGENCE
To determine whether it was proper for the trial court to instruct a verdict for Red Steel, we must view the evidence in the light most favorable to Colvin. We must indulge against the instruction every inference that properly may be drawn from the evidence, and if the recоrd reflects any testimony of probative force in favor of Colvin, we must hold the instruction improper.
White v. White,
To sustain a cause of action for negligenсe it is necessary to produce evidence of a duty, a breach of that duty, proximate cause and damage.
Fort Worth & Denver City Ry. Co. v. Rogers,
Red Steel’s cutting orders, which became part of the contract with McKee, complied with the architect’s specifications requiring the purlins to be 49 feet 11¾ inches in length. There was testimony that it would take two men to move a purlin of the specified length, however, the eight foot purlin was easily moved by Colvin alone. Colvin testified that when the ironworkers worked with the shorter purlins, they had to lay them across two trusses “... so they wouldn’t fall off of or somebody would come and kick them off.” He further testified that, “When we put the short purlins [up], we always laid them down on their side like this where they wouldn’t gеt kicked over or knocked over and fall off or anything.” Colvin contends there is some evidence that the shorter purlins created a more dangеrous condition in the work place than the longer ones. Although the record does not disclose the number, there is evidence that the architect’s plans specify a number of shorter purlins in addition to the 30 longer ones mentioned above.
Colvin’s expert, Mr. Zetterlund, a professional structural engineer, testified that the standards of the Associated General Contractors of America, Inc. require that any steel which is raised in place on a building be secured immediately. Colvin’s Exhibit 44, a portion of a manual on accident prevention published by the Associated General Contractors of Ameriсa, Inc., states, “In setting steel each piece should be securely bolted before the line is taken off.”
Colvin testified that about a week beforе the accident occurred, he and a fellow employee were working on the uppermost level of the structure. He further testified that: the twо of them received all of the purlins from the crew working on the ground; that they placed the purlins atop the trusses; laid the purlins on their sides, and left them there.
In order for Red Steel to have foreseen the probability of an accident occurring because the purlins were cut in shorter lengths than sрecified, it must have also foreseen that Colvin and his fellow workers would violate the standards of the Associated General Contractors of America, Inc., by not securing the purlins when they were placed atop the trusses. There is no evidence in the record which will support such finding.
Colvin relies upon
Bennett v. Span Industries, Inc.,
Colvin also relies on
Texas Industries, Inc. v. Lucas,
STRICT LIABILITY
An essential element of Colvin’s strict liability cause of action is a finding that the product was not fit for its intended or reasonably foreseeable use at the time it left the manufacturer. The purlins were intended to be welded to the top of the trusses and were tо serve as spacers between the trusses and the roof material. The uncontroverted evidence proved that the purlins were fit for the intendеd purpose of providing a spacer between the trusses and the building roof when they left Red Steel. The question remaining is whether Red Steel reasonаbly could have foreseen that the purlins would be placed atop the trusses, left there unattached, violating the safety standards of the Associated General Contractors of America, Inc., and then used by a skilled ironworker to pull himself upright. Red Steel could not reasonably have foreseеn such a use. The purlins were used for the intended purpose and there is no evidence of any other intended or foreseeable use. The dangerous condition which contributed to Colvin’s fall was created on the jobsite not by Red Steel, but by Colvin, his fellow employees and McKee.
We affirm the judgment of the court of appeals.
