98 F. 946 | 7th Cir. | 1900
after making the foregoing statement, delivered the opinion of the court.
Concerning the letter of February 12, 1891, and its effect as a breach of the contract by the plaintiff, we said in our second opinion (46 U. S. App. 59, 65, 20 C. C. A. 233, 73 Fed. 984):
“On the facts as presented in the briefs, beyond which we have not looked, it does not appear that there was an adequate excuse for the refusal to accept further performance of the contract; * * * and, on that basis, whether other modes of relief were available or not, we think it clear that the defendant [now plaintiff] in error can have no remedy in an action upon the contract. It cannot at one and the same time repudiate an executory contract like this, in respect to a part of the subject-matter, and in respect to other parts insist upon enforcement.”
In this respect it is asserted, and seems to be conceded, that at the last trial "the facts remained precisely the same,” and, that being so, the court might without error have instructed peremptorily against a recovery by the plaintiff in any sum; and it would follow that there was no available error in any instruction touching the obligations, duties, or rights of the parties under their contract in so far as confined to the plaintiff’s right of action, — leaving it material to inquire only whether error was committed in respect to the right of the defendant to recover upon its counterclaim. In apparent recognition of ibis as the true status of the case, the argument in the brief for the plaintiff in error begins by saying that the main question, concretely stated, is “whether defendant can recover full contract price for eight-inch standard line pipe, made according to the specification of the contract, in the best manner known to the art of pipe making, but which for some reason is incapable of meet ing another, and, after all, the most important, requirement of the contract, — that it prove tight when tested in line at a pressure of one thousand pounds to the square inch.” We have not been able to perceive that this question, as stated, arises upon the record. It does
“If at the time of the delivery it remained necessary or desirable, and was practicable, by a reasonable expenditure, to bring the pipe up to the requirements of the contract, it was the privilege of the defendant [now plaintiff] in error to make the expenditure necessary for that purpose, and to exact reimbursement of the Crane Company, instead of resorting to the proof of comparative values; but if * * * the pipe met'the requirements of the modified contracts of the Indiana Company, and by reason of the Indiana statute a pipe capable of bearing a pressure of over three hundred pounds was not needed, then manifestly it was not reasonable to expend time or money on an effort to impart to the pipe a degree of strength which could be of no practical utility. Under such circumstances the ordinary rule should prevail, and the recovery should be on the basis of the difference of value between the article delivered and that which ought to have been delivered, to be determined by the market prices, or, if that should be impracticable, then probably by the difference in cost of production at the mills, — certainly not by the cost of repair or reconstruction on or along the trenches in which the pipe was to be laid, where necessarily the work would be more difficult and expensive than at the mills.” i
There does not seem to have been any attempt at the last trial to show, by market prices or otherwise, the difference in value between the pipe delivered and that contracted for. There has been no reference to evidence on that point, and the inference is fair that there was none. The evidence of the tests made of the pipe in line tended, as stated in our former opinion, “to show the quality and value of the pipe delivered as compared with that contracted for,” but that alone was not enough to afford a basis on which to compute or estimate damages on the theory of comparative values. The trial was not conducted on that theory, but, as before stated, the effort was to show that the pipe delivered was defective,— especially that the threading of the pipe and collars was defective, that the collars were too light, and that the substitution of the Hequembourg collars was necessary in order to make the line tight, even under the reduced pressure permitted by the Indiana statute. To the extent necessary to bring the pipe up to that standard, the plaintiff in error, of course, had the right to incur reasonable expense, and to exact' reimbursement, but could not at the same time claim damages on the other basis of difference of values; and there could have been no error in the refusal of an instruction which proceeded on the latter basis. The contention that, under the notice of a counterclaim which alleged the delivery of pipe in conformity to the contract, proof of strict conformity was essential to a recovery of the contract price, if in itself sound, seems not to have been insisted upon or suggested in the court below, and therefore should not be available here. If suggested, the objection could have been obviated by an amendment to the notice. No exception was saved and no error assigned which hinted at an assertion of variance between the pleading and the proof, if, indeed, such a notice of special matter of defense, accompanying the general issue, was intended to be governed by the strict rule applicable to a declaration, that the allegation and the proof must correspond. There
The first specific objection to the charge of the court is that in a number of passages, to which exceptions were saved, the plaintiff was required to sustain the issues of which it had the burden by “satisfactory evidence,” and not simply by a preponderance of the evidencie; but the meaning of the entire charge was clear, as in some instances it was explicitly stated, that the jury should be satisfied by a preponderance of the evidence. The last expression of the court on the point was too plain to be mistalren, when, after stating that the plaintiff was not entitled to recover “unless it has established a cause of’action,” the court added, “It must be established by a preponderance of the evidence.” In view of the nature of the issue;, however, which was whether the pipe was originally defective; in the threading or in the weight of the colliers, or was injured through the negligemee or want of skill of those employed to lay it, — on which latter point the plaintiff, having kept and used the pipe in line, certainly had the burden óf proof, — it is not clear that more than a mere preponderance of evidence might not properly have been required to establish a right of recovery on the declaration.
This objection to the charge; ought not to prevail for the further-reason that it is not pointed out in any exception taken, nor in any specification of error, according to the reeiuirement of our rules 10 and 11 (31 C. C. A. cxlv., 90 Fed. cxlv.), that a party excepting shall “state distinctly the several matters of law in the charge to which he excepts,” and that the assignment of error “shall specify separately and particularly each error asserted and intended to be urged.” To comply with that requirement, it was explained in the recent case of Stewart v. Morris (June Sess., 1899) 37 C. C. A. 502, 96 Fed. 703—
“It may be enough sometimes merely to quote the language of that part of the charge which is supposed to be erroneous. That will do if the language quoted expresses a single, proposition of law with unambiguous directness, but if the quotation embraces different propositions, or, like those now before us, is supposed to carry implications beyond or outside of what is expressed, it is intended by the rule that the exception shall state the particular meaning or implication, the exact proposition of law objected to; and then, to enable this court to determine whether the language of the court embodied that proposition, either expressly or by implication, it is necessary that the language be brought up in the bill of exceptions, and set out totidem verbis, as required by Tille 11, in the specilication of error. * * * These rules, if carefully and intelligently followed, will accomplish the purpose of their adoption, namely, that this court shall not be compelled to consider questions not brought to the attention of the lower court.”
These rules, it should be recognized, were prepared with care. Their terms are ioo clear to have needed exposition, yet, for some reason, — inattention, probably, — their most important requirement lias not been generally heeded. While the court would not needlessly embarrass the practice by insisting upon overnice observance of its rules, it is intended, so far as practicable, to accomplish the wholesome purpose that no question shall be reviewed here which was not considered below.
“For the purpose of charging liability upon the defendant for defects in the pipe and collars as laid, [the plaintiff must be held to a degree of care on its part of like character with that imposed upon the defendant,] to the extent that care and skill in the handling, screwing together, and laying equal in importance sufficiency of the pipe to secure a tight line.”
The clause in brackets, and a like clause in the portion of tlie charge covered by the sixth exception, it is insisted, have relation to the construction of the contract, and carry the implication that the defendant might discharge its obligation under the contract, short of performance, by the exercise of some degree of care or diligence. Neither in the exception nor specification of error is that objeeiion suggested. By the rules it should have been stated definitely as the matter of law excepted to, and should have been specified “separately and particularly” as error in the assignment of errors. It is not an obvious, but, rather, a strained, inference, not likely in itself to have been apprehended by the jury; and other parts of the charge, by which the force of the contract and the obligations thereby imposed on the defendant were clearly and correctly explained, make it impossible that the jury should have been misled as supposed.
To another part of the charge, to the effect that the plaintiff seeks to recover damages for “defects in the make and quality of the pipe delivered,” and that the plaintiff had the burden of the issue, the objection urged is that “this would indicate to the jury that unless the plaintiff could establish, by a preponderance of proof, the existence of defects in the pipe, it must be regarded as up to contract.” And to the part of the charge Immediately following, which was to the effect that if, on the other hand, the preponderance of evidence showed that the pipe, as received, “was so generally defective in thread and taper, or in the weight or quality of the collars, or both, that it was incapable of meeting the requirements of the contract,, and that the defects * * * were not obvious and clearly discoverable upon reasonable inspection on delivery, but could only be ascertained reasonably and fully by a test in line, and if the plaintiff has met all requirements [to be further explained], the finding should be for the plaintiff,” it is objected that “this requires the plaintiff to prove that the pipe was so generally defective in thread and taper, or in the weight or quality of the collars, or both, that it was incapable of meeting the requirements of the contract, and that the defects were such, etc. Now, this imports that the plaintiff must prove that owing to these particular defects the pipe leaked. Obviously, this is not correct.” And by way of argument it is added that “if
Another portion of the charge is said to be obnoxious to two objections, neither of which, however, was disclosed in the exception taken or in the specification of error. The instruction referred to consists of three distinct sentences, and as many distinct propositions, any one of which might have,been the subject of exception; but the two objections urged are directed to the single proposition that by the contract the Crane Company “did assume and agree to furnish pipe and collars of material, strength, weight, and threading which would substantially conform to the specifications of the contract; and it further agreed and promised that the pipe so furnished should be sufficient in those particulars, when laid in line with due care and skill, to stand a pressure of 1,000 pounds gas to the square inch, and to prove tight in line when tested.” Objection is now made to the word “substantially,” and' to the phrase “in those particulars,” as placing an unwarranted limitation upon the responsibility of the defendant; bat the particulars mentioned embrace all that was in dispute, and substantial conformity to the specifications of the contract was certainly sufficient if the general requirement was met, that when in line the pipe should prove equal to the stipulated test. • As the court proceeded at once to say, “It was the quality and competency of the pipe and collars to this end and test that was thus warranted by the defendant, and not a tight pipe line.”
A like objection, not disclosed in the exception or specification of error, is made to another part of the charge on account of the expression “so generally defective in thread, taper, and collars, In weight, thread, and taper,” and in another pari: to the expression “that the defects in the pipe were due to faults in the mill, with which defendant is chargeable”; but in view of the immediate context, and other expressions already referred to, there is no reason to believe that the jury was misled in respect to the obligation of the defendant under the contract.
There was at the trial a question whether the collars should have been recessed so as to admit of calking with lead, and in respect thereto the court instructed that the contract provided for screw joints, not lead joints, and that the absence of a recess or other provision did not of itself constitute a breach of the contract, unless, in the state of the art of pipe making as it was when the pipe was made for delivery under this contract, a provision for lead calking was a mere incident or reasonably necessary to the making of a screw; joint, but that if such recess was not a mere incident to a screw joint, but “a separate and additional joint, independent of the screw,” “it was no part of the duty of the .Crane Company, under its contract, to furnish its collars with such dovetail recess for lead calking.” The word “duty,” as here used, in connection with the words “under its contract,” necessarily means “obligation,” and is not objectionable. In other respects the charge was favorable to the plaintiff, because the contract neither expressly nor by any possible implication required more than a screw joint. That only the defendant agreed to make, and covenanted that it would stand the test; and so the jury was clearly and sufficiently instructed in another part of the charge. It was, perhaps, the privilege of the defendant to employ the .recess, or any other means necessary to make the joints tight; but, excepting the things specified, there was
Exception is saved to the following portion of the charge, — -the only one which may be said to embrace only a single proposition or matter of law, rajable of presentation under the rule by a mere quotation of tlie language:
‘•You will bear in mind, gentlemen, that defects here and there in tlie pipe cannot be recovered for in this action. The plaintiff sues upon a total failure of tlie pipe. líe cannot recover (in this action, at any rate) for defects which may have existed here and there in the pipe. It must be a failure which extends, as I have explained to you, through the whole lot of pipe, so as to make it insufficient for the pulposo of that line. And you will then consider tlie testimony of the Inspectors in that view and for that purpose.”
Whether or not evidence of "defects here and there in the pipe” —a very indefinite expression, surely — -was admissible under the declaration, we need not decide. It does not appear, and is not claimed, that such evidence was offered. The actual contest, as already explained, was over the condition and quality of the pipe and collars used in the construction of the line as a whole. The only proper application of this charge would seem to have been to pipe or collars ¡<U. were rejected, and not used in the line, because found unfit. It is said in the brief of the plaintiff in error that the injurious character of this charge is apparent from the fact that the undisputed evidence shows that between twenty and twenty-five miles of the pipe in controversy was condemned on a joint inspection by representatives of both parties. It is evident that “defects here and there” could not have been understood by the jury to refer to such a quantity of pipe which had been condemned by mutual agreement. Tbe stalenient of fact, however, is not fully borne out by the evidence. There was a species of inspection of pipe and collars, which had been delivered along the line, conducted by an agent of the plaintiff with the assistance, going little beyond observation, of a representative of the Crane Company; and joints of pipe and collars found defective in the thread or seam were marked, and written reports thereof were made, which were signed by both agents, lint the defects found, it is evident, were, in the main, trifling. They did not prevent the use of the pipe in the construction of the line. The plaintiff’s inspector testified that the majority of it was used “right along in making the new line, with the ilequembourg collars.” There was no attempt in that inspection to determine whether the defects discovered were attributable to faults in manufacture or in the handling.
The following instruction, it is said in the brief, was asked “as to the burden of proof”:
“Plaintiff was not bound to receive from the defendant any pipe whatever which did not conform to the requirements of the contract, in its capacity, if properly laid in line, to prove tight in line at a pressure of one thousand pounds to the square inch, gas or air; and, unless you find from a fair preponderance of the evidence that the pipe delivered by the defendant under the contract to the plaintiff, was up to the contract requirements in this regard, the defendant is not entitled to recover the contract price thereof, however you may find as to other matters in evidence.”
Without the statement in the brief, it could hardly be suspected that this was designed to be an instruction “as to the burden of proof.” No ordinary jury could understand its significance in that respect. It is in itself objectionable. There was no question in the case of what character of pipe the plaintiff was bound to receive, and what it was proposed to say on that point, unless more was added, was liable to be misleading in respect to the liability of the plaintiff to pay for pipe which had been received and used. If the pipe was not up to the contract requirements, under a pressure of 1,000 pounds, and yet was of no less value on that account, being equal to all the requirements of the situation, as altered by the statute limiting actual pressure to 800 pounds, a recovery of the contract price was not improper.
By another part of its charge, after referring to evidence touching the manner in which the pipe was laid, and particularly portions which had to be bent, the court directed the jury to “determine from all the testimony whether the neglects in the manner of screwing together and laying were of such a nature that they could fairly and reasonably account for the leaky quality of the portion of the line which was put together and tested, and for a large portion of the defects which were found by the inspectors in the pipe as examined in November — December, I believe it was — of 1890.” The criticism on this, now said to be obvious, but which was not suggested below, is that, of the 106 miles delivered, only twenty miles were laid, and they were not covered by the inspection; that the remaining 86 miles were never laid or screwed together, and therefore it was obviously erroneous to tell the jury that they should determine from all the testimony whether the defects of screwing together and laying were of a nature to account for a large portion of the defects found by the inspectors. No reference has been made to the evidence on which this criticism is based, but, while the last clause of the instruction seems to introduce an element of possible confusion and inconsistency of thought, it is not to be supposed that a jury of ordinary intelligence, aiming at an honest conclusion, was led thereby to believe it possible, or to understand that the charge was intended to mean,
The court, we deem it clear, did not err in admitting proof of tests made during the progress of the trial, at the shops of the defendant, of collars produced in court by the plaintiff in error as samples of defective collars received of the defendant under the contract. The supposed defect being in the collars, it did not affect the competency of the evidence that the test was made by applying them to pipe which had not been delivered under the contract. The court, on the other hand, excluded evidence of tests made by the National Tube-Works Company of one mile of pipe composed of “regular eight-inch line pipe manufactured by that company”; but, as that line was constructed for the purpose of making the test, and contained neither pipe nor collars which had been delivered under the contract, it was a collateral matter, not directly pertinent to any issue in the case, and even if, in its discretion, the court might have admitted the evidence offered concerning it, the refusal to admit it was not error.
The court refused a special request for an instruction defining the obligation of the defendant under the contract, and declaring it not sufficient to relieve the defendant from the obligation, if, in the opinion of the jury, a pipe made with the best skill and materials, according to the specifications of the contract, would be incapable of standing the stipulated pressure test. The court in its own «charge very clearly defined the obligation of the defendant to furnish pipe capable of standing the required pressure, and proving tight in line. There was no suggestion or claim hy the defendant that it could be relieved fx*om the obligation of full performance on account of' any-supposed or proven impossibility or difficulty of making pipe capable of doing what was required. On the contrary, the persistent contention of the defendant was that the pipe delivered had that capacity, the shop tests made before delivery as well as that made during the trial showed that it had, and the verdict shows that the jury was convinced of the fact. But, if the request had been in itself unobjectionable, there would have been no error in refusing it, because, in substance, it was embraced in the charge given.
Considering the length of the court’s charge, and that it was nof given in writing, it is not remarkable that in some respects it is obnoxious to verbal criticism; but as a whole it was notably clear and