Opinion for the Court filed by Senior Circuit Judge WILLIAMS.
Columbia Gas and Columbia Gulf (“Columbia”), petitioners here, entered into agreements with several local distribution companies according to which the latter received discounted service on the condition that they waive certain rights under the Natural Gas Act (the “Act”). Columbia filed the discounted rate agreements with the Federal Energy Regulatory Commission, which rejected them and held that Columbia either had to refile them as negotiated rate agreements or remove the waivers. Columbia petitioned for rehearing, and FERC denied the petition.
We deal here with two sets of issues. First, the Commission argues that we do not have jurisdiction to consider arguments that Columbia did not make in its petition for rehearing. We reject this jurisdictional challenge and treat all of Columbia’s arguments as properly before us. Second, we review Columbia’s assertions that FERC’s orders are inconsistent with its precedents and that its determinations are otherwise arbitrary or capricious. We reject these challenges and affirm the Commission’s orders.
* * *
Columbia Gas and Columbia Gulf are natural gas companies that provide various services under Commission-approved tariffs, including the transportation and delivery of natural gas. Both companies entered into agreements to serve three large local distribution companies — Mountaineer Gas Company, The Cincinnati Gas & Electric Company, and The Union Light Heat & Power Company — at discounted rates (collectively, the “discount shippers”). In addition to offering the discounts, Columbia waived its right under § 4 of the Act, 15 U.S.C. § 717c, to seek Commission approval for an increase in rates to be charged the discount shippers, and promised that they would receive the benefit of any Commission-approved reduction in the discounted rates. Reciprocally, the discount shippers agreed to waive their right under § 5 of the Act, 15 U.S.C. § 717d, to challenge any of Columbia’s rates as unjust or unreasonable. Importantly, the § 5 waivers covered not only the discounted rates but also precluded the discount shippers from challenging the rates for any of Columbia’s services.
FERC initially rejected the agreements,
Columbia Gulf Transmission Corp.,
109 F.E.R.C. ¶ 61,152 (2004)
(“Initial Order”),
on two grounds. First, it said that § 5 waivers were not appropriate in discount agreements but could be included only in negotiated rate agreements. (Columbia
FERC denied the petition for rehearing, but marshaled slightly different reasons.
Columbia Gulf Transmission Corp.,
111 F.E.R.C. ¶ 61,338 (2005)
(“Rehearing Order”).
The Commission continued to maintain that the discount shippers’ § 5 waivers were impermissibly broad; it reasoned that a pipeline should not be permitted “to condition the offering of a discount for one service for which a shipper may have competitive alternatives on limiting the shipper’s section 5 rights to challenge the pipeline rates for other services over which the pipeline does have market power.”
Id.
at 62,
FERC argues that we lack jurisdiction to consider Columbia’s arguments addressed to Commission justifications that emerged for the first time in the Rehearing Order. Section 19(a) of the Act, 15 U.S.C. § 717r(a), requires that a party petition FERC for rehearing before it challenges a Commission order in court. Section 19(b) goes on to say that “[n]o objection to the order of the Commission shall be considered by the court unless such objection shall have been urged before the Commission in the application for rehearing unless there is reasonable ground for failure so to do.” 15 U.S.C. § 717r(b). We have frequently remarked on the strictness of the jurisdictional provisions in the Act. See, e.g.,
ASARCO, Inc. v. FERC,
Our cases support the Commission’s claim only up to a point. Where the Commission on rehearing changes its actual order adversely to the petitioner- — not merely the reasoning — it is commonly treated as having issued a new order. While a party may challenge the new order in court without a new petition for rehearing, such a challenge can attack only
We adopted this approach in
Southern Natural
because “[ojtherwise, we would ‘permit an endless cycle of applications for rehearing and denials,’ limited only by FERC’s ability to think up new rationales.”
Id.
at 1073 (quoting
Boston Gas Co. v. FERC,
The principle of Southern Natural and Washington Water is that when a party filing a petition for rehearing was not on notice of the rationale that FERC would adopt in the rehearing order, the party has a “reasonable ground” for not having addressed that rationale in its petition and accordingly may do so for the first time in court. And a party is on notice only of ideas that FERC has addressed in the initial order with reasonable specificity, but not of ones to which the Commission has only alluded vaguely. See Southern Natural, 877 F.2d at 1072.
We note that the exhaustion requirement in § 19(b) of the Act is, on its face, similar to provisions in other statutes. See
Washington Ass’n for Television and Children v. FCC,
For each of Columbia’s arguments, we will consider whether FERC’s Initial Order placed Columbia on notice of the rationales that the Commission eventually adopted in the Rehearing Order.
* * *
Columbia claims that FERC contravened its own precedents when it decided that the § 5 waivers were overly broad.
In the Rehearing Order, FERC explained “the Commission’s general policy of restricting the use of [§ 5 waiver] clauses to relatively narrow situations.”
Rehearing Order
at 62,
As to
Algonquin
itself, the Commission pointed to features of that case sharply reducing the risk of discrimination: Algonquin had offered to execute such agreements with all similarly situated customers, and it had balanced the § 5 waivers by the customers with a pipeline agreement not to seek any generally applicable rate increases under § 4.
Rehearing Order
at 62,
Columbia’s second objection pertains to FERC’s economic rationale justifying a restriction on the scope of § 5 waivers. FERC essentially argued that companies like Columbia should not be allowed to exploit market power and demand § 5 waivers with respect to rates that are not the subject of discounts.
Rehearing Order
at 62,506-07 P 14. In response, Columbia maintains that all of the rates — discounted and non-discounted — are interrelated, so that relief under § 5 for one rate entails changes in all others. Because Columbia didn’t object to the market power rationale in its petition for rehearing, we must consider whether the Initial Order adequately placed Columbia on notice of the rationale it now attacks. At a high level of abstraction, the Initial Order did discuss FERC’s concern about discount agreements and the breadth of the § 5 waivers. But the Rehearing Order introduced a new basis for concern — the fear that in markets where shippers had alternatives (i.e., competitive markets) pipelines would bargain
Although the objection is properly before us, it is unavailing. As a preliminary matter, we note that Columbia first articulated its objection in a footnote in its opening brief, a dubious practice.
United States v. Whren,
Finally, Columbia argues that FERC erroneously decided that Columbia’s agreements with large shippers are unduly discriminatory against small shippers. In exchange for discounts on certain rates, the large shippers waived their right to challenge the rate structure or the “recourse rates.”
Rehearing Order
at 62,
On the merits of the claim, Columbia fares less well. It attacked FERC’s logic by noting that even if § 5 waivers are narrow in scope, large shippers will not challenge other rates unless the expected benefit of the challenge outweighs the discount. Furthermore, Columbia observed that the interests of large and small shippers often are not parallel, meaning that small shippers do not necessarily benefit from large shippers’ § 5 challenges. But to say that FERC’s preservation of the large shippers’ right to bring challenges is an imperfect protection for small shippers’ interests is a far cry from establishing that the benefits of FERC’s policy are outweighed by its drawbacks. Columbia does not challenge FERC’s basic theory that the broad § 5 waivers impede the readiness of large shippers to bring challenges that might also benefit small shippers. To the extent that the agreements at issue here likely operate to the detriment of small shippers at the margin, the Commission’s logic is sound. We see no basis for concluding that FERC’s rationale is arbitrary or capricious.
For the foregoing reasons, we uphold the Initial and Rehearing Orders against all challenges by Columbia.
So ordered.
Notes
. We infer that FERC emphasizes the subscription phase, when a pipeline firm is seeking commitments from potential customers for a new pipeline, on the ground that then a pipeline's market power is relatively low: potential shippers will have either the alterna-five of continuing to use their then-current carriers, or, if they have no current carrier because they haven’t yet constructed facilities to use the proposed service, of choosing to locate their facilities elsewhere if they decline the proposed new service.
