*1 they do not Consequently, tacts in Texas. here.
control
Accordingly, summary judgment severed,
favor of Fox affirmed and sus- special appearance
R.Civ.P. but the Applied Polymers
tained in favor of is re- against Applied Poly-
versed and the cause
mers is remanded for trial. INTERNA
COLUMBIA ENGINEERING
TIONAL, LTD., Appellant, al., Appellees. M. et
James DORMAN
No. 8324. Texas, Appeals
Court of Civil
Beaumont.
April 1980.
Rehearing May Denied *2 Kirby’s lines across fence and
the extended its property. over
Part M. and March James Dorman On ironworkers, em- W. Walter Blackshear — assisting in the ployees of McBride —were this steel near prefabricated on fence. This steel “hooked” east on it was truck which both ends from the “cherry picker” from a delivered cables (movable) crane or “telescopic” a with crane, operator the Flow- The boom. employee then ers—also a McBride —would it to truck and lower swing steel off the “guid- and Blackshear ground. Dorman end, steel, ed” the one at this apparatus attached to the cable. On (March 1974), the came into crane date line power contact with States’ Gulf 15,000 electricity to flow causing volts Dorman through the and the bodies of cable Blackshear, of whom were horri- and both injured. bly permanently and and A suit resulted in which Dorman Benckenstein, Beaumont, ap- John H. for plaintiffs below. Blackshear were pellant. trial, Black- Shortly, prior to Dorman and Tonahill, Jasper, appellees. Joe H. Kirby, with Gulf shear settled their cases Minnis, four Casey, and United for
DIES, Chief Justice.
($400,000).
dollars
Suits
hundred thousand
indemnity flowed be-
for contribution and
prior
to March
Sometime
and Colum-
tween
defendants
Corporation (hereafter Kirby)
Lumber
ac-
trial,
lengthy
After a
a
bia.
plant (Evans Co.)
quired
Highway
across
percent negligent
one hundred
(east side)
its mill
in Silsbee
sub-
and awarded Dorman and Blackshear
place
the intention
particle
to build in
the trial
damages. Additionally,
stantial
plant.
consulting engineer
board
respond
decreed
should
court
that Columbia
plant
Engineering
Inter-
or-
indemnity
and
to their cross-actions
national,
(hereafter Columbia). The
Ltd.
make them whole for
dered Columbia to
general
Enterprises,
Casey
contractor was
($400,000)
hundred
dollars
four
thousand
(hereafter Casey).
Inc.
Erec-
McBride Steel
prior to trial
they had
in settlement
(hereafter
Corp.
McBride)
tion
was a sub-
It
from this
and Blackshear.
is
Dorman
fabricating
contractor
steel.
Erec-
Minnis
perfected
ap-
has
this
judgment Columbia
Minnis)
Corporation (hereafter
tion
was a
re-
parties will be
peal.
clarity,
For
case
subcontractor and dismissed from the
by name.
opinion generally
to in
ferred
summary judgment.
United
Fi-
States
(hereafter United)
delity
Guaranty
Co.
trial
first
Columbia’s
“[t]he
was intervenor.
admitting
erred in
into evidence
Dorman,
as-
newly
of .
that he
Next
the east side fence of the
acquired
Engineer,
property Gulf States Utilities
sumed
[Columbia’s]
(hereafter
States)
to him
Company
Gulf
owned
or someone from Columbia indicated
tower,
Blackshear,
beams
high voltage
place
steel
maintained a
the fence where the accident oc- wards the
Nanny
fence.”
then came over
curred,
(Dorman)
over
objection that
told Dorman to move it. He
[Columbia’s]
highball”
hearsay, speculative,
gave
such evidence was
testified Moss
“us the
means he
the dunnage
wanted
and steel
upon
not based
fact.”
(and
line).
placed
next to the fence
supervi-
Herb Moss was Columbia’s main
began working
Herbert Moss
for Colum-
sor
engineer
on the work site. On
bia in June
on loan from
another com-
4, 1974,
March
Dorman and Blackshear be-
*3
pany.
consulting engineer
He was a
gan unloading
dunnage
the steel
further
Kirby].”
“had to coordinate the work [at
from the fence referred to herein and fur-
inspected
He
the work and then would cer-
power
ther
from the
line. Dorman then
Kirby
tify to
the amount of work that
(Milton Nanny, Sr.)
testified his foreman
by
would be done
each contractor.
It was
came to him and ordered him to move the
Kirby paid
on this basis
the contractors.
(and
steel closer to the fence
therefore
accident,
Friday
Nanny,
before the
Sr.
power line).
refused,
Dorman at first
but
(McBride foreman) asked Moss if he could
Sr.,
Nanny,
insisted saying, “Because Mr.
unload the steel at the south end of the
Moss says
going
there is
to be a little build-
answered,
blending building. Moss
“I told
ing
going
come out here and it’s
to be in the
objection
him I had no
to him
way.” This evidence did not
its pro-
derive
there,
high
that steel
to watch that
bative force
competency
and cred-
power
blending
line above.
. The
was, therefore,
ibility of Dorman and
inad-
building
seventy feet
sixty
was
or
hearsay.
missible as
the many
See
authori-
(and
east fence
hence about that much far-
ties cited in 24 Tex.Jur.2d Evidence 557 at
§
line). However,
power
ther from the
Moss
(1961);
also see 24 Tex.Jur.2d Evidence
Nanny
going
little
was
to unload “[a]
(1961).
560 at 57
§
blending building,
southwest of the
[w]hich
However
fence”;
trial
ruled:
by
would be
to which Moss had
portion
of the
is strick
objection
by Nanny,
no
when asked
He
“[T]hat
Sr.
en,” and “The jury is admonished not to
telling Nanny,
denied
Sr. “where to locate
consider it
any purposes
Nanny
Monday,”
of what
this steel at a fenceline on
but he
surprised
told him that
“wasn’t
that
unloaded it over
they
Moss said.” “This therefore
Sr.,
Nanny,
there.” He didn’t know
was
cures the error.”
1 C. McCormick & R.
and,
doing
stopped
this or he would have
Ray,
(Texas
Texas Law of Evidence
29§
“Yes, sir,
authority
stop
I had the
him.
1956).
point
Practice 2d ed.
This
is over
by Kirby’s
.”
at-
On examination
ruled.
torney,
hazard
Moss admitted the
would
We believe
appeal
this
will be better un-
the steel
have been the same whether
up
derstood if we next
take
Columbia’s
Monday
Friday
or
location.
unloaded at
through
points
Points 6
11. These
contend
unloading. Kir-
nothing
knew
findings
negligence
proximate
“as the construction
relying
on Moss
supported
cause
are
Columbia
supervisor.”
thought Columbia was
Moss
or
insufficient evidence or are
with more
providing
little unfair in not
him
great weight
preponderance
of the evi-
de-energize this
help. He took no action to
dence.
power
represented Kirby
line. Columbia
We review
points
guid-
these
under the
dealing
insofar as
safety was concerned
Alviar,
ance of Garza v.
with the
Had he been fur-
contractors.
(Tex.1965),
Estate,
King’s
and In re
“probably”
help
nished more
(1951).
tlemen and Moss] making would have the decision au- Dillahunty, an electrical con- James C. thority where to locate that steel? tractor, parties con- was examined con- cerning meaning of the written “A. say would Mr. Moss.” tracts. Sheffield, superintendent Robert Allen referred to in this The two contracts
for Gulf testified he had received no opinion. are to this For attached request de-energize line in following in the observations identification and, made, question, if one had been we have marked them “A” and “B.” de-energized; would have been that such a request proce- provides would have been a “A” that normal We note that contract dure; (Gulf States) frequently Columbia: they
get
requests,
provide insulating
such
or to
“Complete
supervision
construction
devices.
and liaison work with contractors
(B.2)
sub-contractors.”
Walker,
manager
Harlan
resident
suppli-
work
equipment
2. “Liaison
Kirby,
for the
contracted with Columbia
de-
expediting
equipment
ers and
supervision
inspection
determining
(B.6)
liveries.”
how and what and what means were em-
provisions:
ployed
getting
job completed and
“B” has these
Contract
being
County,
(Tex.Civ.
Engineer
[Columbia],
1. “The
Jefferson
S.W. 148
1897, writ);
Inman,
App.
no
and Polk v.
interpreter
first
instance
S.W. 261
judge
the Contract and the
of its
— Texarkana
writ),
propositions
parol
performance,
powers
shall use
under
to show the con
evidence is inadmissible
per-
this Article to enforce faithful
a written
placed
struction to be
contract
both
formance of
Contract
contract,
in the
ambiguity
where there is no
(3a)
parties hereto.
.
.
.
parties may
as
and the intent of the
2. “Time
of the essence for the Con-
therefrom, and, where a written
certained
any
.
. ma-
tract and if
time
agreement
unambiguous,
testimony of
chinery
equipment
explain
properly
it was
expert
witness to
executing
ap-
methods of
the work
with these
quarrel
We have no
excluded.
pear
Engineer
to be unsafe
being
Texas law.
general propositions
Engineer may
order
professor
J. Brennan is a
of indus-
James
improve.
and direct the Contractor
University and a
engineering at Lamar
trial
(3b)
.
.
.’’etc.
degree
with a
in elec-
consulting engineer,
Engineer
ques-
3. “The
shall decide on
and a Ph. D. in mechani-
engineering
trical
arising
tions
under the Contract Doc-
engineering
University
cal
at Aus-
” (4a)
uments.
.
.
he was familiar with the
tin. He testified
4. “The
under the direction
Contractor
Kir-
type
program
that went on between
responsible
Engineer
of the
shall be
building
in the
by and Columbia
.all
such an
particle
plant. He said in
board
” (18b)
materials.
owner
undertaking it was common for the
*5
Engineer
authority
5. The
in an
has
consulting engineer, and that
employ
to
stop
progress
emergency to
of
He read
he had served in such function.
such
B,
work whenever
(of
be-
3a
Exhibit
contract
Section
stoppage may
necessary
McBride)
be
ensure
and said that “as
Kirby
tween
and
(34a)
safety
having
of life.
.
been involved in
engineer
an
and
construction,
paragraph puts the bur-
believe the evidence we have
We
acting in
Engineering
den on Columbia
of
sufficiently supports
summarized
above
Kirby’s
. He inter-
best interest.
1
jury’s
Special
answers to
Issues Nos.
and
had the
preted 3b to mean Columbia
(negligence
proximate
2
and
cause of Co
operate safely
to ascertain the contractors
and, therefore,
lumbia)
overrule Columbia’s
way
contracts are
“and this is the
these
through
Points
Eleven.
Six
that
usually
He also testified
drawn.”
up
We now take
Columbia’s Points Three
gave
the contract
Colum-
paragraph 10a of
points urge
through Five. These
error
cer-
responsibility to make
supervisory
bia
permitting testimony
the trial court in
of
all laws includ-
tain the contracts observed
the contract between
James Brennan that
O.S.H.A.;
the contractor violated
ing
that
Kirby
placed
the burden of
Columbia
para-
that
He said
certain of these rules.
Columbia;
safety operations upon
allowed
made the contrac-
graph 18b of the contract
interpret
Brennan to
a written contract
engineer
re-
of
tor under the direction
rule;
parol
of
evidence
that
violation
supplied.
materials
sponsible for
an
qualified
Brennan was not
to render
type
the same
put on much of
Brennan
interpretation;
and that
should
Nemeth, vice
testimony through Eugene
testify
permitted
not have been
Colum-
Columbia,
an electrical
of
also
president
requirements
bia violated the
of
Occu-
plans
prepared
engineer. Columbia
Safety
Health Administration.
pational
He was
specifications including electrical.
Henry
Phillips,
Columbia cites
v.
105 Tex.
He
Moss arrived.
project manager before
“Now,
533,
(1912);
attorney,
538
v. Had
151 S.W.
Soel
was asked
Columbia’s
den,
182, 19
(1892);
was made be-
1087
Don
the contract
that
85
S.W.
know
He
. ?”
Tindall,
(1869);
ley v.
Slayden v.
108
Craycroft.
194
Deal
trial,
S.W.
plaintiffs
Before
(1917).
Craycroft
him;
settled with
and dismissed
plaintiffs joined
later
Deal Companies.
Columbia’s Points Three through
Plaintiffs settled with the latter and dis-
Five are overruled.
missed it before trial. When the case went
*
Part II
to trial the only
parties
plain-
active
were
tiffs and defendant Deal.
Columbia’s Twelfth Point is: “The trial
percent
Craycroft
neg-
applying
erred in not
the credit rule
ligent;
Companies percent;
Deal
Travel-
reducing
judgment against
appel-
percent;
percent;
ers 20
Deal 45
and that
lant, Columbia, $400,000
the amount of
—in
plaintiffs’
$444,999.
damages were
Plain-
the voluntary payment
by appellees
made
already
tiffs had
received settlements from
to Dorman and Blaekshear.” The Four-
Travelers, Craycroft, and
Companies
Deal
teenth Point is the same.
in excess of this sum.
Columbia cites the recent case of Deal v.
Plaintiffs
judgment against
moved for
Madison, 576
(Tex.Civ.App.—
S.W.2d 409
Deal
jury;
urged
for the award of the
Deal
e.).
Dallas
writ ref’d n. r.
plaintiffs
had obtained full satisfaction
There
surviving husband and
arguing
plaintiffs
the settlements
in effect
Betty
children of
Madison who died in an
nothing.
should take
fire,
apartment house
first sued Travelers
agreeing
In
with the defendant the court
Insurance
Later
Company.
Travelers filed
Gettegno v. The Pari
carefully analyzed
Deal,
party
against
a third
claim
the land-
sian,
(Tex.Com.App.1932,
owner,
Craycroft,
the architect who
holding approved);
Baylor
Bradshaw v.
designed
apartments.
The trial court
University,
comparative so as to any plaintiff proportion each defendant in in this case. Whether tribution from ultimately found him, to to rath- of the defendants are negligence to the attributable settlement, we favorable require equal er than to an contribution have made a nature of the tortfeasor, aleatory formerly required ‘respect as will from Doyle .’ process. the in- settlement permit article but still to 701, 711 n. 5 States, F.Supp. of his jured party only one satisfaction United were allowed to (D.S.C.1977). If Dresser (Emphasis damages.” supplied.) it recovery Leger’s reduce And, (Id. 420): the court held at settlement, Dress- Leger’s dollar value of “[Tjherefore, non-settling a tortfeasor pay portion a small er would be left to paid entitled to deduct amount in $182,- ($284,090.00 damages minus total damages settlement from the amount of $99,400 plain- minus for 331.05 settlement Rather, we jury. negligence equals contributory tiff’s (d) giving interpret subdivision full damages even $2,358.95) of the total effect to the Bradshaw rule in the con- was the main con- though negligence its comparative negligence, text of so that Thus, causing them. in tributing factor remaining permitted defendants are substantially benefit Dresser would to share the credit for the settlement in or miscalculation in re- intransigence proportion respective percentages to their to the case. We refuse fusing to settle therefore, negligence, and, propor- in a which would reward adopt approach (Em- respective tion to their liabilities.” refusing to settle. If defendant phasis supplied). case, it must be party try decides to Clearly application this case has no accept whatever benefits or prepared to instant case because the jury found Colum- from its decision.” burdens flow percent negligent. bia 100 now dis- points overrule the would Company, In T. L. James Inc. v. cussed, the court has majority but the Statham, (Tex.1977) (also attached con- determined otherwise Columbia), plaintiff relied on sued a milk curring opinion. producers employee, association and its Part III alleging plaintiff’s pickup the latter struck Point contends Columbia’s Thirteenth rear, judgment, recovered a ordering appellant “The trial court erred registry into the of the court. $200,000, $100,000 Gulf pay Kirby to highway later Plaintiff sued contractor $25,000. ...” McBride failing flagman station a to warn to approaching vehicles from the rear of art. 2212a Tex.Rev.Civ.Stat.Ann. stopped deny- in front of them. In traffic (Vernon Supp.1978) provide does not suit, (Id. ing the second the court said at situation, we have found no au this 868): Nevertheless, subject. thority on this [plaintiff] could have
“Statham require Columbia inequitable seems to us to brought jointly [against suit both defend- nothing it had pay for the settlements No He did not do so. with, advantage from. gained ants]. do addressing ques- issue was submitted therefore, We, and affirm sustain comparative negligence tion of . .” judgment court’s portion of the trial Columbia, plaintiffs
favor of
portion
reverse and render
We have no such situation in the case
repay
requiring Columbia
Dube,
Clemtex,
review.
also
Ltd. v.
See
*8
settling
the
defendants.
81
persuasive, pertinent,
apposite.
It
rely
confining
plaintiff’s
in
each
recov-
either
we
jurisdiction whose
by
jury:
the
is a case from another
ery
damages
to the total
fixed
The case
controlling.
holdings are not
v.
(1)
Justice Hickman in Bradshaw
Chief
general
Act “and
arose under the Jones
99,
University, 126 Tex.
84 S.W.2d
Baylor
in a fed-
law” which was decided
maritime
703,
(1935):
705
and the
did
eral court in Louisiana
general acceptation
“It
is a rule
any Texas
touch,
tangentially,
not
even
injured party
to but one
is entitled
doctrine set out
If such a
cases or statutes.
by
injuries
satisfaction for the
sustained
law,
into Texas
imported
Leger
in
is to be
being
inju-
.
. There
one
him.
.
our
legislature
the
should be done
can,
ry,
justice,
there
be but one satis-
”
Supreme Court.
injury.
faction for that
.
(2) Chief Justice Greenhill in Palestine
Conclusion
Contractors,
Perkins,
764,
Inc. v.
386 S.W.2d
judgment of the trial
Consequently, the
(Tex.1964):
766
and Black-
which awarded Dorman
“Perkins relies on a number of Texas
the
precise
sums
shear
cases which state the rule that
the non-
4, respective-
Issues 3 and
Special
answer to
settling tortfeasor
entitled to credit on
is
plaintiff
reduced as to each
ly, is now
judgment
already
for the amount
$200,000
plaintiff
sum of
”
paid for the covenant not to sue.
defendants; and,
settling
from the
received
reformed,
judgment as to the said
(3)
Pope
Mr. Justice
in McMillen v. Klin
affirmed;
portion
plaintiffs is now
193,
gensmith,
(Tex.1971):
467 S.W.2d
subrogat-
judgment
which awarded
do,
preserve
“In
as we
carrier
compensation insurance
ed worker’s
rule that a claimant in no event will be
(and
attorneys)
portion
of the sum
entitled to
than the amount
recover more
affirmed;
is
plaintiff
awarded to each
required for full satisfaction of his dam-
portion
judgment
which ordered Co-
ages.
settling defendants the
pay
lumbia to
to the
which said defendants had
(4)
amount
Mr. Justice Steakley in T. L. James
ren-
plaintiffs is reversed and
Statham,
Company,
Inc. v.
558 S.W.2d
'
865,
settling
defendants
denying
dered
(Tex.1977):
recovery against Columbia.
“We adhere to the rule stated in [Brad-
shaw, supra]
explicitly
reaffirmed in
Tex.R.
provisions
Pursuant
[McMillin, supra], that a claimant
in no
448,
apparent from this
Civ.P.
for reasons
event will be entitled to recover more
of the costs in
concurring opinion, one-third
required
than the amount
for full satis-
is assessed
courts
damages.”
faction of his
said costs
jointly
severally;
one-third of
adjudged against
defendants
Many other authorities could be cited but
3,
(as
supra), jointly and
set out in footnote
to do would
so
belabor a
well settled
and,
costs is
severally;
one-third of said
Supreme
our own
Court.4 Even Deal v.
adjudged against Columbia.
Madison,
409,
(Tex.Civ.
419-420
App.
n.r.e.),
writ ref’d
relied
and affirmed
part,
Affirmed in
modified
— Dallas
Justice,
upon by the
is in
Chief
accord
and rendered.
part,
part
and in
reversed
expressed
the views
in the Bradshaw and
It is so ordered.
cases cited
Statham
above.
Justice,
CLAYTON,
concurs.
Leger Drilling
We do
v.
Well
not consider
Control, Inc.,
1979),
opinion.
(5th
join
concurring
