In еarly April of 1995, David V. Bowden, Kevin Mathews, Mathews Home Builders, Inc., and Mathews Custom Homes, Inc. (Builders) finished construction of a house for which they did not yet have a buyer. On April 26, 1995, the Chatham County Building Inspections Department completed its inspection process аnd, in July, 1995, issued a certificate of occupancy. Builders then conveyed the property to David and Kimberly Hickey (Plaintiffs). After Plaintiffs discovered moisture damage under the house’s synthetic stucco cladding, they brought suit on April 26, 1999 against Builders and the manufacturer оf the synthetic stucco, Colormatch Exteriors, Inc. (Appellants). Plaintiffs asserted products liability claims as to Colormatch and, with respect to Builders, alleged negligent construe
tion, breach of warranty, and negligent misrepresentation. The trial court granted summary judgment in favor of Appellants on the ground that the applicable statutes of limitation had expired. The Court of Appeals reversed, concluding that the trial court should have applied the six-year limitation period for contract actions to the claim for breach of implied warranty, and that the four-year statute of limitations for damage to realty did not preclude the remaining tort, fraud, and products liability claims.
Hickey v. Bowden,
By its terms, the four-year time period established in OCGA § 9-3-30 (a) only began running when Plaintiffs’ rights of action in tort accrued. For statute of limitations purposes, the general rule for determining the time a cause of action accrues is well-settled in Georgia. “The true test to determine when a cause of action accrues is to ascertain the time when the plaintiff could first have maintained [his or] her action to a successful result. [Git.]”
Travis Pruitt & Assoc. v. Bowling,
Case Number S01G1063
2. Whatever the date of substantial completion, it occurred before title to the property was conveyed to the Plaintiffs. In the suit аgainst Builders, the issue is whether Plaintiffs’ rights of action nevertheless accrued upon substantial completion of the house even though Builders were still the owners of the property at that time. Travis Pruitt appropriately distinguishes cases involving “alleged negligent design and construction of the plaintiff’s own property. [Cits.]” Travis Pruitt & Assoc. v. Bowling, supra at 226 (1). If the owner contracts with a builder and intends to retain the improved property after completion of the project, he can maintain an action against the contractor immediately upon substantial completion of the allegedly negligent construction and, thus, there is no question that the statute of limitations begins to run at that time. In such a case, the plaintiff is the owner of the property at the time of substantial completion. Where, however, the contractor is a developer who still owns the property at the time of substantial completion, he obviously cannot maintain an action for negligent construction or misrepresentation against himself. If the nеw house was constructed by an owner-builder for the purpose of sale and the property actually is sold, then the only persons who are injured by any negligence of the builder and who can successfully maintain an action therefor are the рurchaser and his successors. With respect to Builders, this case is analogous to Travis Pruitt, where the plaintiff owned only the neighboring property and could not have successfully maintained an action until the adjoining defective property first caused damage to her own property. Thus, the statute only began to run on the tort claims against Builders on the date that Plaintiffs bought the property. They filed suit within that four-year period.
Various circumstances may delay the sale of property by a developer and cause a corresponding delay in the accrual of tort claims for damage to realty. However, the General Assembly has provided for such an eventuality by enacting statutes of ultimate repose. The purpose of these statutes “ ‘is to impose an outside limit on the bringing of lawsuits which are otherwise brought within the applicable statutory period after the action has accrued. [Cit.]’ ”
Armstrong v. Royal Lakes Assoc.,
supra at 645 (1). Statutes of repose apply “regardless of when the injury occurs or, indeed, whether a cause of action has accrued at all prior to the expiration of the period. [Cit.]”
Hanna v. McWilliams,
supra at 651 (3). OCGA § 9-3-51 establishes a reasonable outside time limit beyond which builders are insulated from liability. See
Gwinnett Place Assoc. v. Pharr Engineering,
Case Number S01G1036
3. Our analysis is entirely different with regard to Colormatch. Prior to selling the property to Plaintiffs, Builders were the owners of
the property and could have brought a products liability suit against Colormatch. See
Lamb v. Georgia-Pacific Corp.,
Because Colormatch is the manufacturer of only one component of the house, there
The Court of Appeals’ conclusion that a certificate of occupancy was a prerequisite to substantial completion is contrary to its own
precedent. In
Hanna v. McWilliams,
supra, the plaintiffs specifically contended that their house was substantially completed no earlier than the date when the certificate of occupancy was issued. The Court of Appeals implicitly rejected this contention by holding that the statute of repose on a fireplace improvement to real property began to run upon substantial completion of the fireplace.
Hanna v. McWilliams,
supra at 652 (3). In
Hall v. Harris,
4. Nothing in this opinion affects the holding of the Court of Appeals that the six-year limitation period applies to Plaintiffs’ claims for breach of implied warranty. See generally
Shadix v. Carroll County,
Judgment reversed in Case No. S01G1036. Judgment affirmed in Case No. S01G1063.
