OPINION
On February 28, 1983, appellant Colorado Environments, Inc., now known as Bilbray Industries (CEI), entered into a contract with respondent Valley Grading Corporation (Valley). Pursuant to the terms of the contract Valley was to construct certain on-site and off-site improvements, including two flood retention dams, in a proposed subdivision CEI was preparing to
Contrary to what CEI had indicated, work on the subdivision did not begin within two weeks. Public Works withheld its final approval of the subdivision plans when concerns arose over CEI’s proposed use of “earth-filled” or pervious core dams, rather than impervious core dams as CEI indicated in its initial flood control study. By early April, 1983, CEI decided to abandon the flood retention dam concept and opted for an armored drainage channel instead. On April 12, 1983, CEI and Valley executed a second contract in which Valley agreed to construct the drainage channel. The total price for the two contracts was $1,593,670.
In the interim between Spring and Fall of 1983, Valley bid and performed other projects with CEI’s approval. In September, 1983, CEI informed Valley that construction on the Laughlin subdivision would begin October 1, 1983. Thereafter, CEI again revised the commencement date to November 1, 1983. On October 24, 1983, Valley, apparently fearing yet another postponement, wrote to CEI and demanded that work commence within fifteen days, or that the contracts be cancelled and it receive 20 percent of the contract price as damages. CEI did not respond to the demand in writing, but, sometime after November 1, 1983, CEI’s president, Robert Bilbray, informed Valley that he was accepting bids from other contractors to perform the work. In a letter dated November 16, 1983, Valley expressed its continued willingness to perform the two contracts and characterized CEI’s “bid shopping” as unethical.
CEI again contacted Valley about performing the Laughlin contracts in April, 1984. The possibility of Valley performing the work ended, however, when Valley refused to reduce its contract price by $100,000 as Bilbray demanded. Valley brought the suit that is the subject of this appeal in mid-June, 1984. Thereafter, CEI awarded the construction contracts to another company who commenced work in December, 1984. Following trial on Valley’s breach of contract action, a jury found in Valley’s favor and awarded it compensatory damages in the amount of $1,035,600. The jury’s award included damages for lost profits ($521,449) and standby equipment or delay damages ($514,151). 1 This appeal ensued.
At trial, CEI contended, among other things, that governmental interference prevented it from performing its contracts with Valley and that its performance was contingent upon an implied condition, i. e., that governmental regulations or orders would not prevent its performance within a reasonable time. CEI therefore offered proposed jury Instruction No. 17. The proposed instruction provided: “An implied condition operates where parties enter into a ocntract [sic] on the assumption that some thing essential to its performance will occur.” The district court refused to give the proposed instruction because it believed that the concept of implied conditions was adequately covered in another instruction and that the proposed instruction would confuse the jury. CEI now contends that the district court erred in refusing to give proposed Jury Instruction No. 17. We disagree.
It is a party’s right to have the jury instructed on the theories of its case which are supported by the evidence. Beattie v. Thomas,
Performance of a contract may be subject to conditions and performance need not take place until the conditions are fulfilled. Such conditions may be express or implied. By the phrase “express condition” is meant a provision which is specifically agreed to by the parties either orally or in writing. By the term “implied condition” is meant a term or condition which is recognized by the parties to exist and to bind them in their action despite the fact that it is not expressly spelled out or agreed to by the parties. Such terms are often said to arise by implication from the terms which were expressly enumerated in the contract and agreed to or from practice with the industry or business within which the proposed contract performance would take place. Nonoccurrence of the condition, express or implied, excuses the parties from performing the contract, unless one of the parties is responsible for that nonoccurrence.
(Emphasis supplied.)
The message conveyed by the above emphasized language in Instruction No. 16 is essentially the same as that contained in CEI’s proposed instruction. Instruction No. 16 adequately informed the jury of the concept of implied conditions. There fore, the proposed instruction would have been redundant. Moreover, unlike the instruction that the district court gave, the proposed instruction did not fully inform the jury that performance is not excused when a party is responsible for the nonoccurrence of the condition. Thus, and as the district court believed, the proposed instruction could have confused the jury. Accordingly, we believe that the district court did not err in refusing to give proposed jury Instruction No. 17.
CEI also contends that the district court erred by giving Instruction No. 18 which provided:
A party to a contract may be relieved of his duty to perform under a contract, either temporarily or permanently, when the party’s performance is rendered impossible by unforeseen events or occurrences.
Under Nevada law, one who contracts to render a performance for which government approval is required has the duty of obtaining such approval and the risk of its refusal is on him. Where the requirement of government approval is foreseeable, and is not addressed in the contract, the failure to obtain such approval by the party seeking it does not justify the party’s breach of the agreement, or his failure to perform.
Moreover, where a government regulation does not prohibit performance, but only renders it more costly or difficult to perform, the defense of impossibility of performance does not apply.
Although CEI admits that the requirement of securing the permits to construct was foreseeable, it contends that the second paragraph of the instruction informed the jury that Public Works’ refusal to issue the necessary permits provided no excuse or justification for CEI’s failure to perform. Therefore, argues CEI, the instruction required the jury to reject CEI’s theory of defense. Again, we disagree.
Instruction No. 18, which was based on our decision in Nebaco, Inc. v. Riverview Realty,
CEI next argues that the evidentiary foundation for the jury’s award of “equipment leasing expense (or idle equipment downtime)” was inadequate as a matter of law. In CEI’s view, not only did Valley fail to establish the existence of a lease agreement and that Valley either paid for or was indebted on the leased equipment, Valley also failed to prove that the leased equipment was ever “up” on the job. Therefore, according to CEI, the jury’s damages award on this claim was improper.
At trial, Valley offered testimony that it entered into an oral agreement with Gilbert Development Corporation (Gilbert) to lease the heavy equipment necessary to perform the CEI contracts. Valley introduced into evidence invoices for the months of December, 1983, through February, 1984, that listed the equipment it leased and the cost thereof. The total lease expense for the three month period that Valley estimated it would take to complete the Laughlin project was $229,680. Further testimony established that both Valley and Gilbert recognized Valley’s indebtedness for the leased equipment.
In presenting its damage claim to the jury, Valley offered the testimony of an expert witness who opined that because of CEI’s breach Valley not only was entitled to lost profit damages in the amount of $521,449, it was also entitled to equipment standby or delay damages in the amount of $514,151. According to the expert, the latter damages compensated Valley for the time its leased equipment stood idle and could not be used. CEI presented its own expert who contended that awarding Valley equipment standby damages would constitute a double recovery. The jury, however, accepted the testimony of Valley’s expert and awarded Valley both lost profit and equipment standby damages.
We believe that Valley adequately established the evidentiary foundation necessary to support a claim for equipment leasing costs. The evidence Valley offered was sufficient to prove the existence of a binding oral lease agreement the terms of which the jury could have inferred from the invoices Valley offered into evidence. Moreover, both the testimony at trial and the invoices established Valley’s indebtedness for the leased equipment.
Cf.
Frank Horton & Co. v. Cook Electric Co.,
Subject to the limitations stated in §§ 350-53, the injured party has a right to damages based on his expectation interest as measured by (a) the loss in value to him of the other party’s performance caused by its failure or deficiency, plus (b) any other loss, including incidental or consequential loss, caused by the breach, less (c) any cost or other loss that he has avoided by not having to perform.
Id.
The actual expenses Valley incurred in leasing the heavy equipment to perform the contracts were not costs that Valley “avoided by not having to perform.”
See
Tull v. Gundersons, Inc.,
In contrast to equipment leasing costs, delay damages properly compensate a plaintiff for losses sustained as a result of
delays
attributable to the defendant. Equipment standby damages, a specific category of delay damages,
see
2 S. Stein, Construction Law, para. 11.02[2][a][ii] (1989), usually take the form of lost opportunities to rent idle equipment to others or the plaintiff’s inability to use the equipment at an earlier date on another job.
Cf.
L.L. Hall Construction Co. v. United States,
In most situations in which delay damages are awarded the defendant has caused the time of the plaintiff’s performance to be extended.
See
Zook Bros. Construction Company v. State,
Under the circumstances presented here, we conclude that the damages award in
We have carefully considered CEI’s remaining contentions and conclude that they are without merit. The district court’s judgment is affirmed as modified and the matter is remanded to that court for a redetermination of the amount of pre-judgment interest to which Valley is entitled.
Notes
Although the jury in returning its damage award did not specify the amounts it awarded for lost profit and equipment standby damages, its award coincided precisely with the damage analysis presented by Valley’s expert witness. See infra.
