COLORADO DEPARTMENT OF HIGHWAYS, Plaintiff-Appellee, Utah Department of Transportation, Intervenor-Plaintiff-Appellee, v. UNITED STATES DEPARTMENT OF TRANSPORTATION; James H. Burnley, IV, in his capacity as the Administrator of the Department of Transportation; Federal Highway Administration; Ray Barnhart, Administrator of FHWA; Morris Reinhardt, as Regional Administrator of FHWA, Defendants-Appellants.
No. 85-2572.
United States Court of Appeals, Tenth Circuit.
Feb. 24, 1988.
840 F.2d 753 | 56 USLW 2572
Christine R. Whittaker, Atty., Dept. of Justice, Washington, D.C. (Richard K. Willard, Asst. Atty. Gen., Robert N. Miller, U.S. Atty., Denver, Colo., and Leonard Schaitman, Atty., Dept. of Justice, Washington, D.C. with her on the brief), for defendants-appellants.
Before McKAY, McWILLIAMS and BALDOCK, Circuit Judges.
BALDOCK, Circuit Judge.
1 Plaintiffs-appellees Colorado Department of Highways (Colorado) and Utah Department of Transportation (Utah) challenged the accounting method which the defendant-appellant Federal Highway Administration (FHWA), an entity within the Department of Transportation, determined the states must use to calculate federal reimbursement for construction engineering costs under the Federal-Aid Highway Act (Highway Act).
2 The Highway Act provides two methods by which the federal government can reimburse a state for construction engineering costs. A state may request reimbursement of the actual amounts spent or it may use the optional method provided in
3 On October 25, 1983, Colorado filed a complaint in federal district court alleging that the FHWA‘s interpretation of the percentage allowable under the optional method was contrary to the Highway Act. Specifically, Colorado and Utah alleged that in utilizing the optional method, they should be allowed to compute the rate based upon actual construction engineering costs. The FHWA, however, maintains that the applicable rate must be based upon only reimbursable costs, i.e., those construction engineering costs that do not exceed the fifteen percent maximum allowable costs specified in
4 The government filed a motion to dismiss for lack of jurisdiction and, in the alternative, a motion for summary judgment. Colorado and Utah also moved for summary judgment. The district court denied the government‘s motion to dismiss. After oral argument on cross-motions for summary judgment, the court denied the government‘s motion for summary judgment and granted summary judgment for Colorado and Utah on the merits. After stipulation by the parties, the district court entered judgment for Colorado and Utah in the amount of $845,454.05 and $4,816,772.21, respectively.
5 The Department of Transportation appeals the judgment. First, it contends that the district court lacks subject matter jurisdiction over this claim pursuant to Fed.R.Civ.P. 12(b)(1) because the Tucker Act,
7 A party cannot avoid the exclusive jurisdiction of the Claims Court under the Tucker Act merely by artfully pleading injunctive, declaratory or mandatory relief when the purpose of the suit is to obtain money from the United States in excess of $10,000. Rogers v. Ink, 766 F.2d at 434; New Mexico v. Regan, 745 F.2d 1318, 1322 (10th Cir.1984), cert. denied, 471 U.S. 1065, 105 S.Ct. 2138, 85 L.Ed.2d 496 (1985). Nor may a plaintiff transform a claim for monetary relief into an equitable action simply by requesting injunctive relief that may result in the payment of money. Rogers v. Ink, 766 F.2d at 434 (holding that although plaintiffs’ first prayer seeks declaratory relief, the underlying purpose of the action was to obtain money from the United States); accord New Mexico v. Regan, 745 F.2d at 1322 (holding that State suit to recover federal royalties used to pay a windfall profits tax was within the exclusive jurisdiction of the Claims Court because the States’ declaratory relief request was “incidental and subordinate to the basic suit for money“); Amalgamated Sugar Co. v. Bergland, 664 F.2d at 824 (holding exclusive jurisdiction of the Claims Court even when plaintiff sought only a declaratory judgment because the actual controversy remaining after the equitable issues were settled concerned monetary relief). The fact that equitable remedies are inadequate, even where requested in the complaint, is one factor that courts may consider in determining whether the claim actually is one for money damages. See United States v. Mitchell, 463 U.S. at 227-28, 103 S.Ct. at 2973-74.
8 In the instant case, the three prongs of the Rogers test are met. First, the claim was brought against the United States. Second, the suit is based upon a government contract because the Highway Act, the substantive law underlying the action, specifically creates a contractual relationship between the federal government and the state once the Secretary approves the project:
[T]he State highway department shall submit to the Secretary for his approval, as soon as practicable after program approval, such surveys, plans, specifications, and estimates for each proposed project included in an approved program as the Secretary may require. The Secretary shall act upon such surveys, plans, specifications, and estimates as soon as practicable after the same have been submitted, and his approval of any such project shall be deemed a contractual obligation of the Federal Government for the payment of its proportional contribution thereto....
9
10 Appellees attempt to distinguish the cases in which Claims Court jurisdiction was held exclusive and to analogize the cases finding original or concurrent jurisdiction of the district court. The majority of these cases, however, either support appellant‘s argument for exclusive Claims Court jurisdiction, are factually distinguishable or are not helpful because the issue of Claims Court jurisdiction was not discussed. For instance, some cases cited did not involve Tucker Act jurisdiction because the action was not founded on the Constitution, a federal statute, an executive regulation, a government contract or a federal question. These cases are inapplicable because, here, the Highway Act creates a contractual relationship between the appellees and the United States. See, e.g., Maryland Dep‘t of Human Resources v. Department of Health and Human Services, 763 F.2d 1441, 1451 (D.C.Cir.1985) (Title XX found not to mandate compensation by the federal government); B.K. Instrument, Inc. v. United States, 715 F.2d 713, 727 (2d Cir.1983) (no Tucker Act jurisdiction because there was no underlying contract between the plaintiff and the government); Tennessee ex rel. Leech v. Dole, 749 F.2d 331, 335 (6th Cir.1984), cert. denied, 472 U.S. 1018, 105 S.Ct. 3480, 87 L.Ed.2d 615 (1985) (monetary relief based on restitution did not create a “contract-based claim” sufficient to render exclusive Claims Court jurisdiction under the Tucker Act).
11 Other cases cited by appellees either do not support their argument or, conversely, support the appellants’ argument. See, e.g., California ex rel. Dep‘t of Transp. v. Department of Transp., Federal Highway Admin., 561 F.2d 731 (9th Cir.1977) (Tucker Act jurisdiction not at issue); Laguna Hermosa Corp. v. Martin, 643 F.2d 1376, 1379 (9th Cir.1981) (no Claims Court jurisdiction because money damages not sought by plaintiff); Louisiana Dep‘t of Highways v. United States, 604 F.2d 1339 (Ct.Cl.1979) (additional contractual obligation accepted by Louisiana Department of Highways was not part of contract provisions and specifications approved by FHWA and thus FHWA was not contractually obligated to provide settlement funds).
12 The district court shall vacate the judgment and dismiss the complaints.
13 REVERSED.
