OPINION OF THE COURT
Petitioner Ten Mile River Holding, Ltd. (hereinafter TMR) is the owner of farm land in Dutchess County which had been mined by prior owners and operators in areas denominated as pit Nos. 1, 2 and 3. Respondent Department of Environmental Conservation (hereinafter DEC) granted TMR’s application in 1982 to mine sand and gravel based upon a negative declaration which found that TMR proposed to operate a sand and
In the meantime, petitioner Aldo Colella, acting as TMR’s manager, sought to change its mining plan and stated TMR’s intent to level and reclaim pit Nos. 1 and 2, using topsoil and other materials from pit No. 3. DEC approved the change and directed TMR to submit updated drawings and written plans as part of its renewal application. In January 1985, TMR entered into an agreement with petitioner M.A.C. Sand & Gravel, Inc. (hereinafter MAC) whereby TMR gave MAC the right to conduct mining operations under TMR’s permit. Colella is the sole stockholder and president of MAC.
In May 1985 Colella, acting on behalf of TMR, filed a renewal application with DEC. Thereafter a dispute arose as to the sufficiency of the application, and mining operations on TMR’s property ceased. Mining operations resumed in August 1987 although DEC had not granted a renewal of TMR’s permit. Respondent Commissioner of Environmental Conservation ordered TMR to cease mining in July 1988, but the determination was annulled by Supreme Court on the ground that TMR had submitted a timely application to renew and, therefore, was authorized to continue mining under State Administrative Procedure Act § 401 (2). DEC ultimately denied the renewal application and the Commissioner upheld the denial. TMR did not seek judicial review of the Commissioner’s determination.
In March 1991, DEC commenced the enforcement proceedings at issue herein based upon allegations that petitioners mined outside the permit areas, failed to maintain an adequate reclamation bond, abandoned certain parts of the mining operation, violated the terms of the 1982 permit, disturbed the banks of a stream without a permit, discharged pollutants into the stream without a permit and contravened State water quality standards. After a hearing petitioners were found guilty of the charges and a penalty of $1 million was assessed against petitioners jointly and severally. A penalty of $500,000 was assessed against TMR individually.
Petitioners contend that substantial evidence is lacking to support the determination of guilt of the various charges. Based upon our review of the record, we find the evidence
The finding that petitioners mined for at least 94 days outside the area allowed by the 1982 permit is supported by the testimony of DEC personnel concerning their observations at the site and a map prepared by a geologist in 1990 at TMR’s request. There is also evidence that in 1988 Colella and Jack Harbold, an employee of both TMR and Colella, were ticketed for operating mining equipment in the unpermitted floodplain area. Both tickets resulted in convictions against TMR. The number of days was determined on the basis of the volume of material removed from the unpermitted area, as determined from the geologist’s map and on-site observations by a DEC employee, and the average amount of material removed in a day by the method used by petitioners within the permitted area. There is no evidence in the record that anyone other than petitioners mined in the unpermitted area.
The finding that petitioners constructed an unauthorized haulage road is supported by undisputed evidence that a new haulage road into pit No. 3, which differed from the road on the plan approved by DEC, was constructed without DEC approval. That approval was obtained from other governmental agencies did not obviate the need for DEC approval (see, ECL 23-2713 [1] [a]; 23-2705 [4]; 6 NYCRR 422.2 [b] [4]).
The finding that TMR failed to post an adequate reclamation bond (see, ECL former 23-2717, renum 23-2715 and amended by L 1991, ch 166, § 232) is supported by evidence that TMR posted a $90,000 bond after its first letter of credit expired, while the area affected by the mining activity required a bond of at least $150,000. DEC requested in September 1990 that TMR post an additional bond in the amount of $104,200, which TMR failed to do. DEC later calculated the cost of reclamation to be at least $750,000.
The finding on the issue of reclamation is similarly supported by the record. ECL former 23-2715 required reclamation to be performed in accordance with the approved plan,
The determination found that ECL 71-1305 (3), which prohibits abandonment of a mine without DEC approval, had been violated as early as May 1982, despite the fact that DEC issued a permit in May 1982 and mining activity continued on the premises until May 1985 and resumed again in August 1987. Although the record supports the conclusion that areas of the mine where the mining operations had been completed were not reclaimed as required by the approved plan, there is no basis for finding a separate violation of ECL 71-1305 (3) for the same omission. Respondents note that all mining ceased at the premises from May 1985 to August 1987, but the finding
As to the finding that petitioners violated ECL 17-0501 and 17-0803, there is evidence in the record that a ditch was constructed at Colella’s direction in 1987 to divert water from the mining area in the vicinity of pit No. 3. Petitioners contend that the ditch did not go all of the way to the Ten Mile River, but there is testimony to the contrary and testimony that water diverted from the mine by the ditch discharged into the river, which is a class C(T) stream, having fishing as its best usage (see, 6 NYCRR 701.8). There is also testimony that the waters discharged into the river by the ditch were discolored with sediment and increased the turbidity and sediment in the river. DEC presented evidence that the discharge had an adverse impact on a major fishery. The absence of dead fish does not, as petitioners suggest, affect the credibility of this testimony.
The finding that petitioners disturbed the banks of the Ten Mile River is supported by testimony that construction of the drainage ditch involved the removal of sand and gravel from the river’s banks. There was also testimony of cuts in the bank line, that a swath or pathway had been constructed to allow drainage and that equipment was driven across the river.
Other than as previously discussed on the issue of abandonment, petitioners’ various challenges to the quality and quantity of the evidence relied upon by the Commissioner as the basis for his determination do not, in our view, establish that the requisite substantial evidence is lacking.
MAC and Colella raise a procedural issue, alleging bias on the part of the Administrative Law Judge, but the issue was not raised at the administrative level and was therefore waived (see, Matter of Kessel v Public Serv. Commn., 123 AD2d 203). In any event, there is no evidence of bias or that the outcome of the case resulted from the alleged bias (see, Matter of Hughes v Suffolk County Dept. of Civ. Serv., 74 NY2d 833). We also reject the claim of MAC and Colella that they were entitled to a jury trial.
As to the acts of omission concerning the failure to comply with the progressive reclamation requirements of the approved mined land use plan which included the requirement of sedimentation collection area and berms, we are of the view that MAC and Colella cannot be held responsible under the Mined Land Reclamation Law (ECL art 23, tit 27) as it existed while MAC operated the mine. The obligation to fulfill the requirements of the approved plan was imposed upon the "applicant” (ECL 23-2705 [former (2)]), not the operator (see, ECL 23-2705 [former (9)]). It is undisputed that TMR was the "applicant” and that neither MAC nor Colella was an "applicant”. They cannot, therefore, be subject to liability for the lack of compliance with the requirements imposed upon the "applicant” by the Mined Land Reclamation Law.
Although the determination includes calculations of the maximum possible fines for each violation, the penalty was imposed in lump sums of $1 million and $500,000, with no breakdown for each violation. We have previously rejected lump-sum penalties as insufficient to permit adequate judicial review (see, Matter of Eden Park Health Servs. v Whalen, 73 AD2d 993). Inasmuch as the matter must be remitted to the
Cardona, P. J., Mikoll, White and Yesawich Jr., JJ., concur.
Adjudged that the determination is modified, without costs, by annulling so much thereof as found an abandonment within the meaning of ECL 71-1305 (3) and found petitioners M.A.C. Sand and Gravel, Inc. and Aldo Colella responsible for the lack of compliance with the reclamation provisions of the approved mined land use plan; petitions granted to that extent and matters remitted to respondent Commissioner of Environmental Conservation for further proceedings not inconsistent with this Court’s decision; and, as so modified, confirmed.
